  1. Slide 1: Investor Trip presentation November 2008

    Slide 1: Investor Trip presentation November 2008

    Investor Trip presentation Investor November 2008 Sharjah 2008 Day 2 Engineering & Construction 1

  2. Slide 2: Introduction

    Slide 2: Introduction

    Introduction Objectives of investor presentation – communicate our vision and strategy – communicate the extent of our service capabilities and our market opportunities – communicate how we are building a platform for sustainable growth – provide an opportunity to meet senior management of our Engin

  3. Slide 3: Vision & values

    Slide 3: Vision & values

    Vision & values Our vision is for Petrofac to become the global oil & gas industry’s premier facilities and infrastructure provider, admired by customers and employees for consistently delivering and rewarding excellence Achieving this demands that we: – work to world-class standards – focus always

  4. Slide 4: Petrofac today

    Slide 4: Petrofac today

    Petrofac today Petrofac is a successful business that has enjoyed tremendous growth – doubling of our employee headcount in three years – significant increase in our operational capability through organic development and acquisition – strong year-on-year growth in our financial performance Whilst cu

  5. Slide 5: Industry fundamentals: demand, positive trend

    Slide 5: Industry fundamentals: demand, positive trend

    Industry fundamentals: demand, positive trend OECD and non-OECD oil demand, 1960-2005 90 80 70 60 Demand (mbbls/d) 50 40 30 Recessions: 4Q'69-1Q'70 20 3Q'74-1Q'75 2Q'80-3Q'80 1Q'81-2Q'81 10 4Q'90-1Q'91 1Q'01-3Q'01 0 1962 1967 1972 1977 1982 1987 1992 1997 2002 2007E Source: IEA Total World Demand OE

  6. Slide 6: Industry fundamentals: demand led by China, India, ME

    Slide 6: Industry fundamentals: demand led by China, India, ME

    Industry fundamentals: demand led by China, India, ME 2006 Oil Demand Population Oil Consumption Per (mbbls/year) (millions) Capita (bbls) Source: based on IEA data, World Energy Outlook 2008 North America 9,100 450 20 Europe 5,200 540 10 Disparity Disparity in in consumption consumption per per cap

  7. Slide 7: Industry fundamentals: supply/cost curve

    Slide 7: Industry fundamentals: supply/cost curve

    Industry fundamentals: supply/cost curve Recent sharp decline in oil price and uncertainty over near term levels has led to general expectation that some marginal projects will be deferred Industry’s current investment plans in oil sands, challenging deep water and potentially North Sea may be uneco

  8. Slide 8: Industry fundamentals: supply, easy oil discovered

    Slide 8: Industry fundamentals: supply, easy oil discovered

    Industry fundamentals: supply, easy oil discovered Million standard m3 oil equivalent (mm Sm3) 3,000 Discoveries <5 mm Sm3 Discoveries 5-10 mm Sm3 2,500 Discoveries 10-15 mm Sm3 Discoveries 50-100 mm Sm3 2,000 Discoveries >100 mm Sm3 1,500 1,000 500 0 1967- 1972- 1977- 1982- 1987- 1992- 1997- 2002-

  9. Slide 9: Industry fundamentals: substantial capex spend required

    Slide 9: Industry fundamentals: substantial capex spend required

    Industry fundamentals: substantial capex spend required 120 Demand Demand expected expected to to grow grow 1.6% 1.6% per per year year 100 Oil Production & Demand (mbbls/d) 80 By By 2030, 2030, new new production production capacity capacity of of more more than than 70% 70% of of the the existing

  10. Slide 10: Energy Developments

    Slide 10: Energy Developments

    Amjad Bseisu Energy Developments Production Solutions (SPD, Caltec, Eclipse, Dubai) Training Offshore Engineering & Operations (Facilities Maroun Semaan Management, Brownfield) Engineering services Our 2009 reorganisation (Woking and lower cost engineering centres) New ventures (Mubadala, Saudi Lump

  11. Slide 11: Our 2009 reorganisation

    Slide 11: Our 2009 reorganisation

    Our 2009 reorganisation Principal benefits of new reorganisation structure are: – deliver revenue synergies through greater integration and deployment of multiple services to customers and projects – deliver differentiated returns through innovative commercial structures that provide for an appropri

