Enlight Renewable Energy Ltd · TASE:ENLT

Enlight Renewable Energy — Q4 2023 Earnings Presentation

20 slides from Enlight Renewable Energy's earnings presentation, February 2024

  1. Slide 1: Earnings Presentation Fourth Quarter 2023

    Slide 1: Earnings Presentation Fourth Quarter 2023

    EARNINGS PRESENTATION Fourth Quarter 2023

  2. Slide 2: Legal disclaimer

    Slide 2: Legal disclaimer

    Legal disclaimer This presentation contains forward-looking statements within the meaning of the U.S. Private Securities Litigation Reform Act of 1995. We use of tax equity arrangements; potential claims and disagreements with partners, investors and other counterparties that could reduce intend suc

  3. Slide 3: Enlight at a glance

    Slide 3: Enlight at a glance

    Enlight at a glance Next generation global renewable energy platform Greenfield developer and IPP Global platform Wind, solar and energy storage Control over entire project life cycle Growing activity across Expertise across main renewable U.S., Europe and Israel technologies Extensive track record

  4. Slide 4: Delivering high-growth and high-returns in 2023 and beyond

    Slide 4: Delivering high-growth and high-returns in 2023 and beyond

    Delivering high-growth and high-returns in 2023 and beyond 1 Strong results in 2023 FY‘23 Results In 2023, Enlight followed through on its high-growth and high-return commitment: o Strong financial results with revenue up 33% and Adjusted EBITDA up 45%, demonstrating robustness of $256m joint develo

  5. Slide 5: Strong growth in 2023 with continued improvement in profitability

    Slide 5: Strong growth in 2023 with continued improvement in profitability

    Strong growth in 2023 with continued improvement in profitability Demonstrated value of combined developer and IPP business model Q4 2023 versus Q4 2022 FY 2023 versus FY 2022 21% ($m) ($m) 74 33% 256 61 8% 45% 192 189 47 -35% 66% 43 150 37 130 157% 48% 98 24 90 16 11 38 Revenue Net income Adjusted

  6. Slide 6: Recapping 2023: joint development and IPP model running at full speed

    Slide 6: Recapping 2023: joint development and IPP model running at full speed

    Recapping 2023: joint development and IPP model running at full speed Projects reaching COD, entering construction and converting from development +487 MW & 277 MWh +871 MW & 2.7 GWh New Operational Projects New Projects in Pre-Construction Country Acres • 392 MW and 688 MWh Apex Genesis Wind PV + S

  7. Slide 7: Moving into 2024: improving fundamentals

    Slide 7: Moving into 2024: improving fundamentals

    Moving into 2024: improving fundamentals Equipment prices continue to fall … … while PPA pricing continues to rise … … and interest rates stabilize Key commodity prices Price ($/MWh) US PPA Prices 10-year US government bond yield 120 60.11 $60 100 56.4 5.0% 4.9% 80 $50 52.69 4.5% 4.3% 60 $40 40 Sola

  8. Slide 8: Project returns: mid-teens levered returns expected for 2024-26 CODs

    Slide 8: Project returns: mid-teens levered returns expected for 2024-26 CODs

    Project returns: mid-teens levered returns expected for 2024-26 CODs Overlaying a 10% unlevered return with a 5.25%-5.75% cost of debt Global Portfolio of 2024-26 CODs Equity IRR 3.5 GW 5.4 GWh 90% With Mid-teens % Signed PPAs Unlevered Ratio $352-370m Estimated First 10% Full Year EBITDA1 $3.6bn Es

  9. Slide 9: 2024: Next major expansion, transformation towards the U.S.

    Slide 9: 2024: Next major expansion, transformation towards the U.S.

