  1. Slide 1: Davyhurst Project Site Visit

    For personal use only Davyhurst Project Site Visit ORABANDAMINING.COM.AU March 2025 ORABANDAMINING.COM.AU ASX OBM

  2. Slide 2: Forward looking statements

    Forward looking statements IMPORTANT NOTICE AND DISCLAIMER This Presentation dated 7 March 2025 contains summary information about Ora Banda Mining Ltd ABN 69 100 038 266 (Ora Banda Mining or the Company) and its activities based on information available at the time of preparing the Presentation. Th

  3. Slide 3: Riverina Underground Gold Mine

    For personal use only Riverina Underground ORABANDAMINING.COM.AU Gold Mine March 2025 ORABANDAMINING.COM.AU ASX OBM

  4. Slide 4: Riverina Underground Summary of Operation

    Riverina Underground Summary of Operation For personal use only • Narrow Vein → Long Hole Open Stoping → Top Down • Riverina Decline → 1.5km developed to date → current at 2170 RL → 2165 Level to commence mid-March • North Decline → 800m developed to date → currently at 2250 RL → 2256 Level commence

  5. Slide 5: Riverina Underground Geology

    Riverina Underground Geology Lithology For personal use only • Stratigraphy: The regional geology is characterized by an interbedded sequence of pillow basalts, ultramafics and carbonaceous and sulphidic interflow sediments, overlying a basal ultramafic unit. The sequence is crosscut by a series of

  6. Slide 6: Riverina Underground Geology: The Ore System

    Riverina Underground Geology The Ore System For personal use only • Gold Hosting Shear/Mylonite Zones: The gold deposits in the area are hosted within three separate shear/mylonite zones, namely Reggie’s, Murchison, and Main Lode, all trending approximately north-south. The main endowment is located

  7. Slide 7: Where We Have Come From – Block Model Updates

    Riverina Underground Geology Where We Have Come From – Block Model Updates For personal use only • The more we drill, the more we find • MW4 – much higher grades and volumes ORABANDAMINING.COM.AU • C12/13 – further drilling has identified numerous localised HG pockets – additional mining opportuniti

  8. Slide 8: Maximising value – Increasing OVM

    Riverina Underground Geology Maximising value – Increasing OVM 2215 Level Zambezi Fault For personal use only MW1 ME1 MW4 C09 C12/15 2195 DDDN ORABANDAMINING.COM.AU • Shift in GC drill focus from Main 2295 Level lodes only to wholistic mine corridor programs paying off with additional ore drives and

  9. Slide 9: Growth mindset – Planned Res Def Drilling for remainder of FY25

    Riverina Underground Geology Growth mindset – Planned Res Def Drilling for remainder of FY25 For personal use only • Development of two key drill drives nearing completion in Q3. • By EOFY 25 over 90% of existing LOM expected to be converted • Significant growth expected from un- tested “sharkbite”

  10. Slide 10: Growth mindset – Recent Res Dev Drilling

    Riverina Underground Geology Growth mindset – Recent Res Dev Drilling For personal use only ORABANDAMINING.COM.AU 10

  11. Slide 11: Riverina Underground Geotech: Ground conditions

    Riverina Underground Geotech Ground conditions For personal use only Six main geotechnical domains are identified at Riverina: 1. Basalts and sediments - make up the majority of development 2. Main ore lodes 3. Area between the main lodes 4. Water bearing structures / areas 5. Ultramafic rock ORABAN

  12. Slide 12: Evolution of the Ore Body & Execution of the Plan

    Riverina Underground Operations Evolution of the Ore Body & Execution of the Plan For personal use only 2295 2275 2295 2255 2235 2275 2215 2255 2235 2215 ORABANDAMINING.COM.AU 2255 Level – Stacked Lodes of Main and Murchison 12

  13. Slide 13: Driving Growth in the North

    Riverina Underground Operations Driving Growth in the North For personal use only • Whilst the Riverina South (RVS) mining zone has accelerated, a measured approach has been required in the North (RVN) in order to gain an understanding of the ore body. • Advantages of lagging decline: • Maximise RVS

  14. Slide 14: Capital Projects Planned FY25 Q3/Q4

    Riverina Underground Operations Capital Projects Planned FY25 Q3/Q4 Primary Fan Upgrade For personal use only Ventilation Control ORABANDAMINING.COM.AU Underground Pump Station & Rising Main Underground Telemetry & Fan Control 14

