Energy Resources Of Australia Ltd. Class A · ASX:ERA

Energy Resources Of Australia Ltd. Class A — Non-Deal Roadshow (October 2013)

18 slides from Energy Resources Of Australia Ltd. Class A's roadshow presentation, Oct 22, 2013

  1. Slide 1: ASX cover letter for Asia investor meetings

    Head office Level 3, Energy House, 18-20 Cavenagh St, Darwin NT 0800 GPO Box 2394, Darwin NT 0801, Australia T +61 8 8924 3500 F +61 8 8924 3555 Ranger mine Locked Bag 1, Jabiru NT 0886 Australia T +61 8 8938 1211 F +61 8 8938 1203 www.energyres.com.au ABN 71 008 550 865 A member of the Rio Tinto Gr

  2. Slide 2: ERA update

    For personal use only ERA update Andrea Sutton| Chief Executive Steeve Thibeault | Chief Financial Officer 21-24 October 2013 www.energyres.com.au

  3. Slide 3: Acknowledge Traditional Owners

    Acknowledge Traditional Owners For personal use only • The mining operations of Energy Resources of Australia Ltd (ERA) are located on Aboriginal land and are surrounded by, but separate from, Kakadu National Park • ERA respectfully acknowledges the Mirarr, Traditional Owners of the land on which th

  4. Slide 4: Forward-looking statement

    Forward-looking statement • This presentation has been prepared by Energy Resources of Australia Ltd (“ERA”) and consists of the slides for a presentation concerning ERA. By reviewing/attending this presentation you agree to be bound by the following conditions. For personal use only Forward-looking

  5. Slide 5: Agenda

    Agenda • Overview For personal use only • Safety and people • Brine Concentrator • Ranger 3 Deeps • Progressive rehabilitation • Business Review • Market • Summary 4 www.energyres.com.au

  6. Slide 6: Overview

    Overview • Uranium market challenging in the near term, but long term fundamentals remain positive For personal use only • In light of this, ERA’s strategic areas of focus continue to be: – Health, safety and environment • Year to date achieved all Injury Frequency Rate of 0.37 (12 month rolling ave

  7. Slide 7: Safety and people

    Safety and people 5 • Safety For personal use only 4.5 4 – Continued strong focus on safety and has achieved a year to date all Injury Frequency rate (per 200,000 hrs worked) 3.5 Frequency Rate of 0.37 (12 month 3 rolling average) 2.5 – Record number of days without 2 recordable injury achieved on 7

  8. Slide 8: Exploration decline progress

    Ranger 3 Deeps exploration decline progress For personal use only As at 13 October 2013 face position is 1,475 metres from surface 7 www.energyres.com.au

  9. Slide 9: First cross section of underground close-spaced drilling completed

    First cross section of underground close-spaced drilling of the Ranger 3 Deeps mineral resource completed • Ranger 3 Deeps Exploration Decline For personal use only – Project on schedule and budget – 12 per cent of total drilling programme completed to date – Macmahon Underground Pty Ltd constructin

  10. Slide 10: Exploration decline drilling sequence

    Ranger 3 Deeps exploration decline drilling sequence For personal use only 3rd Drill fan currently in progress. Due for completion approximately mid November (grey) First drill fan complete (pink) Drilling plan to explore northern extension. Due for completion Current fan of drill approximately Apri

  11. Slide 11: Potential underground mine

    Ranger 3 Deeps potential underground mine • Ranger 3 Deeps Mine Prefeasibility Study For personal use only – $57 million underground mine Prefeasibility study progressing in parallel to the decline construction – The Prefeasibility Study is on schedule, fully funded and on budget – The study include

  12. Slide 12: Brine Concentrator formally opened September 2013

    Brine Concentrator formally opened on 19 September 2013 The Brine Concentrator is critical to water management and the For personal use only • rehabilitation programme at Ranger mine • The Brine Concentrator was formally opened by NT Chief Minister Adam Giles on 19 September 2013 • Project has been

  13. Slide 13: Progressive rehabilitation making good progress

    Progressive rehabilitation making good progress For personal use only Pit 3 on completion of mining in November 2012 Pit 3 initial backfill as at September 2013 • Material moved into Pit 3 since December 2012 to date is approximately 19 million tonnes out of a total of 30 million tonnes • Pit 1 dewa

  14. Slide 14: On track to meet 2011 cost savings target of $150 million by 2014

    On track to meet 2011 cost savings target of $150 million by 2014 • Reduced the number of employees by 20 per cent from 2011 to September 2013 For personal use only At 30 June 2013, ERA has achieved total cumulative • Reduced indirect employees costs savings of $102 million through implementation of

  15. Slide 15: Relationship with the Gundjeihmi Aboriginal Corporation

    Relationship with the Gundjeihmi Aboriginal Corporation • The relationship with the Gundjeihmi Aboriginal Corporation, who represent the Mirarr For personal use only Traditional Owners continues to develop • In the first half of 2013, the focus has been on – Implementation of the Mining Agreement –

  16. Slide 16: The market remains challenged in the near term

    The market remains challenged in the near term For personal use only • The after effects of Fukushima continue to weigh on the market − No units operating in Japan, as the Nuclear Regulation Authority evaluates required upgrades and seismic safety − Units expected to be re-started in mid-2014, but p

  17. Slide 17: However, longer-term market fundamentals strong

    However, longer-term market fundamentals strong • Global long-term nuclear growth projections remain strong For personal use only − China has 28 units under construction and another 53 planned by 2025 − Reactor growth still occurring in the US, Korea, UAE, India, and elsewhere • The growth drivers a

  18. Slide 18: Summary

    Summary • Continued strong safety and environmental performance For personal use only • 2013 production of uranium oxide is expected to be between 2,800 and 3,200 tonnes • Ranger 3 Deeps Exploration Decline and Ranger 3 Deeps Mine Prefeasibility Study, progressing on budget and on schedule • Key reh

Energy Resources of Australia — Non-Deal Roadshow (October 2013) on 6ix