  1. Slide 1: NMDC Limited Investors / Analysts / Brokers Meet

    Slide 1: NMDC Limited Investors / Analysts / Brokers Meet

    Quarter – III performa nce review 2012-13 NMDC Limited Investors / Analysts / Brokers Meet 25th & 26th Feb 2013 Mumbai 1

  2. Slide 2: Performance Highlights Q3 FY 2012-13

    Slide 2: Performance Highlights Q3 FY 2012-13

    Quarter – III performa nce review 2012-13 Performance Highlights Q3 FY 2012-13 2

  3. Slide 3: Index of Presentation

    Slide 3: Index of Presentation

    Quarter – III performa nce review 2012-13 Index of Presentation  Performance Highlights  Status of Ongoing Projects  Joint Ventures & Subsidiaries  Personnel & HR  Awards & Accolades 3

  4. Slide 4: Performance (III Qtr 2012-13 vs III Qtr 2011-12)

    Slide 4: Performance (III Qtr 2012-13 vs III Qtr 2011-12)

    Quarter – III performa nce review 2012-13 PERFORMANCE (III Qtr of 2012-13 Vs III Qtr of 2011-12) • Iron Ore Production : 53.64 LT (PY 71.45 LT) 25% • Iron Ore Sales : 53.26 LT (PY 64.04 LT) 17% • Turnover : Rs 2048 Cr (PY Rs 2822 Cr) 27% • Profit before Tax : Rs 1914 Cr (PY Rs 2752 Cr) 30% • Profit

  5. Slide 5: Performance (Upto Dec12 vs Upto Dec'11)

    Slide 5: Performance (Upto Dec12 vs Upto Dec'11)

    Quarter – III performa nce review 2012-13 PERFORMANCE (Upto Dec12 Vs Upto Dec’11) • Iron Ore Production : 176.13 LT (PY 202.99 LT) 13% • Iron Ore Sales : 180.35 LT (PY 208.49 LT) 14% • Turnover : Rs 7500 Cr (PY Rs 8667 Cr) 13% • Profit before Tax : Rs 7220 Cr (PY Rs 8320 Cr) 13% • Profit after Tax :

  6. Slide 6: Physical Performance

    Slide 6: Physical Performance

    Quarter – III performa nce review 2012-13 PHYSICAL PERFORMANCE CURRENT YEAR PREVIOUS YEAR Inc/(Dec) PARTICULARS of 5 UPTO THE UPTO THE QTR I QTR II QTR III QTR III over 7 QUARTER QUARTER 1 2 3 4 5(2+3+4) 6 7 8 I. PRODUCTION: (a) Iron Ore (lwmt) : 68.72 53.77 53.64 176.13 71.45 202.99 (26.86) (b) Dia

  7. Slide 7: Unit Wise Physical Performance

    Slide 7: Unit Wise Physical Performance

    Quarter – III performa nce review 2012-13 UNIT WISE PHYSICAL PERFORMANCE (Qty in LMT) CURRENT YEAR PREVIOUS YEAR UPTO THE UPTO THE Inc/(Dec) of QTR I QTR II QTR III QUARTER QTR III QUARTER 5 over 7 1 2 3 4 5 6 7 8 PRODUCTION: Kirandul 17.83 12.17 14.72 44.72 22.28 73.00 (28.28) Bacheli 29.60 22.42 2

  8. Slide 8: Financial Performance

    Slide 8: Financial Performance

    Quarter – III performa nce review 2012-13 FINANCIAL PERFORMANCE (Rs. in (%) CURRENT YEARCrore) PREVIOUS YEAR Inc/(Dec) Inc/(Dec) PARTICULARS QTR III UPTO QTR III QTR III UPTO QTR III (3) over (5) (3) over (5) (1) (2) (3) (4) (5) (6) (7) a) Sales Revenue 2047.69 7500.02 2822.18 8667.31 (1167.29) (13.

