  1. Slide 1: Nuclear Generation

    Analyst Meeting 2013 Nuclear Generation Dhiaa Jamil, Executive VP and Chief Nuclear Officer

  2. Slide 2: Key takeaways

    Key takeaways – Duke Energy has a best-in-class track record of nuclear performance supported by our operating model – Positioned for fleetwide investments to achieve operational excellence and gain efficiencies – Will maintain new nuclear as an option for future portfolio diversity 24 | Analyst Mee

  3. Slide 3: Duke Energy's 10.5 GW regulated nuclear generation fleet

    Duke Energy’s 10.5 GW regulated nuclear generation fleet (1) 11 units at 6 sites in the Carolinas McGuire Nuclear Station Harris Nuclear Plant Brunswick Nuclear Plant Huntersville, N.C. New Hill, N.C. Southport, N.C. Crystal River Nuclear Plant Catawba Nuclear Station Crystal River, Fla. York, S.C.

  4. Slide 4: Operational Excellence: Continuous measurement of nuclear KPIs to drive accountability and performance

    Operational Excellence: Continuous measurement of nuclear KPIs to drive accountability and performance 2008 2009 2010 2011 2012 Key Performance Indicator Legacy Legacy Legacy Legacy New (KPI) Duke Duke Duke Duke Duke (1) Personal Safety (TISAR) Radiological Safety (Dose) Nuclear Safety (Scrams) Capa

  5. Slide 5: Nuclear fleet optimization – integration of operating organizations and governance/oversight

    Nuclear fleet optimization – integration of operating organizations and governance/oversight Chief Nuclear Officer Operations Governance & Oversight Working together to integrate the organizational and functional models 27 | Analyst Meeting 2013

  6. Slide 6: Focused on targeted investments

    Focused on targeted investments Cumulative Targeted Performance NRC Fukushima Investment ’13 -’15 Improvement Requirements Capital ~$175M ~$500M O&M ~$50M ~$100M Total ~$225M ~$600M Fleetwide performance focus NRC Fukushima requirement focus – Strategic hiring of new employees – Ability to cope with

  7. Slide 7: Crystal River nuclear plant update

    Crystal River 3 nuclear plant update – Retirement announced Feb. 5, 2013 – Selected SAFSTOR (safe storage) method for decommissioning – Decommissioning will occur over 40-60 years; covered by Nuclear Decommissioning Trust Next Steps By March File notification to NRC of cessation of operations and fi

  8. Slide 8: Maintain new nuclear as an option for future capacity

    Maintain new nuclear as an option for future capacity – Continue support of the NRC combined construction and operating license applications – Continue to explore regional generation partnership opportunities – Support development of regulatory mechanisms to recover nuclear financing costs during co

  9. Slide 9: Key takeaways

    Key takeaways – Duke Energy has a best-in-class track record of nuclear performance supported by our operating model – Positioned to make fleetwide investments to achieve operational excellence and gain efficiencies – Will maintain new nuclear as an option for future portfolio diversity 31 | Analyst

  10. Slide 10: Appendix materials

    Appendix materials A-1 | Analyst Meeting 2013

  11. Slide 11: Nuclear refueling outages

    Nuclear refueling outages 2012 2013 2014 2015 Actual Planned Planned Planned Brunswick 1 Brunswick 2 Catawba 1 Catawba 2 Harris McGuire 1 McGuire 2 Oconee 1 Oconee 2 Oconee 3 Robinson Total Number of Outages 8 6 6 7 A-2 | Analyst Meeting 2013