  1. Slide 1: South Africa Region

    South Africa Region CER] Ficvos

  2. Slide 2: Overview

    Overview Gold Production and NCE Margin (2008 – 2011) koz % 2 500 16 KDC 14 Pretoria 2 000 South Deep Johannesburg 12 Beatrix 1 500 10 Bloemfontein 8 Durban 1 000 2 066 2,066 2 095 2,095 1,866 6 4 500 2 Cape Town 0 0 2008 2009 2010 2011E Production NCE Margin Mineral Reserves & Resources EBITDA1 (Gr

  3. Slide 3: Multi-shaft underground complexes

    Multi-shaft underground complexes KDC Beatrix South Deep  Formed in 2010 from Driefontein  Shallower, safer, steadier  34.5Moz reserve and >50 years of (West) and Kloof (East) life  Large, challenging, complex and  Well capitalised, consistent  Safer, mechanised mining deep ore body performer

  4. Slide 4: Since 2007 significant progress on safety but 2011 has levelled off

    Since 2007 significant progress on safety but 2011 has levelled off Fatalities1 Serious Injuries1 # fatalities # serious injuries 40 1000 35 900 800 30 700 25 600 20 500 15 400 300 10 200 5 100 0 0 2005 2006 2007 2008 2009 2010 2011YTD 2005 2006 2007 2008 2009 2010 2011YTD 2 ________________________

  5. Slide 5: Redoubling efforts to achieve zero harm...

    Redoubling efforts to achieve zero harm... • Compliance • Engineer out risk • Health & wellness o harm • Aligned stakeholders Goal: Zero • Culture: Hearts & minds 101

  6. Slide 6: ...through numerous initiatives

    ...through numerous initiatives Culture: Hearts Aligned g Health & Engineer g out Compliance and Minds stakeholders wellness risk  Leadership  Engagement with  Holistic approach  Underground  Increased communication unions and to well-being well being – transport safety frequency of and commitm

  7. Slide 7: South African production in decline, plans in place to arrest this

    South African production in decline, plans in place to arrest this Production (‘000oz) South Africa Region production (‘000 ounces) 2 500 B ti Beatrix KDC S th D South Deep 2 000 1 500 1 000 KDC accounts for >90% of the decline since 2009 500 0 2008 2009 2010 2011E 103

  8. Slide 8: Decline due to reduced mineable face length at KDC

    Decline due to reduced mineable face length at KDC % Change (9 months to Sept 2010 vs 9 months to Sept 2011)  Overall gold down 11% driven by − Reduction in face length worked Gold -11% − Decline in g grade =  Mine call factor has been stable Grade (cm.g/t) -3%  Overall productivity maintained de

  9. Slide 9: Plan to stabilise KDC between 250-275koz per quarter

    Plan to stabilise KDC between 250-275koz per quarter  Major investments in developing a safety culture  Business Process Re-engineering Programme (BPR) − Shaft Full Potential (SFP) programme that is already delivering − NCE management helping to mitigate cost inflation in 2011  Focus on surface m

  10. Slide 10: Shaft Full Potential programme: two fundamental drivers

    Shaft Full Potential programme: two fundamental drivers Back to basics... ‘Full potential’ crew productivity Increasing ‘work place availability’  Launched several pilots - already having  Focus on accelerating off and on reef a positive impact development - Continuous blasting - Realising full po

  11. Slide 11: Our cost reduction program has helped offset inflation

    Our cost reduction program has helped offset inflation SA Region Net Cost (R million)  R838 million of cost reductions have helped contained cost escalation below inflation − Wage rates ~9% − Electricity ~27%  Further cost savings identified

  12. Slide 12: KDC production holding steady in 2011

    KDC production holding steady in 2011 Moving closer to 2010 levels KDC average monthly production (‘000 ounces) 140 123 121 120 101 100 90 92 87 80 60 40 20 0 2008 2009 2010 Q1 2011 Q2 2011 Q3 2011 Q4 2011E 107

  13. Slide 13: ~5Moz surface opportunity at KDC

    ~5Moz surface opportunity at KDC KDC and South Deep Surface Resources RD V6# RD V5# RD V2#  Tailings Storage Facilities: KDC West RD 2Vent# ~4.1Moz g gold ((~418 Mt @ RD L10# RD 10 0.3g/t) South Deep RD 8 & 9 RD 13 RD 5 RD 7 RD 11  Surface S f R Rock k Dumps: D RD 12 RD HW# RD 6 ~0.6Moz gold (~30M