  9. Slide 9: Physical Performance

    Slide 9: Physical Performance

    Quarter – III performa nce review 2012-13 PHYSICAL PERFORMANCE 2012-13 2011-12 PRODUCTION (LWMT) Upto Q1 Q2 Q3 Q1 Q2 Q3 Q4 2011-12 Dec’12 Lump 25.22 21.21 19.35 65.78 22.84 26.20 25.65 26.61 101.30 Fines 43.50 32.56 34.29 110.35 38.78 43.72 45.80 43.00 171.30 Total: 68.72 53.77 53.64 176.13 61.62 69

  10. Slide 10: Despatch Analysis

    Slide 10: Despatch Analysis

    Quarter – III performa nce review 2012-13 DESPATCH ANALYSIS QTY. IN LMT Despatch 2012-13 (Apr-Dec‘12) 2011-12 (Apr-Dec‘11) Bailadila Doni Total Bailadila Doni Total Rail 122.86 27.83 150.69 125.34 31.92 157.26 Road 4.80 27.33 32.13 7.35 5.50 12.85 Pipe Line - 0.00 - 36.57 0.00 36.57 Total 127.66 55.

  11. Slide 11: Selling Expenses

    Slide 11: Selling Expenses

    Quarter – III performa nce review 2012-13 SELLING EXPENSES Rs in crore Year to date Particulars Variance Remarks / Reasons 31-Dec-12 31-Dec-11 Railway Freight 232.63 41.32 191.31 Increase in export despatches by 7.51 LMT. Selling expenses 192.51 104.98 87.53 Due to increase in export qty by 3.46 LMT

  12. Slide 12: Details of Other Expenses

    Slide 12: Details of Other Expenses

    Quarter – III performa nce review 2012-13 Details of Other Expenses Rs in crore Year to date Particulars Variance Remarks / Reasons 31-Dec-12 31-Dec-11 1) Power & electricity 42.40 37.15 5.25 Increase in power charges Mainly on account of offloading of maintenance of 2) Repairs & Maintenance 42.58 3

  13. Slide 13: Capital Expenditure up to Q3 FY 2012-13

    Slide 13: Capital Expenditure up to Q3 FY 2012-13

    Quarter – III performa nce review 2012-13 CAPITAL EXPENDITURE (Up to IIIrd quarter ) in FY 2012-13 - Rs in Crore Projects/Schemes Actual Upto 3rd Qtr Bailadila 11B 19.98 Kumarswamy 76.23 3MTPA Steel Plant – CG 672.69 2 MTPA Steel Plant Karnataka 0.00 Pellet Plant- Doni. 140.17 Other Schemes 17.84 AM

  14. Slide 14: Iron Ore Sales

    Slide 14: Iron Ore Sales

    Quarter – III performa nce review 2012-13 Iron Ore Sales (Rs. in crores) 12000 11285.33 11167.56 11000 10000 9000 9000 8608.46 8000 7559.11 8000 7401.33 7000 6222.6 7000 6000 5705.32 6000 5000 4000 5000 3000 4000 2000 3000 1000 2000 2007- 2008- 2009- 2010- 2011- 1000 08 09 10 11 12 9M-FY12 9M-FY13 I

  15. Slide 15: Financial Performance PBT

    Slide 15: Financial Performance PBT

    Quarter – III performa nce review 2012-13 Financial Performance PBT (Rs. in crores) 11000 10759.47 10000 9727.17 9000 8320.230000 9000 00001 8000 8000 7219.81 7000 6648.23 7000 6000 6000 4947.47 5207.32 5000 5000 4000 4000 3000 3000 2000 2000 1000 2007- 2008- 2009- 2010- 2011- 1000 08 09 10 11 12 9M

  16. Slide 16: Financial Performance PAT

    Slide 16: Financial Performance PAT

    Quarter – III performa nce review 2012-13 Financial Performance PAT (Rs. in crores) 8000 9000 7265.39 7000 6499.22 6000 7000 5623.11 5000 4372.38 4877.42 4000 5000 3250.98 3447.26 3000 3000 2000 1000 1000 0 9M-FY12 9M-FY13 2007-08 2008-09 2009-10 2010-11 2011-12 PAT Performance for last 5 years 9M-F

