Slide 1: Investor presentation – Europe's next iron ore producer
Investor presentation – Europe’s next iron ore producer March 2014 1
Slide 2: Disclaimer
Disclaimer This document has been produced by Nordic Iron Ore AB (publ) (the “Company”) . The Company is planning to make an offering of shares in the Company by way of a private placement. This document does not constitute or form part of, and should not be construed as, an offer for sale or subscr
Slide 3: Agenda
Agenda Introduction Investment highlights Project time development Financial information 3
Slide 4: What defines a good iron ore project?
What defines a good iron ore project? Access to railway direct to deep sea port Easily beneficiated ore Large iron resources Low operating costs – Around 50 USD/dmt 62% Fe, FOB Low capital intensity – <150 USD/annual tonne production, 62% Fe Scaleability 4
Slide 5: Nordic Iron Ore at a glance
Nordic Iron Ore at a glance Restarting Ludvika Mines – Blötberget – concession granted – Väsman field – under further exploration – Håksberg – concession granted A brownfield iron ore project Existing rail from mine to deep water port Environmental permit expected shortly Scoping study sho
Slide 6: Project Update: Major Achievements 2013
Nordic Iron Ore - Project Up date Major Achievements 2013 New Scoping study Ludvika Mines - double production capacity Definite Feasibility Study - Phase 1 Blötberget commenced State Investment Fund - Inlandsinnovation new financier Increase in mineral resources + 280% LoI Oxelösund Port –
Slide 7: Our targets
Our targets Production 4.3 Mtpa Production start coarse fines: Q4 2015 Commissioning new beneficiation plant Q4 2016 Concentrate 67% Fe or better 7
Slide 8: Solid economics
Solid economics IRR 23 % (unleveraged) Pay back period 5.5 years At least 15 year life of mine 8
Slide 9: Agenda – Investment highlights
Agenda Introduction Investment highlights Project time development Financial information 9
Slide 10: One of Sweden's largest mineralisations
One of Sweden’s largest mineralisations Håksberg: Indicated 25 mt @ 36% Inferred 12 mt @ 36% Väsmans syd mineralisation: Indicated 7 mt @ 39% Inferred 86 mt @ 38% Blötberget : Indicated 30 mt @ 45% Inferred 10 mt @ 43% 10
Slide 11: One of Sweden's largest iron mineralisations
One of Sweden’s largest iron mineralisations Håksberg: 3 Indicated 25 Mt @ 36% Inferred 12 Mt @ 36% Väsmans South mineralisation: Indicated 7 Mt @ 39% Inferred 86 Mt @ 38% Blötberget *: Measured 11 Mt @ 35% Indicated 27 Mt @ 45% Inferred 21 Mt @ 33% * Preliminary technical report (JORC) 11
Slide 12: Expansion potential
Expansion potential 75000 MagTot (nt) 65000 55000 Targeting mineral resources in excess of 300mt N S 12
Slide 13: Beneficiation plant next to existing railway
Beneficiation plant next to existing railway 13
Slide 14: Integrated scaleable project
Integrated scaleable project Development in three phases 14
Slide 15: Product price premium
Product price premium High quality product 67% Fe Concentrate 15
Slide 16: High quality product
High quality product NIO will produce high quality pellet fines (possibility to produce sinter fines), expected to Comparison of average % Fe yield premium pricing 80 % 70 % 60 % 50 % 40 % 30 % 20 % 10 % 0% Resources Fortescue Dannemora (fines) Kumba Cleveland Cliffs BHP Northern Iron Vale Dannemora
Slide 17: Competitive cost level
Competitive cost level Competitive cash cost and premium product USD 76/dmt /NIO 17
Slide 18: Low development risk
Low development risk Existing logistics Existing mine infrastructure Existing services Scaleable project Experienced team
Slide 19: Existing logistics – competitive OPEX
Existing logistics – competitive OPEX Existing railway from mine to deep water port MSEK 450 (MUSD 65) committed by government for refurbishment of railway All year ice free port Baby Cape/Panamax capacity LoI signed with Oxelösund port 19
Slide 20: Summary: main project characteristics
Summary: main project characteristics 1 Large mineralization with expansion potential 2 High quality product 3 Low development risk 4 Very competitive OPEX and existing logistics 20
Slide 21: Agenda – Project development
Agenda Introduction Investment highlights Project development Financial information 21
Slide 22: Initial phase (2010-2012)
Initial phase (2010-2012) Organisation, management team & BoD Funding: Two mining concessions granted PEA/Scoping study MSEK 98 Environmental permit application (MUSD 15) 22
Slide 23: Current phase (2013/14)
Current phase (2013/14) Expansion and infill drilling Funding: Beneficiation tests and process layout MSEK 70 DFS Phase I (MUSD 11) Preparation for IPO 23
Slide 24: Construction Phase I (2014-2016)
Construction Phase I (2014-2016) Mining concession application Väsman Funding: Environmental permit application Väsman MSEK 2 400 Preparation for construction phase – Dewatering Blötberget (MUSD 350) – New entrance tunnel Production start Phase 1a 24
Slide 25: Construction Phase I (2014-2016) cont.
