Tilt Renewables Limited

Tilt Renewables — Corporate Update (November 2025)

9 slides from Tilt Renewables's corporate update, Nov 11, 2025

  1. Slide 1: Rye Park Wind Farm CCC Meeting

    RYE PARK WIND FARM CCC MEETING 11 NOVEMBER 2025

  2. Slide 2: Contents

    CONTENTS 1. BUSINESS ARISING FROM MINUTES 2. PROJECT UPDATE 3. ENVIRONMENT & COMPLIANCE 4. COMMUNITY ENHANCEMENT FUNDS UPDATE 5. COMMUNITY & STAKEHOLDER ENGAGEMENT UPDATE RPWF CCC Presentation 2

  3. Slide 3: Business Arising from Minutes: CCC Closed Actions

    BUSINESS ARISING FROM MINUTES CCC CLOSED ACTIONS FROM APRIL – NOVEMBER 2025 Action Item Responsible Comments 5 DJ to email Yass Valley Council (Mayor & CEO) to seek further Closed. support for turning off aviation lights DJ 6 Tilt to liaise with Vestas to investigate lighting at base of some Closed

  4. Slide 4: Business Arising from Minutes: CCC Open Actions

    BUSINESS ARISING FROM MINUTES CCC OPEN ACTIONS – NOVEMBER 2025 Action Item Responsible Due By Comments 8 Dilapidation Surveys – Tilt to confirm details of Next meeting Dilap surveys not public documents. Have the Yass Street Survey, including results & forwarded concerns to council regarding two Til

  5. Slide 5: Project Update

    PROJECT UPDATE How we are doing so far • Bushfire preparation activities  RFS site visit in September  Other activities include inspection of access roads, review emergency plans, emergency drills • 2nd year annual service and inspections ongoing • Civil work complete on minor erosion along with i

  6. Slide 6: Environment & Compliance

    ENVIRONMENT & COMPLIANCE Biodiversity Management • On-site rehabilitation activities are complete • Ongoing monitoring until success criteria is met • Bird and bat monitoring • Year 1 complete • Year 2 to commence in November • First annual report will be published Q1 2026. Modification Application

  7. Slide 7: Community Enhancement Funds

    COMMUNITY ENHANCEMENT FUNDS Community Enhancement Funds update • Yass Valley Council • $27,500 + FY 25/26 available = $55,413.29 available to distribute • 25/26 round applications evaluated on 10/11/25 • Hilltops Council • 25/26 round applications evaluated on 11/11/2025 • Upper Lachlan Shire Counci

  8. Slide 8: Community & Stakeholder Engagement

    COMMUNITY & STAKEHOLDER ENGAGEMENT Communications • Annual newsletter – next edition to be distributed in December 2025 • Council briefings • Hilltops Council – 8 October • Aiming to provide briefings to Yass Valley and Upper Lachlan Shire Councils later in the year Complaints and Enquiries • Direct

  9. Slide 9: Thank you – please complete our engagement survey

    THANK YOU – PLEASE TAKE 5 MINUTES TO COMPLETE OUR ENGAGEMENT SURVEY RPWF CCC Presentation 9