  17. Slide 17: Annual Cash Profit

    Slide 17: Annual Cash Profit

    Quarter – III performa nce review 2012-13 Annual Cash Profit (Rs. In Crores) 12000 10945 Cash Profit Amount 9764 (Rs in Crores) 10000 12000 8000 10000 6572 8420 8000 7322 6000 5005 5264 6000 4000 4000 2000 2000 0 0 9M 2011-12 9M 2012-13 2007-08 2008-09 2009-10 2010-11 2011-12 17

  18. Slide 18: Net Worth

    Slide 18: Net Worth

    Quarter – III performa nce review 2012-13 30000 28355 28000 26000 24363 24000 22000 20000 18000 16000 14000 12000 10000 31.12.2011 31.12.2012 Rs. in crores Net Worth 18

  19. Slide 19: Dividend

    Slide 19: Dividend

    Quarter – III performa nce review 2012-13 Dividend (Rs. in crore) 1000 178.34 792.94 (200%) 1800 800 1600 130.77 1400 600 1200 396.47 (100%) 14.16 400 1605.78 1000 10.53 44.43 1177.58 800 200 862.04 600 649.39 0 641 400 1st Interim FY 2nd Interim FY 200 12-13 12-13 0 Interim Dividend declared in FY

  20. Slide 20: Earning per Share (EPS)

    Slide 20: Earning per Share (EPS)

    Quarter – III performa nce review 2012-13 Earning per Share (EPS) – in Rs. 20 18.33 18 16.39 16 16 14.18 14 14 12.30 12 11.03 12 10 10 8.69 8 8 6 6 4 4 2 2 0 0 2008-09 2009-10 2010-11 2011-12 9M-FY12 9M-FY13 Earning per share EPS for 9M FY 12-13 20

  21. Slide 21: Status of ongoing Projects

    Slide 21: Status of ongoing Projects

    Quarter – III performa nce review 2012-13 Status of ongoing Projects 21

  22. Slide 22: Upgradation of Evacuation Infrastructure

    Slide 22: Upgradation of Evacuation Infrastructure

    Quarter – III performa nce review 2012-13 a) Upgradation of Evacuation Infrastructure i) Uniflow Railway Line Uniflow Railway Line commissioned in May 2012. This augments evacuation capacity by 3 million tonnes. ii) Slurry Pipeline MoU signed with RINL for construction of Slurry Pipeline and setting

  23. Slide 23: Snapshots of Uniflow Railway Line

    Slide 23: Snapshots of Uniflow Railway Line

    Quarter – III performa nce review 2012-13 Snapshots of Uniflow Railway Line 23

  24. Slide 24: Snapshots of Uniflow Railway Line

    Slide 24: Snapshots of Uniflow Railway Line

    Quarter – III performa nce review 2012-13 Snapshots of Uniflow Railway Line 24

  25. Slide 25: Bailadila Deposit 11B

    Slide 25: Bailadila Deposit 11B

    Quarter – III performa nce review 2012-13 c. Bailadila Deposit 11 B  Location : Kirandul Complex, Dist. South Bastar Chhattisgarh  Capacity : 7.0 MTPA  Capital Outlay: Rs. 607.17 Cr  EPCM Consultant : M/s MECON, Bangalore  Project is being executed through Seven Packages  All the packages have

  26. Slide 26: Snapshots of Bailadila Deposit 11B

    Slide 26: Snapshots of Bailadila Deposit 11B

    Quarter – III performa nce review 2012-13 Snapshots of Bailadila Deposit 11 B 26

  27. Slide 27: Kumaraswamy Iron Ore Project

    Slide 27: Kumaraswamy Iron Ore Project

    Quarter – III performa nce review 2012-13 d) Kumaraswamy Iron Ore Project  Location : Donimalai, Dist. Bellary Karnataka  Capacity : 7.0 MTPA  Capital Outlay: Rs. 898.55 Cr  EPCM Consultant : M/s MECON, Bangalore  Project is being executed through Six Packages  Orders for four main packages ar