  12. Slide 12: Our growth, Engineering & Construction

    Slide 12: Our growth, Engineering & Construction

    Our growth, Engineering & Construction Previous investor trip to United Arab Emirates in November 2006 Engineering & Construction division has grown significantly since that time Key awards during the year included Kashagan third oil train, Ebla gas plant, Jihar gas plant, KOC gas pipeline Revenue (

  13. Slide 13: Our growth, Engineering & Construction

    Slide 13: Our growth, Engineering & Construction

    Our growth, Engineering & Construction Division now capable of undertaking much larger scale contracts Strong growth in headcount and revenue, and even stronger growth in net profit Engineering & Construction remains leveraged to the strong fundamentals of the oil & gas industry Net profit (US$m) Ne

  14. Slide 14: Our growth, Engineering & Construction, personnel

    Slide 14: Our growth, Engineering & Construction, personnel

    Our growth, Engineering & Construction, personnel By location 2008 Current employee strength ~ 5,000 Sharjah 1,771 37% Sites 1,518 31% Manpower Growth 4800 Mumbai 521 11% Woking 556 11% 4000 Chennai 433 9% Moscow 40 1% 2600 (rounded) 4,800 By class 2008 Engineering 2,027 42% 2006 2007 2008 Construct

  15. Slide 15: Our growth, Engineering & Construction, personnel

    Slide 15: Our growth, Engineering & Construction, personnel

    Our growth, Engineering & Construction, personnel Recruited approximately 1,000 personnel in 2008 Brand reputation and awareness in universities and market place Employee referral programme implemented Organisation and Development team fully established focused on competency and career development/p

  16. Slide 16: Our growth, Engineering & Construction, infrastructure

    Slide 16: Our growth, Engineering & Construction, infrastructure

    Our growth, Engineering & Construction, infrastructure Infrastructure – major IT projects Unified global computer network and e-mail infrastructure under one umbrella (Petrofac.com) Group wide enterprise business software solution (Oracle ERP) Business continuity plan, IT disaster recovery

  17. Slide 17: Our growth, the way forward

    Slide 17: Our growth, the way forward

    Our growth, the way forward Consolidate position in current core markets – Maintain cost competitiveness – Maintain relations with customers, subcontractors and service providers Well focused push into: – Abu Dhabi and Saudi Arabia for EPC opportunities – LNG – Offshore engineering and construction

  18. Slide 18: Future growth drivers and initiatives

    Slide 18: Future growth drivers and initiatives

    Future growth drivers and initiatives

  19. Slide 19: Future growth drivers and initiatives: overview

    Slide 19: Future growth drivers and initiatives: overview

    Future growth drivers and initiatives Overview In spite of global economic events, outlook is optimistic International oil companies and national oil companies remain focused on investment although a slowing down in some areas (downstream) Core markets – Middle East and Africa remain strong Human ca

  20. Slide 20: Strategies for growth and risk management

    Slide 20: Strategies for growth and risk management

    Future growth drivers and initiatives Strategies for growth and risk management Geography - diversification by region – portfolio of risk: security, political/legal, economic – five/six core country markets with numerous opportunistic countries – local presence continues to be a strong differentiato

  21. Slide 21: Geographic diversification, sales and development focus

    Slide 21: Geographic diversification, sales and development focus

    Future growth drivers and initiatives Geographic diversification, sales and development focus Middle East – Qatar, Saudi Arabia, Kuwait, Oman, UAE – Iraq (medium term) – Iran (medium to long term) Africa – Algeria, Egypt, Tunisia, Nigeria, Libya CIS – Kazakhstan, Turkmenistan, Russia

  22. Slide 22: Geographic diversification

    Slide 22: Geographic diversification

    Future growth drivers and initiatives Geographic diversification Objective is to maintain a balanced portfolio by target region – 2005 Middle East order intake – 2006 Africa and CIS order intake – 2007 Africa and CIS order intake – 2008 Middle East order intake – 2009 Middle East and Africa Increase

  23. Slide 23: Customer and product diversification

    Slide 23: Customer and product diversification

    Future growth drivers and initiatives Customer and product diversification Focus on strong relationships with international oil companies and national oil companies Mitigate cyclical industry trends by – LNG, refinery, petrochemical – balance services over offshore/onshore Ability to offer different