  14. Slide 14: Surface mining underpins KDC production profile

    Surface mining underpins KDC production profile Requires acquisition of new plant and KDC surface production de-risked by conversion of existing ones processing tailings and rock dumps Forecast Production 2011E – 2020E (‘000 ounces) 1 • Migrate surface rock dump processing to mobile 200 plant (Pytho

  15. Slide 15: Exploring alternative options for KDC

    Exploring alternative options for KDC KDC West KDC East D7 D10 D8 2 plants; D2 5 operating 3 plants; l t shafts h ft 7 operating shafts D1 K3 D4 D5 K8 K7 Legend Operating shaft EBA Plant Tailings dam 1. Bring forward valuable ounces 2 2. R i Review mining i i areas serveddbby operating ti shafts h f

  16. Slide 16: Beatrix continues to provide predictable stable production

    Beatrix continues to provide predictable stable production A cash generator: R525m free cash flow generated in 9 months to September 2011 Beatrix production profile ((‘000 000 oz)  Consistent stable production from shallow orebody 500  No N significant i ifi seismic i i risk i k 400  Well capital

  17. Slide 17: South Deep – flagship project in the region

    South Deep – flagship project in the region World class reserve well understood Forecast production build-up (koz) 800  Massive ore body: 34.5Moz reserve (>50 years of life) 700  High tech, safer, mechanised bulk mining 600 500  Mine design that has cracked the deep level bulk 400 300 mining code

  18. Slide 18: Ventilation shaft deepening

    Ventilation shaft deepening 80% complete complete, on budget and on time; commissioning planned July 2012 113

  19. Slide 19: Ventilation shaft equipping & headgear

    Ventilation shaft equipping & headgear Headgear A-Frame early lift strategy Completed in May 2011 Rock winder installation progressing to plan – all major components manufactured and delivered to the mine 114

  20. Slide 20: Tailings storage facility

    Tailings storage facility Return Water Dam – lining complete in No.2 TSF – tailings deposition to cover the toe drains is in progress Pump station No.1 No.2 Penstock - returning water to fill the return water dam Return Water Dam – compartment No.2 being filled 115

  21. Slide 21: Backfill infrastructure

    Backfill infrastructure Full Plant Tailings – Backfill plant under construction at South Shaft 116

  22. Slide 22: Plant expansion

    Plant expansion 450ktpm downstream processing capacity Leach extension earthworks Leach extension earthworks Elution earthworks Elution earthworks Thickener earthworks 330ktpm milling capacity Thi k Thickener earthworks th k 117

  23. Slide 23: Mining philosophy

    Mining philosophy Mining a massive orebody at depth De-stress mining Backfilling Large backfilled stope Mechanisation Mechanisation 118

  24. Slide 24: Combined mining methods

    Combined mining methods 3D View of planned mining Drifts Long hole stoping t i Drives De-stress Stope Drives De-stress Stope Access Drives 119

  25. Slide 25: De-stress accelerating, being de-risked with more access points

    De-stress accelerating, being de-risked with more access points South Deep De-stress mining (m2)  Enhanced understanding of the ore 8 000 body, logistics, and skills required 6 000  Increasing number of access points in place to lower delivery risk 4 000  Mining methodology proven; seismicity man

  26. Slide 26: South Africa Region: the way forward

    South Africa Region: the way forward  Targeting stable production of 250-275koz per quarter from KDC − On-going optimisation − Surface mining to de-risk production profile − Numerous options under review  Steady consistent production from Beatrix  Ramp-up Ramp up at South Deep  Critical enablers

  27. Slide 27: Sustainable steady state production

    Sustainable steady state production ~ 2Moz South Deep ramp-up 700koz run-rate ~ 1.7Moz Beatrix stable at by end 2015 ~350kozpa Beatrix ~355koz KDC stabilised at South Deep 1 to 1.1Moz* ~280koz KDC ~1.1Moz Current 2015 Target _________________________ * Anticipated annual production over next 3 to 5