  28. Slide 28: Kumaraswamy Iron Ore Project

    Slide 28: Kumaraswamy Iron Ore Project

    Quarter – III performa nce review 2012-13 Kumaraswamy Iron Ore Project 28

  29. Slide 29: Donimalai Pellet Plant

    Slide 29: Donimalai Pellet Plant

    Quarter – III performa nce review 2012-13 e) Donimalai Pellet Plant  Location : Donimalai, Dist. Bellary Karnataka  Capacity : 1.2 MTPA  Capital Outlay: Rs. 572.00 Cr  EPCM Consultant : M/s M N Dastur & Co, Kolkata  Project is being executed through Six Packages  Orders for five packages are p

  30. Slide 30: Snapshots of Donimalai Pellet Plant

    Slide 30: Snapshots of Donimalai Pellet Plant

    Quarter – III performa nce review 2012-13 Snapshots of Donimalai Pellet Plant 30

  31. Slide 31: Quarter – III performa

    Slide 31: Quarter – III performa

    Quarter – III performa nce review 2012-13 31

  32. Slide 32: Integrated Steel Plant of 3.0 MTPA at Nagarnar

    Slide 32: Integrated Steel Plant of 3.0 MTPA at Nagarnar

    Quarter – III performa nce review 2012-13 f) Integrated Steel Plant of 3.0 MTPA capacity at Nagarnar, Jagdalpur in Chattisgarh State.  The Plant is being set up at an investment of Rs. 15525 crore.  About 2119 acres of land has been in possession of NMDC for the plant and other infrastructure faci

  33. Slide 33: Snapshots of 3.0 MTPA Integrated Steel Plant at Nagarnar

    Slide 33: Snapshots of 3.0 MTPA Integrated Steel Plant at Nagarnar

    Quarter – III performa nce review 2012-13 Snapshots of 3.0 MTPA Integrated Steel Plant at Nagarnar RMHS System BATTERY #1 - Precast Placement 33

  34. Slide 34: Snapshots of 3.0 MTPA Integrated Steel Plant at Nagarnar

    Slide 34: Snapshots of 3.0 MTPA Integrated Steel Plant at Nagarnar

    Quarter – III performa nce review 2012-13Snapshots of 3.0 MTPA Integrated Steel Plant at Nagarnar Scale Pit Under Excavation For Thin Slab Blast Furnace Foundation 34 Caster & Mills package

  35. Slide 35: Diversification into Coal

    Slide 35: Diversification into Coal

    Quarter – III performa nce review 2012-13 g) Diversification into Coal Shahpur East and Shahpur West Coal Blocks in M.P. allotted to NMDC under Government Dispensation Route for Commercial Mining and detailed exploration done through MECL under MoU. Mining Plan MoC approved the Mining Plan including

  36. Slide 36: Coal Blocks: Land, Environment Clearance, DPR

    Slide 36: Coal Blocks: Land, Environment Clearance, DPR

    Quarter – III performa nce review 2012-13 Land Acquisition Applications for Land acquisition for both the coal blocks have been submitted to concerned district Collectors. Environment Clearance MOEF issued revised Terms of Reference letter (TOR) on 10.01.2013 with validity date 27.10.2013. Draft EIA

  37. Slide 37: Capacity of existing mines in Bailadila sector after expansion by 2014-15

    Slide 37: Capacity of existing mines in Bailadila sector after expansion by 2014-15

    Quarter – III performa nce review 2012-13 Capacity of existing mines in Bailadila sector after expansion by 2014-15  Kirandul Complex Bacheli Complex  Deposit – 14 : 5 MTPA Deposit – 5 : 10 MTPA  Deposit – 11C : 7 MTPA Deposit – 10&11A :7 MTPA  Deposit – 11B : 7 MTPA Total : 17 MTPA  Total : 19