  24. Slide 24: Customer and product diversification: LNG / GTL

    Slide 24: Customer and product diversification: LNG / GTL

    Future growth drivers and initiatives Customer and product diversification LNG / GTL Selective technology positions – alliances, joint ventures with specialist contractors Build on local presence – UAE – Oman – Algeria – Qatar – Kuwait – Kazakhstan

  25. Slide 25: Competition

    Slide 25: Competition

    Future growth drivers and initiatives Competition With the Tier 1 contractors, limited peer competition, increasing Korean competition Development of differentiated position – through execution model, services to EPC, operations and training – through reliability and delivery leading to repeat busin

  26. Slide 26: Petrofac Emirates - new venture in the UAE

    Slide 26: Petrofac Emirates - new venture in the UAE

    Future growth drivers and initiatives Petrofac Emirates - new venture in the UAE Joint venture between Petrofac and Mubadala Scope of work, EPC in UAE and where Mubadala has participating interest Major short-term bidding activity – ADCO, SAS, BAB Compression – ADGAS, Das Island – GASCO, Habshan uti

  27. Slide 27: Saudi Arabia

    Slide 27: Saudi Arabia

    Future growth drivers and initiatives Saudi Arabia Actively bidding for projects eg. Karan utilities & offsites, Yanbu export refinery Excellent visibility of opportunities 2009-2012 in core oil & gas, refinery and petrochemical Local legal entity established – essential for in-country execution Tar

  28. Slide 28: LNG

    Slide 28: LNG

    Future growth drivers and initiatives LNG Prequalified for Shell LNG projects worldwide, US$5-10 billion greenfield Bid for world class LNG project, albeit unsuccessful (Algeria) Currently bidding for other LNG opportunities Good visibility of short/medium-term prospects Pursuing strategic alliances

  29. Slide 29: The outlook

    Slide 29: The outlook

    Future growth drivers and initiatives The outlook Target markets, outlook remains positive Good visibility of 2009, 2010 prospects for EPC Acquisitions on a selective basis Securing and retention of resources is a primary focus

  30. Slide 30: Risk management

    Slide 30: Risk management

    Petrofac PY € F 2) e 2 % ce

  31. Slide 31: Risk management

    Slide 31: Risk management

    Risk management Executive risk management strategy Risk Risk management management processes processes Contract/project Corporate risk management support and execution and guidance management

  32. Slide 32: Risk management strategy

    Slide 32: Risk management strategy

    Risk management strategy Executive risk management strategy Focus on areas of principal expertise, lump sum EPC and engineering services Mitigation through a broad portfolio, countries and services Strong management control and accountability Heavy investment in proposal management and project contr

  33. Slide 33: Risk management approach

    Slide 33: Risk management approach

    Risk management approach Corporate support and guidelines Measurement and monitoring of corporate risk exposures, banks, countries, contracts, commodities, and other counter-party risk (vendors, subcontractors) etc Use of guidelines to establish limits and parameters for risk taking Common processes

  34. Slide 34: Contract risk in Engineering & Construction

    Slide 34: Contract risk in Engineering & Construction

    Contract risk in Engineering & Construction COUNTRY RISKS CUSTOMER RISKS Join venture/ Consortium agreement Contracts PARTNER RISKS PETROFAC Purchase orders Subcontracts SUBCONTRACTOR RISKS VENDOR/SUPPLIER RISKS

  35. Slide 35: Petrofac's contractual risk policy

    Slide 35: Petrofac's contractual risk policy

    Petrofac’s contractual risk policy Petrofac seeks balanced contractual risk allocation with customers, partners and subcontractors to: – avoid disproportionate potential liabilities – eliminate/minimise potential liabilities outside Petrofac control – allow an equitable allocation of risks amongst p

  36. Slide 36: Contract risk, prequalification cycle

    Slide 36: Contract risk, prequalification cycle

    Contract risk, prequalification cycle Prospect Prequalification Prequalification Prospect identification documents documentssubmission submission identification Prequalification phase Assessment Assessment of of customer customer risk risk & & country risk country risk High High level level executio

  37. Slide 37: Contract risk, proposal cycle

    Slide 37: Contract risk, proposal cycle

    Contract risk, proposal cycle Risk review Proposal ready Risk review Tender Tender Technical and Proposal ready for review committee committee Proposal Proposal Bid/no bid Technical and Receive Receive information Bid/no bid for review (RRC) Review information decision commercial commercial (RRC) Re

