  1. Slide 1: 2011 interim results

    2011 interim results 4 August 2011

  2. Slide 2: Cautionary statement

    Cautionary statement This presentation has been prepared by Rio Tinto plc and Rio Tinto Limited (“Rio Tinto”) and consisting of the slides for a presentation concerning Rio Tinto. By reviewing/attending this presentation you agree to be bound by the following conditions. Forward-looking statements T

  3. Slide 3: Jan du Plessis, Chairman

    Jan du Plessis Chairman Bengalla

  4. Slide 4: Tom Albanese, Chief executive

    Tom Albanese Chief executive Grande-Baie, Quebec

  5. Slide 5: Continued improvement in safety

    Continued improvement in safety Injury frequency rates 2002–2011 H1 Per 200,000 hours worked 4 August 2011 Rio Tinto 2011 interim results 5

  6. Slide 6: 2011 first half highlights

    2011 first half highlights • Record first half underlying EBITDA and earnings from higher prices • Record first half cash flows from operations • Recovering from challenging first quarter weather events • Growth projects progressing well – Pilbara expansion accelerates – Riversdale acquisition compl

  7. Slide 7: Volatility expected to continue

    Volatility expected to continue Commodity market prices • First half prices considerably (Daily spot price index (1 January 2010=100)) higher than 2010 • Generally positive outlook for metals and minerals prices – Global growth expected to average 3.5% in 2011 – Chinese GDP to expand by 9.5% in 2011

  8. Slide 8: Iron ore recovers from severe weather

    Iron ore recovers from severe weather • Stable and strong prices reflect Iron ore underlying result (US$bn) robust demand and weak supply growth • Significant weather disruptions in first half – Shipments lower following train derailment – Production rebounded in Q2 • Pilbara expansion to 225 Mt/a c

  9. Slide 9: Clear pathway for 454 Mt/a global capacity

    Clear pathway for 454 Mt/a global capacity • Pilbara 333 Mt/a accelerated by six Car Dumpers (x2) months to H1 2015 • Headcount at site to double in 1.8 km second half Existing Cape 2.5km Lambert Port • Proven track record of delivery Tug harbour – Capital expenditure remains on A$ budget 1st 53 Mt/

  10. Slide 10: Targeting long-term margin transformation in Aluminium by 2014

    Targeting long-term margin transformation in Aluminium by 2014 Aluminium underlying result • Increased first half prices due to (US$bn) tight physical market • Results impacted by exchange rates and higher input costs for caustic, coke and pitch • Bauxite & Alumina affected by wet weather in Queensl

  11. Slide 11: Lower Copper grades: recovery expected in 2012

    Lower Copper grades: recovery expected in 2012 Copper underlying result • Strong pricing continues (US$bn) – Market finely balanced – Disruptions to global supply, including recent labour disputes • Lower volumes from dip in grades at all three major operations • Recovery in copper production expect

  12. Slide 12: Advancing world class copper projects

    Advancing world class copper projects Oyu Tolgoi • Construction almost 1/3 complete • Workforce to peak this year at 14,000 • Training programs developing Resolution • $103 million newly approved • Encouraging drill results La Granja • 30,000 meter drilling programme 50% complete • Promising interse

  13. Slide 13: Significant disruptions from weather events at Energy operations

    Significant disruptions from weather events at Energy operations Energy underlying result • Strong coal prices following (US$bn) significant supply disruptions • Queensland operations recovering from force majeure • Expansions in the Hunter Valley progress • Mt Pleasant decision due towards the end

  14. Slide 14: Riversdale acquisition successfully completed

    Riversdale acquisition successfully completed • Tier one hard coking coal Car Dumpers (x2) resources in Mozambique • Benga (65% Rio Tinto, 35% Tata 1.8 km Steel) Existing Cape 2.5km Lambert Port – First exports planned end 2011 Tug harbour – Growth potential beyond 10Mt/a – 60% hard coking, 40% ther

  15. Slide 15: Rapidly improving demand environment for Diamonds & Minerals

    Rapidly improving demand environment for Diamonds & Minerals Diamonds & Minerals underlying result • Strong pricing environment (US$bn) – Continued strong demand for borates and TiO2 – Improved market conditions for diamonds – TiO2 contracts steadily being replaced with shorter-term mechanisms • Hea

  16. Slide 16: Guy Elliott, Chief financial officer

    Guy Elliott Chief financial officer Richards Bay Minerals rehabilitation

  17. Slide 17: Record first half earnings

    Record first half earnings Underlying earnings 2010 first half vs 2011 first half ($m) Note: Exploration and evaluation variance includes $229 million decrease in gain on undeveloped property sales (+$229 million gain in H1 2010 from sale of undeveloped coal properties) 4 August 2011 Rio Tinto 2011

  18. Slide 18: Earnings cash cost performance driven by rising input prices and weather events

    Earnings cash cost performance was driven by rising input prices and weather events Breakdown of cash cost variance • Unit cost efficiency impacted by lower volumes • Maintenance cost and volumes Other production effected by weather events and one-offs Input prices ($182m) and other • Mining and loc

  19. Slide 19: Outstanding cash flow generation

    Outstanding cash flow generation 2011 first half cash flows Half yearly operating cash flows ($bn) ($bn) Other: $0.5bn Interest: $0.3bn Dividends from EAUs Increase in net debt Cash flows from and other Tax: $3.7bn consolidated operations inflows: $5.3bn Dividends: $1.2bn Buyback: $2.4bn Cash flows