  38. Slide 38: Joint Ventures and Subsidiaries

    Slide 38: Joint Ventures and Subsidiaries

    Quarter – III performa nce review 2012-13 Joint Ventures and Subsidiaries Stake Name of the held Partner Purpose Company by NMDC J&KMDC Ltd. JKML 74% Setting up of Magnesite Project in the State of Jammu NMDC-CMDC Ltd. CMDC 51% Development of Iron Ore Deposit Nos.13 & 4 at Bailadila. NMDC Power Ltd.

  39. Slide 39: Joint Ventures and Subsidiaries (Contd…)

    Slide 39: Joint Ventures and Subsidiaries (Contd…)

    Quarter – III performa nce review 2012-13 Joint Ventures and Subsidiaries (Contd…) Stake held Name of the Partner by Purpose Company NMD C Kopano-NMDC Kopano 50% To acquire and develop mineral Mineral Pty. Ltd., Logistic prospects for steel making raw Johannesburg Services (Pty.) material such as Ir

  40. Slide 40: Analysis of Manpower Position

    Slide 40: Analysis of Manpower Position

    Quarter – III performa nce review 2012-13 Analysis of Manpower Position (in Nos.) 6200 6128 6100 6000 5924 5895 5900 5800 5700 5652 5600 5500 5400 2009 2010 2011 2012 Number of Employees as on 31.01.2013 - 5811 40

  41. Slide 41: Analysis of Employee Cost

    Slide 41: Analysis of Employee Cost

    Quarter – III performa nce review 2012-13 Analysis of Employee Cost (Rs. in crores) 600 500 529.10 491.05 418.46 500 400 392.88 421.1 419.51 400 300 300 200 200 100 9M-FY12 9M-FY13 100 9M FY 12-13 2009 2010 2011 2012 41

  42. Slide 42: Analysis of Employee Cost

    Slide 42: Analysis of Employee Cost

    Quarter – III performa nce review 2012-13 ANALYSIS OF EMPLOYEE COST Rs in Crore Year to date Particulars Variance Remarks / Reasons 31-Dec-12 31-Dec-11 Prov. for Wage Revision of Salaries, Wages & Bonus 298.12 274.19 23.93 workmen Rs. 25.72 Cr Contribution to Staff PF,EPF & DLI 22.24 19.27 2.97 Cont

  43. Slide 43: Value added per employee

    Slide 43: Value added per employee

    Quarter – III performa nce review 2012-13 Value added per employee (Rs. in lakhs) 180 167.10 159.05 160 140 122.75 120 94.72 93.58 100 67.12 80 60 40 20 0 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 43

  44. Slide 44: CSR Activities

    Slide 44: CSR Activities

    Quarter – III performa nce review 2012-13 CSR Activities NMDC has identified 6 major thrust areas of CSR:- a) Infrastructure b) Drinking Water c) Health d) Education e) Training f) Employment 44

  45. Slide 45: Mile stones & Accolades

    Slide 45: Mile stones & Accolades

    Quarter – III performa nce review 2012-13 Mile stones & Accolades • Signing of MoU with Govt. since 1991-92. • Excellent performer in MoU ratings in almost all the years. • PSE Excellence Award as Company of the Year in Navratna category • Indira Gandhi Rajbasha shield for 13 times. • ‘Star PSU of t

  46. Slide 46: Disclaimer

    Slide 46: Disclaimer

    Quarter – III performa nce review 2012-13 Disclaimer Cautionary Statement The statements contained in the Presentation may be forward looking statements and progressive within the meaning of applicable laws and regulations. Actual results may vary from those expressed or implied, depending upon econ

  47. Slide 47: Thank You

    Slide 47: Thank You

    Quarter – III performa nce review 2012-13 THANK YOU 47