  38. Slide 38: Major contractual terms in EPC contracts

    Slide 38: Major contractual terms in EPC contracts

    Major contractual terms in EPC contracts Rely upon information Financial provisions and securities (payment terms, bank guarantees, etc) Liquidated damages for delay & failure to achieve performance guarantees Change in law Maximum aggregate liability of contractor under the contract Consequential l

  39. Slide 39: Contract risk, project cycle

    Slide 39: Contract risk, project cycle

    Contract risk, project cycle Commencement Commencement Mechanical Provisional Provisional Final Final Mechanical of ofEPC EPCcontract contract completion acceptance acceptance acceptance acceptance completion Warranty period EPC phase Commissioning phase Warranty phase Engineering By By Petrofac/ Pe

  40. Slide 40: Contract risk, profile

    Slide 40: Contract risk, profile

    Progress Final acceptance certificate Warranty phase Provisional Acceptance 100% Certificate Pay LDs Pay LDs Make good Make good RFSU ‘Back to back’ completion vendor Mechanical Execution phase guarantees Vendor representatives at site s ure e as nmio Correct design/ performance test igat Contract r

  41. Slide 41: Subcontracts, risk management

    Slide 41: Subcontracts, risk management

    Subcontracts, risk management PETROFAC CONSTRUCTION CONSTRUCTION MATERIAL MATERIAL SUBCONTRACTORS SUBCONTRACTORS VENDORS/SUPPLIERS VENDORS/SUPPLIERS Back-to-back Back-to-back basis basis with with a) a) Pass-through Pass-through obligations obligations the the EPC EPC contract contract b) b) Warrant

  42. Slide 42: Contract risk, large scale projects strategy (1)

    Slide 42: Contract risk, large scale projects strategy (1)

    Contract risk, large scale projects strategy (1) CUSTOMER Joint & several liability Joint towards customer Jointventure venture Petrofac Petrofac – JVPartner – JV Partner Sharing of risks PETROFAC JV PARTNER E, P & C Scope E, P & C Scope Engineering Engineering Procurement Procurement Construction C

  43. Slide 43: Contract risk, large scale projects strategy (2)

    Slide 43: Contract risk, large scale projects strategy (2)

    Contract risk, large scale projects strategy (2) CUSTOMER Joint & several liability Joint venture Joint venture towards customer Petrofac – Partner 1 – Partner 2 Petrofac – Partner 1 – Partner 2 Sharing of risks PETROFAC PARTNER 1 PARTNER 2 Engineering Engineering Procurement Procurement Engineering

  44. Slide 44: Subcontractor risk management

    Slide 44: Subcontractor risk management

    Subcontractor risk management Commencement of Mechanical Provisional Final Commencement of Mechanical Provisional Final EPC contract completion acceptance acceptance EPC contract completion acceptance acceptance Warranty period Commissioning Warranty EPC phase phase phase Late Late Lack Lack of of D

  45. Slide 45: Vendor/supplier risk management

    Slide 45: Vendor/supplier risk management

    Vendor/supplier risk management Placement of Mechanical Provisional Final Placement of Mechanical Provisional Final completion acceptance acceptance purchase order completion acceptance acceptance purchase order Warranty period Commissioning Order execution phase phase Warranty phase Order Order of

  46. Slide 46: The project cycle

    Slide 46: The project cycle

    The project cycle PROPOSAL STAGE AWARD STAGE EXECUTION STAGE Identification Identification of of Negotiations Negotiations with with Ensure Ensure strong strong critical critical contract contract customer customer to to ensure ensure fair fair support support & & risks risks and and mitigation miti

  47. Slide 47: Execution management

    Slide 47: Execution management

    Petrofac PY Execution management

  48. Slide 48: Execution management

    Slide 48: Execution management

    Execution management Phases of a project Basic components of each phase Common drivers

  49. Slide 49: Execution management, project phases

    Slide 49: Execution management, project phases

    Execution management, project phases Bid start Contract Bidding and award COMM complete proposals Performance Contract test complete realisation End of Custody handover liabilities Warranty period

