APC Minerals Limited · ASX:APC

APC Minerals — Goldphyre Resources — Investor Presentation (March 2016)

22 slides from APC Minerals's investor presentation, March 2016

  1. Slide 1: Currently 100% of Australia's potash is imported

    “CURRENTLY 100% OF AUSTRALIA’S POTASH IS IMPORTED. THE DEVELOPMENT OF A LOCAL SOURCE OF POTASH WOULD BE A SIGNIFICANT WIN FOR AUSTRALIAN FARMERS” Goldphyre Resources Limited Investor Presentation

  2. Slide 2: Corporate Overview

    CORPORATE OVERVIEW FOCUSSED ON STAKEHOLDER RETURN CAPITAL STRUCTURE ASX: GPH BOARD & MANAGEMENT / SHAREHOLDERS SHARES ON ISSUE* 145.9 MATT SHACKLETON EXECUTIVE CHAIRMAN BRENTON SIGGS TECHNICAL DIRECTOR OPTIONS ON ISSUE* 96.5 DEAN GOODWIN NON-EXEC DIRECTOR MARKET CAP @ $0.08 $11.6m CARSTEN KRAUT PRIN

  3. Slide 3: Unique Investment Proposition

    UNIQUE INVESTMENT PROPOSITION AUSTRALIAN POTASH FOR AUSTRALIAN FARMERS • WA brine hosted Sulphate of Potash (SOP) project • Aiming to feed the domestic demand for SOP which is currently 100% imported • Superior mining jurisdiction in the eastern goldfields of WA • Simple, well established brine extr

  4. Slide 4: Lake Wells

    LAKE WELLS LOCATION TRANSFORMATIONAL DEAL BRIEF HISTORY LOGISTICS THE PALAEOCHANNEL EXPLORATION TARGET Goldphyre Resources Limited Investor Presentation

  5. Slide 5: Lake Wells Potash Project

    LAKE WELLS POTASH Lake McKay (Agrimin) CAPEX A$TBD PROJECT 540kms north west of of Alice Springs LD (Reward Minerals) CAPEX A$320m Karinga Lakes (Rum Jungle Resources) 800kms south east of Port Hedland CAPEX A$93m – A$340m 200kms south west of Alice Springs IDEALLY POSITIONED TO Beyondie (Kalium Lak

  6. Slide 6: Transformational Deal

    TRANSFORMATIONAL DEAL LAKE WELLS PROJECT AREA TRIPLED IN SIZE • Transformational deal with one of the industry’s most prominent players • Deal with Mark Creasy owned Lake Wells Exploration Pty Ltd (LWE) announced December 2015*, closes by May 2016 • Triples the size of Goldphyre’s Lake Wells Potash

  7. Slide 7: Brief History

    BRIEF HISTORY RAPID PROGRESS • Q2 2016: Maiden JORC Resource estimate • Q2/Q3 2016: test bore & pumping trials, Going forward …. evaporation pond trials, process test work • Q3 2016: JORC Resource upgrade • Q1 2017: Measured JORC Resource MARCH 2016 estimate Exploration Target* of 6Mt – 37Mt (specif

  8. Slide 8: Regional Infrastructure

    REGIONAL INFRASTRUCTURE Goldphyre’s Lake Wells Potash Project sits adjacent to an air-strip, with road-train capacity haulage roads to the project’s door step GREAT CENTRAL ROAD 90km LAVERTON- STATION LEONORA ROAD 85km ROAD 125km LEONORA RAIL HEAD 280km LOW CAPEX PRODUCTION PATHWAY (TARGETING SUB $1

  9. Slide 9: Exploration Target

    EXPLORATION TARGET SPECIFIC YIELD considers the recoverability of the brine containing potash Exploration target using specific yield 6Mt – 37Mt Of recoverable SOP, at a grade range of 8,900 mg/l – 13,900 mg/L TOTAL POROSITY is a measure of the in-situ brine volume without regard to recoverability E

  10. Slide 10: The Palaeochannel

    THE PALAEOCHANNEL Pumping brine from palaeochannels is a common, simple process Drilling currently underway to upgrade Exploration Target on +40km of palaeochannel BASAL SAND AQUIFER HAS HIGHEST SPECIFIC YIELD Goldphyre Resources Limited Investor Presentation