  15. Slide 15: Production Performance

    Riverina Underground Operations Production Performance • Surface tele hut → Increase in productivity For personal use only • Stope recons demonstrating high recovery and low overbreak • Multiple QA QC processes to ensure high quality plans and execution • Ongoing D&B improvements → optimising design

  16. Slide 16: Development Performance

    Riverina Underground Operations Development Performance For personal use only • Independent firing → Reduce cycle times and improve Decline development rate • Multiple ore drives per level → reduced capital outlay per ounce recovered • Multi-use drives (RAD/ESC/OD/SPL) → reduce required excavations

  17. Slide 17: Today's Visit

    Riverina Underground Operations Today’s Visit For personal use only ORABANDAMINING.COM.AU 17

  18. Slide 18: Today's Visit

    Riverina Underground Operations Today’s Visit For personal use only ORABANDAMINING.COM.AU 18

  19. Slide 19: Today's Visit

    Riverina Underground Operations Today’s Visit For personal use only ORABANDAMINING.COM.AU 19

  20. Slide 20: Today's Visit

    Riverina Underground Operations Today’s Visit For personal use only ORABANDAMINING.COM.AU 20

  21. Slide 21: Sand King Geology

    For personal use only Sand King ORABANDAMINING.COM.AU Geology Step 2 in OBM’s Drive to 150 ORABANDAMINING.COM.AU ASX OBM

  22. Slide 22: Where are we?

    Where are we? • Welcome to Siberia, of which Sand King is just but one For personal use only slice of the pie • 38km from Davyhurst Mill, 87km to Kalgoorlie • Historical mining district with multiple old open pits with mineralization open at depth • 36km from Davyhurst camp, 25 minute commute for FI

  23. Slide 23: Sand King's OBM Story

    Sand King’s OBM Story For personal use only • Historically modelled as a large open pit deposit • Timeline to UG was very fast: • First diamond hole targeting UG in October 2023 hit 14.3m @ 8.3g/t and showed “stacked lode” potential; 33 hole drill program commenced • Small cutback in open pit comple

  24. Slide 24: Siberia Geology

    Siberia Geology For personal use only • Gold Mineralisation is hosted in a series of high- grade conjugate (30 degrees offset to one another) tension veins, overprinting older shear zones which host sub economic gold grades and local high grade endowments ORABANDAMINING.COM.AU • Sits in a basalt suc

  25. Slide 25: What really is it?

    What really is it? For personal use only • Part of a dextral shear zone compromising multiple stacked lodes • Core of the deposit is as dilational jog, with multiple 090 structures sympathetic to the 060 shear zone. ORABANDAMINING.COM.AU • 060 (north south mine grid) and 090 (N30E mine grid) are vis

  26. Slide 26: (North South Mine Grid) Structures

    26 ORABANDAMINING.COM.AU For personal use only 060 (North South Mine Grid) Structures

  27. Slide 27: Structures

    27 ORABANDAMINING.COM.AU For personal use only 090 Structures

  28. Slide 28: Sand King Resource

    Sand King Resource Open in every direction, have we just started to uncover an elephant? For personal use only ORABANDAMINING.COM.AU 28

  29. Slide 29: Sand King Resource vs latest GC model

    Sand King Resource vs latest GC model For personal use only ORABANDAMINING.COM.AU Resource model grade shells – long section looking west Grade control model grade shells - long section looking west 29

  30. Slide 30: Sand King Resource vs latest GC model

    Sand King Resource vs latest GC model For personal use only ORABANDAMINING.COM.AU Resource model grade shells – plan view of 4315 level Grade control model grade shells – plan view of 4315 level 30

  31. Slide 31: Further upside: Blowouts or Knuckles

    Further upside “Blowouts” or “Knuckles” • Structural intersections create localised ‘blowouts’ For personal use only • Underrepresented in MRE – Difficult to model with wide (resource) spaced drilling • We know they are there from mining them in the pit! • First one UG (previously unknown) already i

  32. Slide 32: Geology: Blowouts or Knuckles

    Geology “Blowouts” or “Knuckles” For personal use only 14m “Blowout” ORABANDAMINING.COM.AU Length m2 Depth Volume Tonnes Grade Ounces Blow-Out 50 780 60 46,800 132,444 5 21,291 060 50 200 60 12,000 33,960 4 4,367 *Down plunge extent (Depth) is assumed 32