  50. Slide 50: Execution management, proposal & bidding

    Slide 50: Execution management, proposal & bidding

    Execution management, proposal & bidding •Vendors •Vendors •Subcontractors •Subcontractors Customer Technical •Specialist •Specialistservices services •Technology/licensors •Technology/licensors Proposal Commercial Contractual

  51. Slide 51: Execution management, proposal approach

    Slide 51: Execution management, proposal approach

    Execution management, proposal approach Proposals are the cornerstone of good execution Manage the proposal as a project Mobilise the task force for the proposal Understand, analyse, dissect technical, contractual and commercial requirements Engage with customer, in clarification Identify third part

  52. Slide 52: Execution management, proposal approach

    Slide 52: Execution management, proposal approach

    Execution management, proposal approach Technical Prepare and submit technical proposal including clear representation of your understanding of requirements Prepare preliminary execution plans for the realisation phase including organisation, schedule, specifications and data sheets and basis of bid

  53. Slide 53: Execution management, proposal approach

    Slide 53: Execution management, proposal approach

    Execution management, proposal approach Engineering Verification and endorsement of the FEED – meets performance guarantees, material deliveries, alternatives, etc Development of the FEED at the bid stage, as required, to support the detailed estimate, provide early start for all disciplines Third p

  54. Slide 54: Execution management, proposal approach

    Slide 54: Execution management, proposal approach

    Execution management, proposal approach Contractual Prepare detailed list of contractual obligation and liabilities - assess criticality/ acceptability and risk associated with each submission Prepare detailed clarifications and qualifications and engage the customer Quantify cost where it is possib

  55. Slide 55: Execution management, proposal approach

    Slide 55: Execution management, proposal approach

    Execution management, proposal approach Commercial proposal Zero pricing principle (no rules of thumb, no estimation curves) Issue enquiries and obtain quotations Engage critical vendors in clarification and negotiations Evaluate data obtained against in-house recent data from projects Engage subcon

  56. Slide 56: Execution management, project realisation

    Slide 56: Execution management, project realisation

    Execution management, project realisation Engineering Project Procurement services Project Construction HSSE management Commissioning QA/QC Project controls

  57. Slide 57: Execution management, project realisation

    Slide 57: Execution management, project realisation

    Execution management, project realisation Project management principles Risk - early identification of risks and plans for mitigation HSSE - safe execution saves time and money Quality - the most cost effective scenario is do it right first time Customer satisfaction - create win-win relation with t

  58. Slide 58: Execution management, project realisation

    Slide 58: Execution management, project realisation

    Execution management, project realisation Project management approach Task force, with full in-house capability and competence QA and HSSE are an integral part of the project activities Construction/commissioning driven schedule Target driven schedules and plans Decision making process based on tech

  59. Slide 59: Execution management, quality assurance & control

    Slide 59: Execution management, quality assurance & control

    Execution management, quality assurance & control Quality management principles Customer focused organisation Leadership and standard setting Involvement of right resources Process approach (plan, do, check, act) Continual improvement Best practices, lessons learned Factual approach to decision maki

  60. Slide 60: Execution management, HSSE

    Slide 60: Execution management, HSSE

    Execution management, HSSE Management commitment to highest health, safety, security and environment standards Risk based inherently safe approach Exhaustive in-house HSSE technical capability for all project phases Integration of home office and site HSSE organisations

  61. Slide 61: Execution management, HSSE

    Slide 61: Execution management, HSSE

    Execution management, HSSE Construction HSSE programmes including: – emergency response procedures – crisis management – training – security – medical resources Proven capability of world class HSSE performance on projects with – extreme environments – low competency manpower – brownfield operations

  62. Slide 62: Execution management, HSSE

    Slide 62: Execution management, HSSE

    Execution management, HSSE Principles/approach Identify project specifics and risk areas – early and remain focused Develop programmes and specific plans Set targets and KPIs across all levels of project staff Develop plans, monitor, report and improve Visible leadership Ensure execution plans embod

  63. Slide 63: Execution management, engineering

    Slide 63: Execution management, engineering

    Execution management, engineering Full in-house capability and control Cover all aspects from studies to detailed engineering - Woking, Sharjah, Mumbai, Chennai & Indonesia High value operation centres (Mumbai, Chennai and Indonesia) Integrated data centric approach In-built quality assurance proces