    2024: Next major expansion, transformation towards the U.S. 2024 Projects Reaching COD 2024 Projects Commencing Construction +543 MW & 1.6 GWh +1 GW & 2.9 GWh +29% Generation +55% Generation +580% Energy Storage +1040% Energy Storage Generation capacity Storage capacity Generation capacity Storage c

  10. Slide 10: Growth in 2024: Starting on three new flagship projects, Atrisco reaches COD

    Slide 10: Growth in 2024: Starting on three new flagship projects, Atrisco reaches COD

    Growth in 2024: Starting on three new flagship projects, Atrisco reaches COD Combination of large-scale projects at high returns Country Acres Roadrunner Location California Location Arizona Capacity 392 MW + 688 MWh Capacity 294 MW + 940 MWh Status Construction starts 1H24 Status Construction start

  11. Slide 11: Growth in 2024: Diverse mix of new wind, solar and battery projects

    Slide 11: Growth in 2024: Diverse mix of new wind, solar and battery projects

    Growth in 2024: Diverse mix of new wind, solar and battery projects Continuing to expand presence across EU and Israel with high projected project returns Gecama Hybrid Location Solar, Spain Capacity 225 MW + 200 MWh Status Near Construction First Year $38-40m / $28-29m Revenues / EBITDA1 Unlevered

  12. Slide 12: 2024 Guidance – Revenues of $335-360m and Adjusted EBITDA of $235-255m

    Slide 12: 2024 Guidance – Revenues of $335-360m and Adjusted EBITDA of $235-255m

    2024 Guidance – Revenues of $335-360m and Adjusted EBITDA1 of $235-255m Operational Portfolio Revenue Adjusted EBITDA1 )MW & MWh) ($m) ($m) 50% CAGR 335-360 Key Assumptions +236% CAGR in MW • 90% of generation sold at fixed prices +579% CAGR 2,426 MW + 35% through hedges or PPAs in MWh 1,880 MWh 256

  13. Slide 13: Medium term picture: unique leadership position across interconnection

    Slide 13: Medium term picture: unique leadership position across interconnection

    Medium term picture: unique leadership position across interconnection Transmission infrastructure is the principal constraint for renewable energy today Mature Projects Advanced Development Development 3.1 GW + 3.6 GW + 2.9 GW 100% of 100% of U.S 32% of U.S U.S Mature Advanced Development Developme

  14. Slide 14: Case study: delivery of PJM portfolio

    Slide 14: Case study: delivery of PJM portfolio

    Case study: delivery of PJM portfolio 1.4 GW and 2.2 GWh of energy storage fast tracked to final interconnection agreements Project Name Status Generation (MW) Storage (MWh) State 1 PJM portfolio carries minimal network upgrade costs Near Gemstone 185 - Michigan Construction Advanced Blackwater 720

  15. Slide 15: 2026 plan: 5.3 GW and 5.7 GWh operational

    Slide 15: 2026 plan: 5.3 GW and 5.7 GWh operational

    2026 plan: 5.3 GW and 5.7 GWh operational Massive growth into middle of decade: operational capacity expected to triple to 5.3 GW and 5.7 GWh by the end of 2026 2024 | Atrisco (364 MW, 1.2 GWh) Major Expected 2025 | Gecama & Roadrunner (519 MW, 1.1 GWh) 5,338 MW + 5,649 MWh CODs 2026 | CO Bar & Coun

  16. Slide 16: Appendix

    Slide 16: Appendix

    en Appendix

  17. Slide 17: PJM fast track portfolio

    Slide 17: PJM fast track portfolio

    PJM fast track portfolio Reedy Creek Horsepen Branch Bear Island Blackwater Blackwater B Gemstone Swift Creek Mature-Near Construction Advanced Development Early-Stage Development 17

  18. Slide 18: Reconciliation between Net Income to Adjusted EBITDA

    Slide 18: Reconciliation between Net Income to Adjusted EBITDA

    Reconciliation between Net Income to Adjusted EBITDA ($ thousands) For the 12 months ended For the three months ended 12/31/23 12/31/22 12/31/23 12/31/22 Net Income (loss) 98,067 38,113 16,228 10,955 Depreciation and amortization 65,796 42,267 21,611 13,454 Share based compensation 4,970 8,673 970 1

  19. Slide 19: Portfolio snapshot

    Slide 19: Portfolio snapshot

    Portfolio snapshot Generation, Storage, Graph, MW MWh scale Portfolio definitions Operational, under construction and pre- + + Mature construction (expected to start construction within 12 months) + 10,549 12,603 20,618 30,743 4,693 12,491 Projects which are expected to begin Advanced construction w

  20. Slide 20: Thank you

    Slide 20: Thank you

    en Thank you

Source: Internet Archive copy of enlightenergy.co.il