  33. Slide 33: How we operate

    How we operate Detailed geology paired with dynamic data assessment and integration For personal use only 14m “Blowout” ORABANDAMINING.COM.AU 33

  34. Slide 34: How we operate

    How we operate Detailed geology paired with dynamic data assessment and integration For personal use only 14m “Blowout” ORABANDAMINING.COM.AU 34

  35. Slide 35: How we operate

    How we operate Detailed geology paired with dynamic data assessment and integration For personal use only 14m “Blowout” ORABANDAMINING.COM.AU 35

  36. Slide 36: How we operate

    How we operate Detailed geology paired with dynamic data assessment and integration For personal use only 14m “Blowout” ORABANDAMINING.COM.AU 36

  37. Slide 37: Siberia (not just about Sand King): Opportunities and Re-cap

    Siberia (not just about Sand King) Opportunities and Re-cap For personal use only • Close to key infrastructure in a regional mining hub – Remember, Claremont of the goldfields • Open along strike and down dip. Potential for considerable growth in resource • Competent and homogenous ground for effic

  38. Slide 38: Siberia Operations: Sand King Underground

    For personal use only Siberia Operations ORABANDAMINING.COM.AU Sand King Underground Overview of Ora Banda Mining’s Second Underground Mine ORABANDAMINING.COM.AU ASX OBM

  39. Slide 39: Sand King Underground Project Set-up

    Sand King Underground Project Set-up For personal use only Primary Ventilation Circuit Escapeway operational for stoping ORABANDAMINING.COM.AU Commissioned 4337 Level Substation 39

  40. Slide 40: Sand King Underground Project Set-up

    Sand King Underground Project Set-up For personal use only Surface Power Station Core Shed and Wash Pad Updated Surface Admin and Workshop Area ORABANDAMINING.COM.AU Mine Water Infrastructure Surface Explosives Compound 40

  41. Slide 41: Sand King Underground Development

    Sand King Underground Development For personal use only • 2,031m developed since the start of the project (Start of March 2025) • 2 x jumbo’s utilised at Sand King Underground • Development rates forecasted to increase ORABANDAMINING.COM.AU with the 2nd production level already active (S4291) and a

  42. Slide 42: Sand King Underground Development

    Sand King Underground Development For personal use only • Ground condition at Sand King is classified ‘Good’ (NGI Q-System) with a tight range between the 25th and 75th percentile i.e. consistent good quality ground is expected across the ORABANDAMINING.COM.AU project. 42

  43. Slide 43: Sand King Underground Production

    Sand King Underground Production For personal use only • Production drilling commenced in late February 2025 • 76mm production holes with a floating boom production drill rig • Slots designed to be drilling with a Rhino Rig ORABANDAMINING.COM.AU with a 760mm rise supported then by a 2m x 2m box patt

  44. Slide 44: Sand King Underground Production

    Sand King Underground Production For personal use only FY25 production from the 4315 Level ORABANDAMINING.COM.AU FY25 production from the 4291 Level 44

  45. Slide 45: Long live the King

    Sand King Underground Long live the King For personal use only ORABANDAMINING.COM.AU We are only just getting started on this deposit… 45

  46. Slide 46: Davyhurst Project Exploration Summary

    For personal use only Davyhurst Project Exploration Summary ORABANDAMINING.COM.AU ORABANDAMINING.COM.AU ASX OBM

  47. Slide 47: Overview Map: major mineralised trends

    Overview Map 7 major mineralised trends that are substantially under-explored (especially at depth) For personal use only 1. RIVERINA 2. MULLINE 3. DAVY CENTRAL - WAIHI 4. ROUND DAM 5. CALLION 7. PYTHON TREND ORABANDAMINING.COM.AU 6. SIBERIA 47

  48. Slide 48: Focus on Understanding Geology

    Focus on Understanding Geology For personal use only • OBM believes the key to discovery is to first have a good understanding of the geology • The exploration team has pursued this belief in each of our project areas with a strong focus on: • re-assessing historical data with fresh ideas, ORABANDAM

  49. Slide 49: 1. Riverina

    49 ORABANDAMINING.COM.AU For personal use only 1. Riverina 1. RIVERINA

  50. Slide 50: New Geological Understanding = New Exploration Model

    New Geological Understanding = New Exploration Model For personal use only ORABANDAMINING.COM.AU Historical Exploration Model New Exploration Model Detailed mapping leads to new regional geology interpretation 50