  20. Slide 20: Capital expenditure ramping up

    Capital expenditure ramping up •Ramp up in major project growth capex expected to continue •Increasing levels of capital investment over the medium term Simfer payment •Major projects progressing well •Some spend delays due to weather interruptions in first half •Increasing procurement activity and

  21. Slide 21: Capital cost estimates revised for strengthening of Australian dollar

    Capital cost estimates revised for strengthening of Australian dollar Pilbara infrastructure to 283Mt/a Yarwun 2 (Control budget A$bn) (Control budget A$bn) 4 August 2011 Rio Tinto 2011 interim results 21

  22. Slide 22: Industry supply response remains challenged

    Industry supply response remains challenged 2011 Lead time outlook • Equipment lead times are increasing Equipment type 0 1 2 3 (years) • Resource nationalism will slow Grinding mills investment in growth Draglines Barges • Project financing challenged in Locomotives current volatile markets Generat

  23. Slide 23: Balancing growth with capital returns

    Balancing growth with capital returns • More than $10 billion of high quality investments in first half Cash from operations • Capital expenditure ramping up • Regained single A credit rating • Capital return programme increased by $2 billion to $7 billion to be completed by end of Q1 2012 Investmen

  24. Slide 24: Tom Albanese, Chief executive

    Tom Albanese Chief executive Oyu Tolgoi construction site

  25. Slide 25: Shift in metals consumption towards the developing world continues

    Shift in metals consumption towards the developing world continues GDP per capita by region Building height categories RMB thousand Floors, steel intensity (kg/m2) < 100 F Steel intensity (high-end) Steel intensity (low-end) < 50 F < 32 F < 18 F < 12 F <8F Average 5-40 40-50 50-70 60-100 80-120 110-

  26. Slide 26: $26 billion of major capital projects underway

    $26 billion of major capital projects underway Project timeline(1) % Complete $ Capex(2) Production $91m +5mtpa $284m +5mtpa $763m +5.3mtpa $2.1bn 15mtpa(4) $7.3bn (3) +53mtpa $1.1bn 15mtpa(4) $166m(5) Access high grade ore $6bn +100ktpd ore $340m 30mlb Ph1, 60mlb Ph2 (capacity) $469m +17kt Ni, 13kt

  27. Slide 27: High quality tier one projects currently in advanced study

    High quality tier one projects currently in advanced study Indicative Indicative first Indicative Project Product capex(1) production production(1) Nammuldi (Pilbara 283) Iron ore $ 2013 NA Pilbara 333 Iron ore $$ 2015 +50mtpa IOCC Phase 3 Iron ore $ 2013 +2.7mtpa Simandou Iron ore $$ 2015 +95mt

  28. Slide 28: Deep portfolio of strong earlier stage projects

    A deep portfolio of strong earlier stage projects provide options for further quality growth • Pilbara 433mtpa Iron Ore • Orissa • IOCC expansions • Resolution • KUC North Rim Skarn Copper • La Granja • Northparkes expansion • Escondida options • AP60 Phase 2 • Armargosa (bauxite) Aluminium • Sarawa

  29. Slide 29: Investment in technology and exploration gives competitive edge

    Our investment in technology and exploration gives us competitive edge Exploration drill rig Iron Ore Operations Centre, Perth Mine planning Driverless trucks, Pilbara 4 August 2011 Rio Tinto 2011 interim results 29

  30. Slide 30: Record results – global expansion options grow

    Record results – global expansion options grow • Record first half earnings, EBITDA and operating cash flow • Strong demand outlook with continued volatility, strong currencies and higher input prices • $10 billion of high quality investment in first half • World class growth programme gathering mom

  31. Slide 31: 2011 interim results

    2011 interim results 4 August 2011

  32. Slide 32: Breakdown of price variance

    Breakdown of price variance Earnings impact from price $9,496 million ($m) Traded Non-traded 4 August 2011 Rio Tinto 2011 interim results 32

  33. Slide 33: Breakdown of volume variance

    Breakdown of volume variance Earnings impact from volumes $782 million ($m) 4 August 2011 Rio Tinto 2011 interim results 33

  34. Slide 34: Reconciliation of underlying to net earnings

    Reconciliation of underlying to net earnings $m 2010 Underlying earnings 7,781 Net impairment charges (147) Exchange differences and gains on derivatives 63 Other (110) Net earnings 7,587 4 August 2011 Rio Tinto 2011 interim results 34

  35. Slide 35: Modelling earnings

    Modelling earnings Impact on full year 2010 average underlying earnings Earnings sensitivity price/rate ($m) Copper 426c/lb +/-43c/lb 324 Aluminium $2,551/t +/-$255/t 737 Gold $1,447/oz +/-$145/oz 64 Molybdenum $18/lb +/-$1.8/lb 54 Iron ore +/-10% 1,710 Coal* +/-10% 318 A$ 103 USc +/-US10.3USc 846 C

  36. Slide 36: Net debt: definition change from 2011

    Net debt: definition change from 2011 • The Group’s net debt definition has been modified, such that it is now stated net of adjustments for funding arrangements relating to certain Equity Accounted Units (EAUs) and consolidated operations. • This avoids including borrowing liabilities twice, where

Rio Tinto — H1 2011 Earnings Presentation on 6ix