Construction Phase I (2014-2016) cont. Construction project build up Construction of plant with first production line and rail terminal • Off-take agreements • Feasibility study Phase II 25
Slide 26: Construction Phase II (2017-2019)
Construction Phase II (2017-2019) Organizational build up Funding: Production start and ramp-up MSEK 350 Construction of production line 2 (MUSD 50) Commissioning of line 2 26
Slide 27: Construction Phase III (2020-2021)
Construction Phase III (2020-2021) Mine development Production ramp-up Construction of production line 3 Commission production line 3 27
Slide 28: Risk mitigation
Risk mitigation Construction risk and process risk greatly reduced due to: 1 Complete DFS before final investment decision 2 Experienced project management team 3 Detailed planning and close monitoring of schedule 4 Focus on cost control and follow up systems 5 Professional procurement with close mo
Slide 29: Risk mitigation – separate project organisation
Risk mitigation – separate project organisation Project director Exploration Procurement & Controller quality Production Economy & finance Planning HSE CEO Logistics HR Marketing and sales Blötberget Väsman Environment Håksberg Skeppmora 29
Slide 30: Project development schedule
Project development schedule -- Key milestones Investment decision, Financing & Organisational build up Construction Phase 1 Beneficiation start DFS-Phase 1 Installation & commissioning & ramp up 2013 2014 2015 2016 2017-2021 Environmental permit IPO B+H 30
Slide 31: Management and board
Management and board Management Christer Lindqvist Lennart Eliasson Hans Thorshag Louise Sjögren Paul Marsden CEO CFO Technical Director Chief Geologist Sales and Marketing Board of directors Broad mix of skills, knowledge and experience Board is incentivised through stock ownership 31
Slide 32: Agenda – Financial information
Agenda Introduction Investment highlights Project development Financial information 32
Slide 33: Attractive economics
Attractive economics Exemple calculation at full production, USD/t Assumed long term price (62% Fe) 120 Premium (67% Fe) +15 Freight –24 FOB 111 OPEX* -52 OH-cost -1 Financing cost** -10 Margin 48 *During the ramp up periods OPEX will be higher, but Phase 1 has an OPEX of only 46.6 USD/tonne ** Fina
Slide 34: CAPEX – three phases overview and schedule
CAPEX- three phases overview and schedule 10% MUSD 678 to full production 4% 5% 38% 200 42% 152 Mining Benefication 138 Transport & Logistics Infrastructure & Buildings Administration 128 102 100 87 Studies = 30 71 Phase III=167 Phase II =182 Phase I = 298 0 2014/15 2015/16 2016/17 2017/18 2018/19 2
Slide 35: Capex incl DFS and production ramp-up, Base case
Capex incl DFS and production ramp-up, Base case (Pre financing cost and pre tax) Second fund raise only after production start Phase I Revenue from Q3 2015 Gradual ramp up of logistics chain Large part of Capex financed internally - external need MUSD 325 200 For Phase Ia Phase I-III Intern
Slide 36: Key figures (Phase 1)
Key figures (Phase 1) Targeting a 1.43 Mtpa operation OPEX 46.6 USD/t CAPEX to full production USD 298 million Pay back period ≈ 4.5 years NPV (@ 8.0%) USD 186 million Project IRR 17%, (unleveraged)mine at 36
Slide 37: Key figures (All Phases)
Key figures (All Phases) Targeting a 4.3 Mtpa operation OPEX 51.5 USD/t CAPEX to full production USD 678 million Pay back period ≈ 5.5 years NPV (@ 8.0%) USD 934 million Project IRR 23%, (unleveraged)mine at 37
Slide 38: Thank you