Slide 1: Canada Water Development Construction Liaison Forum
Canada Water Development Construction Liaison Forum Plots A1 & A2 (and surrounding area) October 2021
Slide 2: Overview of today's presentation
• Introductions • Overview of recent and current works • Progress update on works in Surrey Quays Overview of Shopping Centre car park today’s • Updates from our contractors presentation - Construction of Plot A2 (Mace) - Construction of Plot A1 (Wates) • Update on job and training opportunities
Slide 3: Our presenters
Our presenters SARAH WARD Construction Neighbour Liaison Manager Canada Water Masterplan OLLY MACK EMMALEEN MAYELL Contractor, Wates Contractor, Mace Construction of Construction of Plot A1 Plot A2
Slide 4: Plots A1 & A2
Plots A1 & A2 Plot A1 will provide a new 35-storey building which will include retail, residential and office space. Ground preparation and site setup is under way. Plot A2 will include a leisure centre for Southwark Council at ground and basement level, town centre retail and food outlets along the
Slide 5: Wider Canada Water Development works
Wider Canada Water Development works Plot K1 - Site setup is expected to begin in October / November 2021, which will deliver 79 affordable homes. Demolition of former Rotherhithe Rear of Printworks Police Station site – works are was completed in underway to build a July 2021. basement for a below-
Slide 6: Works in Surrey Quays Shopping Centre car park
Works in Surrey Quays Shopping Centre car park • Mace and Wates are installing hoarding to prepare for the construction of Plots A1 and A2. • The entry/exit point at the Surrey Quays Road/Deal Porters Way junction will be closed overnight on 14th and 15th October to remove the barriers. • Entry and
Slide 7: Site layout and vehicle access
Site layout and vehicle access • The haul road, by the former Rotherhithe Police Station, is shared between Plots A1 and A2 and controlled by Alandale Group. • The entrance to the haul road is on Lower Road. Traffic marshals are located on Lower Road to ensure there is no traffic build up and to ens
Slide 8: Plot A2
‘amine ai “aria 2) 08)
Slide 9: Plot A2 – Overview
Plot A2 – Overview Expected timeframes: Mace took over the site in early October from the enabling works contractors and work is expected to be complete by the end of August 2024. • Plot A2 includes a leisure centre for Southwark Council at ground and basement level, town centre retail and food outl
Slide 10: Plot A2 – Current site activity
Plot A2 – Current site activity • Mace started piling works in early October 2021. • These works will generate some noise and vibration as it involves drilling into the earth to help create a stable structure to strengthen a building’s foundations. • All works are carried out in accordance with the
Slide 11: Plot A2 lookahead
Plot A2 lookahead • Piling works will continue within the footprint of the building in January 2022. • Bulk excavation will start in January 2022 - excavators will be situated around the perimeter of the site (within the site boundary). • Tower crane erection will begin in February 2022. • Community
Slide 12: Plot A1
Wates” iii ono voianniaanna ony i li alin
Slide 13: Plot A1 – Overview
Plot A1 – Overview Expected timeframes: Work began at the end of September 2021 and is expected to be complete by October 2024. • Plot A1 includes 186 residential apartments over a 35 storey tower which includes 178 homes for private sale and 8 homes as shared ownership. • There will be 6 floors of
Slide 14: Plot A1 – Upcoming site activity
Plot A1 – Upcoming site activity • Wates are preparing the foundations for site offices which are expected to complete in late October / early November 2021. • Piling works will begin from w/c 25th October 2021. • Piling will generate some noise and vibration as it involves drilling into the earth t
Slide 15: Plot A1 – Site welfare
Plot A1 – Site welfare • Wates site accommodation will be located on the former Rotherhithe Police Station site which is adjacent to the entrance of the haul road used by construction traffic for Plots A1 and A2. • Wates personnel will enter the A1 site accommodation via a security office located on
Slide 16: Common working practices
Common working practices Standard construction working hours: Environmental monitoring: • Monday – Friday: 8am - 6pm • In line with industry standards and the Construction Management Plans for each development site, environmental • Saturday: 8am - 2pm (no noisy works before management is a critical
Slide 17: Jobs and training opportunities
Jobs and training opportunities • British Land is committed to getting local people into meaningful, sustained employment starting with the opportunities generated by construction. • Mace is delivering training opportunities and jobs for local people, starting this month. • All new vacancies which w
Slide 18: Keeping you informed
Keeping you informed Meet the contractors • Wates and Mace will be making themselves available at a set time and location each month to speak with those who want more information and have questions. These will be advertised via site signage, our e-newsletter and on our website. Printed newsletter: •