  1. Slide 1: Corporate Presentation

    Corporate Presentation November 2015 ShaMaran – A Lundin Group Company

  2. Slide 2: Strategy: Return value to shareholders

    Strategy: Return value to shareholders  Focus on project execution to get to Atrush first oil • Four wells ready for production • Pipeline contract signed in November 2015 • Facilities commissioning in Q2 2016 with first oil mid 2016 • Challenging Kurdistan environment continues to put pressure on

  3. Slide 3: Atrush block in Iraqi Kurdistan

    Atrush block in Iraqi Kurdistan  Awarded in 2007 Atrush  ShaMaran acquired interest in 2010  Discovered Atrush in 2011 Kurdistan  Partners / working interests • Shamaran / 26.8% • Taqa (Operator) / 53.2% • Marathon / 20% • KRG / up to 25% right to back in • In March 2013 the KRG gave notice of i

  4. Slide 4: Atrush world class large oil discovery

    Atrush world class large oil discovery  Discovered in 2011  Jurassic fractured carbonate  Large 25x3 km structure • fault bounded - 3 way dip closed  Resources (as at 31 December 2014) MMBoe 1P/C 2P/C 3P/C Gross Reserves 31.2 61.5 121.0 Gross Contingent 186 310 452 Gross Prospective 121 173 247

  5. Slide 5: Well tests show excellent productivity

    Well tests show excellent productivity Medium oil column • ~420 m 25o-27oAPI oil column 9,059 bopd 27oAPI • Excellent productivity • Communication east-west 8,200 bopd • No formation water on test 26oAPI • Good vertical communication • Proven in Upper Jurassic and Lower 4,200 bopd Jurassic Mus forma

  6. Slide 6: Atrush Phase 1 development ongoing

    Atrush Phase 1 development ongoing  FDP Phase 1 approved in October Atrush block boundary 2013  Phase 1 starts development of Phase 1 western part of the field  Central Processing Facilities to Further Phases handle 30,000 bopd under Saikhan block construction  4 wells ready for production • CK-

  7. Slide 7: Atrush Phase 1 production facilities

    Atrush Phase 1 production facilities  Modular concept with provisions to expand and replicate. Capable of handling liquid rates of 30,000 bopd, initially  Maximize gas utilization. Minimize sour gas flaring with provisions for future sulphur recovery, power generation, etc. ShaMaran – A Lundin Gro

  8. Slide 8: Project progress

    Project progress April 2015 October 2015 ShaMaran – A Lundin Group Company 8

  9. Slide 9: Project Status – Process area

    Project Status – Process area  Process area construction progressing well ShaMaran – A Lundin Group Company 9

  10. Slide 10: Project Status – Power generation

    Project Status – Power generation  Gas Turbine Generator fully assembled • 2 units installed  Process control room and main sub-station installed ShaMaran – A Lundin Group Company 10

  11. Slide 11: Project Status – Piping

    Project Status – Piping  Pipe rack installation ongoing  Pipe fabrication and welding ongoing ShaMaran – A Lundin Group Company 11

  12. Slide 12: Atrush export

    Atrush export Feeder pipeline Kurdistan Export Pipeline  Atrush crude to be exported via existing Kurdistan Export Pipeline to Fishkabur and on to Ceyhan  Feeder pipeline equipment being mobilised ShaMaran – A Lundin Group Company 12

  13. Slide 13: KRG’s Atrush feeder pipeline

    KRG’s Atrush feeder pipeline  Pipeline EPC contract with KAR Group signed on November 1, 2015 to include: • Pumping station • 6 km 10” section from Production facilities to intermediate pigging station (IPPR) • 2 km 12” section from IPPR to Atrush Block boundary  Agreement with MNR • KRG to instal

  14. Slide 14: Project schedule

    Project schedule  4 wells drilled and ready for production  Substantially all equipment and material procured  Most equipment now installed or in transit to site  Piping installation ongoing  Feeder pipeline work commenced  Cost unchanged from late 2014  Commissioning in second quarter 2016 

  15. Slide 15: Work ongoing to realise full field value

    Work ongoing to realise full field value  Submitted field development plan update in November 2015 • No commitment to further phases of development • Production data needed • Drill CK-7 to appraise centre part of the field • Potential further delineation drilling to the east and west ShaMaran – A L

  16. Slide 16: Kurdistan export update

    Kurdistan export update  KRG continues to export via Ceyhan • October: 439 kbopd from KRG controlled fields, Atrush 156 kbopd from NOC fields (Kirkuk) Kurdistan • Short pipeline outages due to sabotage and theft • October 2015 US court ruling; “There remains no legal obstacle in the United States o

  17. Slide 17: Funding

    Funding  Funding requirements under review and dependent on: • Magnitude and timing of the KRG exercising its right to acquire up to 25% interest • 2016 spending considerations  Further development phases to be funded through production ShaMaran – A Lundin Group Company 17

  18. Slide 18: Corporate profile

    Corporate profile  Share capital  SNM share price on TSX.V • Issued and outstanding 1,579,768,534  Market capitalisation • CAD 103M (@ November 16, 2015)  Major shareholders • Lundin family trusts 19.1% • Columbia Wanger 6.8% • Lundin Petroleum 6.6% • Directors/Management 0.3%  Trading informat

  19. Slide 19: The Lundin Group

    The Lundin Group Combined market cap >$10.9 Billion ShaMaran – A Lundin Group Company 19

  20. Slide 20: Key points

    Key points  Robust Atrush development project  World class resource base • Gross 2P 61.5 MMBoe • Gross 2C 310 MMboe  First oil target mid 2016  Facilities construction ongoing  Pipeline construction started  Looking for new opportunities  Strong Lundin Group support ShaMaran – A Lundin Group

  21. Slide 21: Cautionary statements

    Cautionary statements This document contains statements about expected or anticipated future events and financial results that are forward-looking in nature and, as a result, are subject to certain risks and uncertainties, such as legal and political risk, civil unrest, general economic, market and