Enlight Renewable Energy Ltd · TASE:ENLT
Enlight Renewable Energy — Q4 2023 Earnings Presentation
20 slides from Enlight Renewable Energy's earnings presentation, February 2024

Slide 1: Earnings Presentation Fourth Quarter 2023
EARNINGS PRESENTATION Fourth Quarter 2023

Slide 2: Legal disclaimer
Legal disclaimer This presentation contains forward-looking statements within the meaning of the U.S. Private Securities Litigation Reform Act of 1995. We use of tax equity arrangements; potential claims and disagreements with partners, investors and other counterparties that could reduce intend suc

Slide 3: Enlight at a glance
Enlight at a glance Next generation global renewable energy platform Greenfield developer and IPP Global platform Wind, solar and energy storage Control over entire project life cycle Growing activity across Expertise across main renewable U.S., Europe and Israel technologies Extensive track record

Slide 4: Delivering high-growth and high-returns in 2023 and beyond
Delivering high-growth and high-returns in 2023 and beyond 1 Strong results in 2023 FY‘23 Results In 2023, Enlight followed through on its high-growth and high-return commitment: o Strong financial results with revenue up 33% and Adjusted EBITDA up 45%, demonstrating robustness of $256m joint develo

Slide 5: Strong growth in 2023 with continued improvement in profitability
Strong growth in 2023 with continued improvement in profitability Demonstrated value of combined developer and IPP business model Q4 2023 versus Q4 2022 FY 2023 versus FY 2022 21% ($m) ($m) 74 33% 256 61 8% 45% 192 189 47 -35% 66% 43 150 37 130 157% 48% 98 24 90 16 11 38 Revenue Net income Adjusted

Slide 6: Recapping 2023: joint development and IPP model running at full speed
Recapping 2023: joint development and IPP model running at full speed Projects reaching COD, entering construction and converting from development +487 MW & 277 MWh +871 MW & 2.7 GWh New Operational Projects New Projects in Pre-Construction Country Acres • 392 MW and 688 MWh Apex Genesis Wind PV + S

Slide 7: Moving into 2024: improving fundamentals
Moving into 2024: improving fundamentals Equipment prices continue to fall … … while PPA pricing continues to rise … … and interest rates stabilize Key commodity prices Price ($/MWh) US PPA Prices 10-year US government bond yield 120 60.11 $60 100 56.4 5.0% 4.9% 80 $50 52.69 4.5% 4.3% 60 $40 40 Sola

Slide 8: Project returns: mid-teens levered returns expected for 2024-26 CODs
Project returns: mid-teens levered returns expected for 2024-26 CODs Overlaying a 10% unlevered return with a 5.25%-5.75% cost of debt Global Portfolio of 2024-26 CODs Equity IRR 3.5 GW 5.4 GWh 90% With Mid-teens % Signed PPAs Unlevered Ratio $352-370m Estimated First 10% Full Year EBITDA1 $3.6bn Es

Slide 9: 2024: Next major expansion, transformation towards the U.S.
2024: Next major expansion, transformation towards the U.S. 2024 Projects Reaching COD 2024 Projects Commencing Construction +543 MW & 1.6 GWh +1 GW & 2.9 GWh +29% Generation +55% Generation +580% Energy Storage +1040% Energy Storage Generation capacity Storage capacity Generation capacity Storage c

Slide 10: Growth in 2024: Starting on three new flagship projects, Atrisco reaches COD
Growth in 2024: Starting on three new flagship projects, Atrisco reaches COD Combination of large-scale projects at high returns Country Acres Roadrunner Location California Location Arizona Capacity 392 MW + 688 MWh Capacity 294 MW + 940 MWh Status Construction starts 1H24 Status Construction start

Slide 11: Growth in 2024: Diverse mix of new wind, solar and battery projects
Growth in 2024: Diverse mix of new wind, solar and battery projects Continuing to expand presence across EU and Israel with high projected project returns Gecama Hybrid Location Solar, Spain Capacity 225 MW + 200 MWh Status Near Construction First Year $38-40m / $28-29m Revenues / EBITDA1 Unlevered

Slide 12: 2024 Guidance – Revenues of $335-360m and Adjusted EBITDA of $235-255m
2024 Guidance – Revenues of $335-360m and Adjusted EBITDA1 of $235-255m Operational Portfolio Revenue Adjusted EBITDA1 )MW & MWh) ($m) ($m) 50% CAGR 335-360 Key Assumptions +236% CAGR in MW • 90% of generation sold at fixed prices +579% CAGR 2,426 MW + 35% through hedges or PPAs in MWh 1,880 MWh 256

Slide 13: Medium term picture: unique leadership position across interconnection
Medium term picture: unique leadership position across interconnection Transmission infrastructure is the principal constraint for renewable energy today Mature Projects Advanced Development Development 3.1 GW + 3.6 GW + 2.9 GW 100% of 100% of U.S 32% of U.S U.S Mature Advanced Development Developme

Slide 14: Case study: delivery of PJM portfolio
Case study: delivery of PJM portfolio 1.4 GW and 2.2 GWh of energy storage fast tracked to final interconnection agreements Project Name Status Generation (MW) Storage (MWh) State 1 PJM portfolio carries minimal network upgrade costs Near Gemstone 185 - Michigan Construction Advanced Blackwater 720

Slide 15: 2026 plan: 5.3 GW and 5.7 GWh operational
2026 plan: 5.3 GW and 5.7 GWh operational Massive growth into middle of decade: operational capacity expected to triple to 5.3 GW and 5.7 GWh by the end of 2026 2024 | Atrisco (364 MW, 1.2 GWh) Major Expected 2025 | Gecama & Roadrunner (519 MW, 1.1 GWh) 5,338 MW + 5,649 MWh CODs 2026 | CO Bar & Coun

Slide 16: Appendix
en Appendix

Slide 17: PJM fast track portfolio
PJM fast track portfolio Reedy Creek Horsepen Branch Bear Island Blackwater Blackwater B Gemstone Swift Creek Mature-Near Construction Advanced Development Early-Stage Development 17

Slide 18: Reconciliation between Net Income to Adjusted EBITDA
Reconciliation between Net Income to Adjusted EBITDA ($ thousands) For the 12 months ended For the three months ended 12/31/23 12/31/22 12/31/23 12/31/22 Net Income (loss) 98,067 38,113 16,228 10,955 Depreciation and amortization 65,796 42,267 21,611 13,454 Share based compensation 4,970 8,673 970 1

Slide 19: Portfolio snapshot
Portfolio snapshot Generation, Storage, Graph, MW MWh scale Portfolio definitions Operational, under construction and pre- + + Mature construction (expected to start construction within 12 months) + 10,549 12,603 20,618 30,743 4,693 12,491 Projects which are expected to begin Advanced construction w

Slide 20: Thank you
en Thank you
Source: Internet Archive copy of enlightenergy.co.il
More decks from Enlight Renewable Energy Ltd
Q3 2026 Earnings Presentation36 slides · Nov 3, 2026
Investor Presentation (November 2026)48 slides · November 2026
Q3 2026 Earnings Presentation36 slides · November 2026
Investor Presentation (October 2026)46 slides · October 2026
Investor Presentation (August 2026)44 slides · August 2026
Q2 2026 Earnings Presentation36 slides · August 2026