  51. Slide 51: New Model = New Ideas to Test

    New Model = New Ideas to Test For personal use only • Riverina – Sunraysia Shear System • 7.5km strike length, open to south • Contains Little Gem prospect • Riverina – Forehand – Silver Tongue area • New tension vein model ORABANDAMINING.COM.AU • High potential for resource extensions • Eastern She

  52. Slide 52: First Test of the New Model

    First Test of the New Model For personal use only • Better understanding of the geology led to confidence in new generation targets • Application for EIS co-funded drilling – GRANTED • Two holes drilled: ACE • Little Gem target – Riverina to Sunraysia shear system • Ace target – Au-Cu associated wit

  53. Slide 53: The Little Gem Story: First hole = Immediate Success

    The Little Gem Story For personal use only First hole = Immediate Success • Three significant high-grade gold zones were intersected in LGDD24001 (@ 1g/t lower cut): • 5.27m @ 3.26g/t Au 180m VERTICAL • Inc. 0.77m @ 10.77g/t Au • 4.55m @ 7.37g/t Au • Inc. 1.55m @ 12.59g/t Au • 4.40m @ 3.43g/t Au ORA

  54. Slide 54: The Little Gem Story: Host to High-Grade Mineralisation

    The Little Gem Story For personal use only HOST TO HIGH–GRADE MINERALISATION • Highly visible white carbonate host to high- grade mineralisation (visually distinct from country rock) • Consistent high-grade throughout host carbonate • 4.55m @ 7.37 g/t Au ORABANDAMINING.COM.AU 54

  55. Slide 55: The Little Gem Story

    The Little Gem Story For personal use only • Recognition that Little Gem host was the same as the host at Sunraysia deposit (4km south) LGDD24001 ORABANDAMINING.COM.AU 55

  56. Slide 56: The Little Gem Story: Current state of play

    The Little Gem Story Current state of play: For personal use only 1. Awaiting assay results from holes LGDD25001 – 5 2. Re-assessing / re-interpreting geology at Sunraysia – same host and style of mineralisation to Little Gem 3. Additional drilling planned once assays received ORABANDAMINING.COM.AU

  57. Slide 57: 2. Mulline

    57 ORABANDAMINING.COM.AU For personal use only 2. Mulline 2. MULLINE

  58. Slide 58: Mulline Trend Historical Production

    Mulline Trend For personal use only Historical Production Prospect Tonnes Grade Oz Lady Gladys 1,913,500 3.1 189,700 Mulline Rose 178,000 2.6 14,800 Laterite Pits 487,000 1.2 19,200 Historical 9,300 43.3 13,000 Mines ORABANDAMINING.COM.AU SECTION SECTION TOTAL 236,700 Current Resource TOTAL 2,050,00

  59. Slide 59: Mulline Trend

    Mulline Trend Dedicated resources allocated to Mulline to unpack from the ground down For personal use only ORABANDAMINING.COM.AU 59

  60. Slide 60: 3. Davy Central - Waihi

    60 ORABANDAMINING.COM.AU For personal use only 3. Davy Central 3. DAVY CENTRAL - WAIHI

  61. Slide 61: Waihi – Golden Pole

    61 ORABANDAMINING.COM.AU For personal use only Waihi – Golden Pole

  62. Slide 62: Waihi – Homeward Bound Sections

    62 ORABANDAMINING.COM.AU For personal use only Waihi – Homeward Bound Sections

  63. Slide 63: Waihi Main Lode Long Section

    63 ORABANDAMINING.COM.AU For personal use only Waihi Main Lode Long Section

  64. Slide 64: 4. Round Dam Trend

    64 ORABANDAMINING.COM.AU For personal use only 4. ROUND DAM 4. Round Dam Trend

  65. Slide 65: Round Dam Trend: Walhalla – Federal Flag Mineralisation model

    Round Dam Trend Walhalla – Federal Flag Mineralisation model For personal use only ORABANDAMINING.COM.AU 65 Schematic 3D model showing dominant gold lodes relative to simplified lithological sequence

  66. Slide 66: Round Dam Trend Growth Opportunity

    Round Dam Trend Growth Opportunity For personal use only • Significant opportunity to materially increase resource base in short timeframe • Shallow open-pit targets = relatively cheap discovery cost • Any discovered resource provides backup mill feed • RC drilling started in February to test ORABAN