  64. Slide 64: Execution management, procurement

    Slide 64: Execution management, procurement

    Execution management, procurement Integrated within project task force – buying, inspection and expediting Worldwide capability - Europe, US, Middle East offices Terms and conditions that cater for all potential risks and liabilities Deep understanding of our market/vendors Use of customer vendor li

  65. Slide 65: Execution management, construction and completions

    Slide 65: Execution management, construction and completions

    Execution management, construction and completions Principles Construction is generally sub-contracted Early engagement of construction partner - bidding Ensure relationship is governed by an equitable contract, that is almost ‘back to back’ with the main contract Develop a complementary win-win rel

  66. Slide 66: Execution management, construction

    Slide 66: Execution management, construction

    Execution management, construction Construction approach Experienced, hands-on construction management team – supervision, planning, quality, HSSE, material management – proper training and exposure Construction partner (local) – local materials, logistics, customs clearance, construction resources

  67. Slide 67: Execution management, completions

    Slide 67: Execution management, completions

    Execution management, completions Completion principles Use in-house resources Mobilise early enough to involve them in the formal reviews Input to engineering equipment, model reviews Input to quality plans of vendors Early definition of commissioning handover systems/schedule Identification and al

  68. Slide 68: Execution management, warranty

    Slide 68: Execution management, warranty

    Execution management, warranty Obtain back-to-back warranties Plan warranty period activities Allow provisions – in-house resources – third party costs (involve vendors) – materials Assign warranty coordinator (continuity) Responsiveness and problem solving Develop relations with the plant custodian

  69. Slide 69: Current projects

    Slide 69: Current projects

    Petrofac PY Current proj ects

  70. Slide 70: Current Sharjah projects

    Slide 70: Current Sharjah projects

    Current Sharjah projects Facilities upgrade, Kuwait Harweel, Oman Hasdrubal, Tunisia Salam gas plant, Egypt In Salah gas compression, Algeria Ebla gas plant, Syria Jihar gas plant, Syria KOC 40” feed pipeline Kashagan Train 3 Kashagan construction management Dec 04 Dec 05 Dec 06 Dec 07 Dec 08 Dec 09

  71. Slide 71: KOC facilities upgrade

    Slide 71: KOC facilities upgrade

    Petrofac rp) KOC facilities upgrade

  72. Slide 72: KOC facilities upgrade

    Slide 72: KOC facilities upgrade

    KOC facilities upgrade Customer Kuwait Oil Company (KOC) Project type Multi location Brownfield - EPCC- LSTK Scope Oil processing capacity increase and relocation of all underground hydrocarbon service piping to above ground at seven gathering centres & two booster stations Award May 2005 Schedule (

  73. Slide 73: KOC facilities upgrade: project description

    Slide 73: KOC facilities upgrade: project description

    KOC facilities upgrade Project description Project covers seven oil gathering centres (GCs’) and two gas booster stations (BSs’) Section-I Crude oil processing capacity increase by addition of HP/LP separators, hydro cyclones (de-oiler) in six GC’s and desalter trains in five GCs’. Capacity increase

  74. Slide 74: KOC facilities upgrade

    Slide 74: KOC facilities upgrade

    KOC facilities upgrade Engineering from Sharjah All procurement from Sharjah Construction through single CMEI local subcontractor Kharafi National Consistency check and change management across various stations maintained through project engineering management & discipline leads Sequential shut down

  75. Slide 75: Harweel field development

    Slide 75: Harweel field development

    Petrofac rp) Harweel field development

  76. Slide 76: Harweel field development

    Slide 76: Harweel field development

    Harweel field development Customer Petroleum Development Oman (PDO) Project description Harweel field development, enhanced oil recovery (EOR) project Project type Oil & gas production/treatment Grass roots/tie-ins Scope Engineering, procurement, construction, pre-commissioning, training Award Decem

  77. Slide 77: Ebla gas project surface facilities

    Slide 77: Ebla gas project surface facilities

    Ebla gas project surface facilities

  78. Slide 78: Ebla gas project surface facilities

    Slide 78: Ebla gas project surface facilities

    Ebla gas project surface facilities Customer Petro-Canada Palmyra BV Project Ebla gas project surface facilities Location Palmyra, Syria Scope Engineering, procurement, construction, commissioning and start-up Commenced March 2008 Completion April 2010 Contract value US$477 MM