  11. Slide 11: Goldphyre's Lake Wells Potash Project is a valuable asset in a promising location

    GOLDPHYRE’S LAKE WELLS POTASH PROJECT IS A VALUABLE ASSET IN A PROMISING LOCATION…… • POTASH PROJECTS NEED GRADE AND SCALE ✔ • BULK PROJECTS NEED INFRASTRUCTURE ✔ • EVAPORATION PROJECTS NEED A CONDUCIVE ENVIRONMENT ✔ • TRIED AND TESTED PRODUCTION METHODS DERISK DEVELOPMENT ✔ • BRINE FROM PALAEOCHANN

  12. Slide 12: Derisking Lake Wells

    DERISKING LAKE WELLS Q1 2016 Q2 2016 Q4 2016 Q1 2017 • Incorporate LWE data into exploration target Exploration target data area • n/a • n/a • n/a • COMPLETE • Brine sampling • Collect core for across horizons, Inferred resource porosity and specific geophysics • n/a • n/a yield analysis • PUBLISH R

  13. Slide 13: Derisking Lake Wells

    DERISKING LAKE WELLS Exploration target Inferred resource Indicated resource Measured resource Desktop studies n/a n/a n/a Auger sampling n/a Core drilling n/a Exploration drilling Geophysics Test bores n/a n/a Modelling n/a Environmental n/a n/a Reporting Not started Complete Goldphyre Resources Li

  14. Slide 14: Compelling Opportunity

    COMPELLING OPPORTUNITY IDEALLY POSITIONED FOR RAPID PROJECT DEVELOPMENT AND GROWTH • Very strong grades and scale • Moving quickly towards de-risked JORC Resource Estimates • Drilling currently underway • Well funded for next program of works: test pumping Q3 2016 • Strong and supportive shareholder

  15. Slide 15: New Emerging Potash Player

    NEW EMERGING POTASH PLAYER A$M Market Capitalisation 11 Agrimin AMN 17 Rum RUM 19 SO4 42 Reward RWD 58 0 10 20 30 40 50 60 70 Goldphyre Resources Limited Investor Presentation

  16. Slide 16: Goldphyre Technical

    GOLDPHYRE TECHNICAL POTASH 101 LOGISTICS PROJECT SPECS PROJECT ECONOMICS Goldphyre Resources Limited Investor Presentation

  17. Slide 17: Potash 101

    POTASH 101 Phosphorous Potassium: one of the 3 essential macro-nutrients Nitrogen MACRO NUTRIENTS Sulphate of Potash – SOP: the premium source of K from potash OTHER 10% Potassium SOP 10% GLOBAL CONSUMPTION C. 56MT PER ANNUM POTASSIUM BEARING SALTS & COMPOUNDS ARE CALLED POTASH MOP 80% Goldphyre Res

  18. Slide 18: Potash SOP

    POTASH SOP SOP is produced in several ways: the most expensive is the Mannheim process, the least expensive is through brine-evaporation 3% The average cost of production for a $US200 tonne of SOP from a brine hosted-evaporative operation 29% The average price of a tonne of 50% $US650 SOP fob Vancou

  19. Slide 19: SOP Production

    SOP PRODUCTION SOP held in brine is produced through evaporation Pumping Converting The palaeochannel bore- Schoenite is field pumps brine into converted, or evaporation ponds crystallised, into SOP Evaporating Processing Brines pass through evaporation ponds, dropping out salts along the way Harves

  20. Slide 20: Competent Persons Statements

    COMPETENT PERSONS STATEMENTS The Hydrogeological information in this report has been prepared by AQ2 with direction and review by Jeffery Lennox Jolly. Mr Jolly is a principal hydrogeologist with AQ2 and has over 30 years of international experience. He is a member of the AusIMM and the Internationa

  21. Slide 21: Disclaimer & Forward Looking Statements

    DISCLAIMER & FORWARD LOOKING STATEMENTS This presentation has been prepared by Goldphyre Resources Ltd (“GPH”). It contains background information about GPH current at the date of this presentation. The presentation is in summary form and does not purport to be all inclusive or complete. Recipients

  22. Slide 22: Lake Wells Potash Project

    LAKE WELLS POTASH PROJECT Street: 31 Ord Street, West Perth, Western Australia 6005 E-Mail: m.shackleton@goldphyre.com.au Mobile: + 61 (0) 438 319 841 www.goldphyre.com.au Goldphyre Resources Limited Investor Presentation

Goldphyre Resources — Investor Presentation (March 2016) on 6ix