  67. Slide 67: Callion, Siberia & Python

    Callion, Siberia & Python More potential at 3 other major trends For personal use only Callion • Significant early stage work ongoing to upgrade regional model and further test drill targets Siberia 5. CALLION • 18km of strike that is largely 7. PYTHON TREND ORABANDAMINING.COM.AU 6. SIBERIA untested

  68. Slide 68: Processing Department

    For personal use only Processing Department ORABANDAMINING.COM.AU ORABANDAMINING.COM.AU ASX OBM

  69. Slide 69: Overview – Davyhurst Processing Plant

    Overview – Davyhurst Processing Plant For personal use only • Conventional goldfields plant • Three (3) stage crush to nominal f80 – 10mm. • Grinding circuit with gravity concentrator – 2 x 1.3MW Primary and Secondary Mills. • Leach and adsorption circuit through to tailing thickener. ORABANDAMINING

  70. Slide 70: Practices and Performance

    Practices and Performance For personal use only • A historically neglected asset – poor availability, high staff turnover, low skill sets. • Company committed significant resources and funds to improve performance → now getting the benefit • OBM engaged Prescient Asset Management to provide assistan

  71. Slide 71: Major Projects: Crushing Automation

    Major Projects Crushing Automation For personal use only • Historically, crushing circuit under performance due to electromechanical availability and operational practices. • Significant work undertaken to improve availability, however continued exposure regarding circuit operation occurred. • Keys

  72. Slide 72: Major Projects: EEPL Installation

    Major Projects EEPL Installation For personal use only • Davyhurst plant designed to operate at 150tph at a work index (WI) of 13.5kWhr/t – predominately OP oxide/transitional ore. • Current WI from UG operations is 18.0kWhr/t → to achieve required throughput required upgrades to existing mill confi

  73. Slide 73: Davyhurst Processing – Going forward

    Davyhurst Processing – Going forward For personal use only • Now a solid asset that is performing well • Major works are completed • Focus remains on continued improvements for long term success including: • Continued de-bottlenecking of the front end – Three stage crushing and milling circuit will

  74. Slide 74: Our Purpose, Vision

    For personal use only Our Purpose Ore-some Rocks, Awesome People – Our why Exploring, Developing and Delivering Vision Creating unparalleled growth, sustainably – Our aspiration Building the next mid tier miner ORABANDAMINING.COM.AU March 2025 74

  75. Slide 75: Values | How we operate

    Values | How we operate Winning is all about the people For personal use only ORABANDAMINING.COM.AU 75 75

  76. Slide 76: Appendix

    ORABANDAMINING.COM.AU For personal use only Appendix ORABANDAMINING.COM.AU 76

  77. Slide 77: Mineral Resource Estimate Statement

    Mineral Resource Estimate Statement1 MEASURED INDICATED INFERRED TOTAL MATERIAL PROJECT ('000t) (g/t Au) ('000t) (g/t Au) ('000t) (g/t Au) ('000t) (g/t Au) ('000oz.) LIGHTS OF ISRAEL - - 74 4.3 180 4.2 254 4.2 34 MAKAI SHOOT - - 1,985 2.0 153 1.7 2,138 2.0 136 For personal use only WAIHI Open Pit -

  78. Slide 78: Ore Reserve Statement

    Ore Reserve Statement1 For personal use only DAVYHURST GOLD PROJECT ORE RESERVE BY DEPOSIT Notes: 1. The table contains rounding adjustments to reflect accuracy and may not total exactly. PROJECT AREA PROVED PROBABLE TOTAL MATERIAL 2. This Ore Reserve was estimated from practical mining envelopes an

  79. Slide 79: ASX Listing Rule 5.23 Statements

    ASX Listing Rule 5.23 Statements Mineral Resources and Reserves For personal use only The information in this Presentation that relates to Mineral Resources and Ore Reserves Exploration Results (Continued) has been extracted from the Company’s ASX release, ‘Annual Mineral Resource and Ore Reserve St

  80. Slide 80: Contact details

    Contact details LUKE CREAGH For personal use only Managing Director +61 8 6365 4548 admin@obmltd.com.au ORABANDAMINING.COM.AU ORABANDAMINING.COM.AU 80