  79. Slide 79: Ebla gas project surface facilities: overview

    Slide 79: Ebla gas project surface facilities: overview

    Ebla gas project surface facilities Overview The scope comprises engineering, procurement, construction, commissioning and start-up of: – gas treatment plant producing 80 MMSCFD of sales gas – gas gathering station – flow lines and pipelines, connecting well sites and gas gathering stations with the

  80. Slide 80: Hasdrubal gas plant

    Slide 80: Hasdrubal gas plant

    Petrofac rp) Hasdrubal gas plant

  81. Slide 81: Hasdrubal gas plant

    Slide 81: Hasdrubal gas plant

    Hasdrubal gas plant Customer BG Tunisia/ETAP Contractor Petrofac E&C Project type Gas processing / LPG & Condensate Export Location Hasdrubal, Tunisia Scope Engineering, procurement, construction and commissioning Award November 2006 Schedule Ready for hydrocarbon introduction, 29 months Contract va

  82. Slide 82: Hasdrubal gas plant, plant capacity

    Slide 82: Hasdrubal gas plant, plant capacity

    Hasdrubal gas plant, plant capacity Input 120 MMSCFD of raw gas and gas condensate/oil Product 15,000 BPD of stabilised condensate and oil 400 TPD butane and propane 98.6 MMSCFD of lean gas

  83. Slide 83: Khalda gas processing plant

    Slide 83: Khalda gas processing plant

    Petrofac rp) Khalda gas processing plant

  84. Slide 84: Khalda gas processing plant

    Slide 84: Khalda gas processing plant

    Khalda gas processing plant Customer Khalda Petroleum Company Project type Gas production/treatment/grass roots Scope Salam gas trains 3 &4 (SGT 3/4) Engineering, procurement, construction, commissioning and initial operations Award October 2006 Schedule 25 months (original) Value Approx $400 millio

  85. Slide 85: Khalda gas processing plant: key features

    Slide 85: Khalda gas processing plant: key features

    Khalda gas processing plant Key features Fast-track project, 25 months from award to gas in Full PDMS plant modelling Adjacent to existing operating facilities (SGT-1 & 2) – construction safety – SIMOPS / (O&M) High pressure (separation) – 110 bar Tie-ins from SGT-3 & 4 to existing plant – completed

  86. Slide 86: In Salah gas compression

    Slide 86: In Salah gas compression

    Petrofac rp) Cc o yy rd) L fo = O U W) o fe) < A =

  87. Slide 87: In Salah gas compression

    Slide 87: In Salah gas compression

    In Salah gas compression Customer ISG (joint venture), Sonatrach 35%, BP 33%, Statoil, 32% Contractor Petrofac E&C Project type Compression project Location Three sites, Teg, Reg & Krechba 600 km from Hassi Messaoud, Algeria Scope Engineering, procurement, construction, utilities commissioning, proc

  88. Slide 88: In Salah gas compression

    Slide 88: In Salah gas compression

    In Salah gas compression Reg and Teg Addition of further field separation and cooling Two parallel trains of gas turbine driven compression Associated utilities, air compressor package, nitrogen package, HP flare system, 3.8MW GTUG) Krechba Addition of further field separation and cooling Single tra

  89. Slide 89: Engineering services

    Slide 89: Engineering services

    Petrofac rp) Engineering services

  90. Slide 90: Engineering services

    Slide 90: Engineering services

    Engineering services Successful delivery of – consultancy – FEEDs – detailed engineering – PMC/EPCM A differentiated offering to Engineering Services customers based on Petrofac’s unique combination of LSTK EPC, operations management, training and asset management capabilities

  91. Slide 91: Engineering Services, structure

    Slide 91: Engineering Services, structure

    Engineering Services, structure Woking Mumbai Chennai >500 personnel >500 personnel >400 personnel Consultancy Detailed Detailed engineering support engineering support FEED to Sharjah to Sharjah, Woking Detailed design and Aberdeen PMC/EPCM

  92. Slide 92: Engineering services, Woking

    Slide 92: Engineering services, Woking

    Engineering services, Woking Currently occupying four office locations, allowing capacity for >800 personnel Extend offering for engineering and project management services in other geographic regions such as Middle East, North Africa, West Africa, and CIS Continued expansion into higher volume mark

  93. Slide 93: Engineering services, current project, Karachaganak

    Slide 93: Engineering services, current project, Karachaganak

    Engineering services, current project, Karachaganak Project Karachaganak Phase III FEED, Kazakhstan Customer KPDL Duration October 2006 – December 2008 Scope Front end engineering design (FEED) FEED for the construction of new facilities for the Phase III expansion project of the Karachaganak field.

  94. Slide 94: Engineering services, current project, Kharyaga

    Slide 94: Engineering services, current project, Kharyaga

    Engineering services, current project, Kharyaga Project Kharyaga Phase III project Customer Total E&P Russia Duration December 2007 – December 2008 Scope Front end engineering design (FEED) Basic Design (TEO-C) The Phase III development will ensure the facilities maintain oil production at the prese

  95. Slide 95: Engineering services, Mumbai and Chennai

    Slide 95: Engineering services, Mumbai and Chennai

    Engineering services, Mumbai and Chennai Supports delivery of proposal and project work for Sharjah, Woking and Aberdeen Centre of excellence for detailed engineering and 3D modelling Operates with the same business management system as Sharjah and Woking – certified to ISO 9001 Strong resource base

  96. Slide 96: Offshore engineering

    Slide 96: Offshore engineering

    Petrofac rp) Offshore engineering

  97. Slide 97: Offshore engineering, introduction

    Slide 97: Offshore engineering, introduction

    Offshore engineering, introduction Enhanced service line offering for 2009 Market research and customer surveys indicate Petrofac can readily build on excellent E&C reputation to participate in $10billion pa offshore capex market Based in Woking - synergies and resource share with existing E&C engin

  98. Slide 98: Offshore engineering, strategy

    Slide 98: Offshore engineering, strategy

    Offshore engineering, strategy Leading offshore engineering team in Woking will be grown and supported by E&C engineering, offshore operations and brownfield engineering. More intensive business development and marketing programme Q1 2009 Pursue reimbursable FEED engineering projects Build capabilit

  99. Slide 99: Offshore engineering, strategy

    Slide 99: Offshore engineering, strategy

    Offshore engineering, strategy We will consider cost effective strategic acquisition opportunities to accelerate growth and build competency/specialist expertise Utilise Petrofac lower cost engineering centres EPC projects effectively lead to additional negotiated business opportunities for Petrofac

  100. Slide 100: Offshore engineering, market

    Slide 100: Offshore engineering, market

    Offshore engineering, market Focus is on international oil and gas companies and national oil companies Major offshore projects – brownfield (field development) – greenfield (new build/conversion) – abandonment/decommissioning Specific regions – North Sea – Middle East – South East Asia – West Afric

  101. Slide 101: Offshore engineering, projects

    Slide 101: Offshore engineering, projects

    Offshore engineering, projects Petrofac Energy Developments offshore project, examples – Cendor Phases I and II, Malaysia – West Don and Don Southwest, UK North Sea

  102. Slide 102: Offshore engineering: Cendor

    Slide 102: Offshore engineering: Cendor

    Offshore engineering Acquisition date, 2004 Partners, Petronas Carigali, Kufpec, PetroVietnam Petrofac working interest, 30% and operator Field description: – Location offshore Peninsular Malaysia (Block PM304) – Formation, miocene – Reservoir depth 1,600 metres TVD, average well depth 2,900 MD – Re

  103. Slide 103: West Don and Don Southwest

    Slide 103: West Don and Don Southwest

    Offshore engineering West Don and Don Southwest

  104. Slide 104: Offshore engineering – West Don and Don Southwest

    Slide 104: Offshore engineering – West Don and Don Southwest

    Offshore engineering – West Don and Don Southwest Petrofac as licence holder and field operator has managed every element of the project delivery from subsurface evaluation and concept development, through regulatory engagement to detailed engineering, drilling, execution and ultimately operation of

  105. Slide 105: Offshore engineering - summary

    Slide 105: Offshore engineering - summary

    Offshore engineering - summary Natural market progression for Petrofac Utilise extensive and differentiated in-house expertise Market is ready for an innovative new participant Build from low cost reimbursable business to full EPC project capability Established Petrofac presence in target offshore r