Slide 1: Park Elektrik Üretim Madencilik Sanayi ve Ticaret A.Ş.
Park Elektrik Üretim Madencilik Sanayi ve Ticaret A.Ş. March 2013

Slide 2: Contents
Contents I. Park Elektrik Overview 3 II. Ciner Group in Brief 7 III. Operations 10 IV. Reserves 13 V. Shift To Open Pit Mining 17 VI. Planned Investments 23 VI. Financial Structure 27 VII. Evaluation of The Latest Financial Tables 36 VIII. Corporate Governance Rating 42 Park Elektrik Madencilik Marc

Slide 3: I. Park Elektrik Overview
I. Park Elektrik Overview Park Elektrik Madencilik March 2013 3

Slide 4: The Company
The Company Initially offered to public in 1997, Park Elektrik is the sole copper mining company on the ISE. The company currently operates two mines namely; a copper mine in Siirt and an asphaltite (a kind of hydrocarbon) mine in Sırnak. Making up 90% of total sales revenues, concentrated coppe

Slide 5: Ownership Structure
Ownership Structure Others 32% Park Holding 61% Turgay Ciner 7% Park Elektrik Madencilik March 2013 5

Slide 6: Participation, Park Termik
Participation, Park Termik Park Elektrik has 10% stake in Park Termik Elektrik San. ve Tic. A.S., a Ciner Group company which is involved in thermal power generation in Çayırhan, Ankara. Park Termik operates Çayırhan Thermal Power Plant which has a total production capacity of 620 MW, in four un

Slide 7: II. Ciner Group in Brief
II. Ciner Group in Brief Park Elektrik Madencilik March 2013 7

Slide 8: Ciner Group, Main Line of Businesses
Ciner Group, Main Line of Businesses Ciner Group Park Holding Ciner Yayın Holding Energy & Mining Commerce, Media Group Industry & Group Services Group Major Companies Major Companies Major Companies Park Elektrik, Park Ciner Marine, & Brands Termik, Silopi Elektrik, Ciner Aviation, Haberturk Newspa

Slide 9: Ciner Group, Introduction
Ciner Group, Introduction Park Holding, the main shareholder of Park Elektrik with 61% share, is solely owned by Mr. Turgay Ciner. Ranking among the largest Groups of Turkey, Ciner Group’s history goes back to 1978 when it was founded. The Group has a diversified business portfolio. However, the

Slide 10: III. Operations
III. Operations Park Elektrik Madencilik March 2013 10

Slide 11: Park Elektrik's Existing & Planned Facilities
Park Elektrik’s Existing & Planned Facilities Natural Gas Power Plant Edirne Copper Mine Siirt HPP Natural Gas Diyarbakı Asphaltite Power Plant r Mine Adana Sırnak Park Elektrik Madencilik March 2013 11

Slide 12: I) Madenköy Copper Zone
I) Madenköy Copper Zone Park Elektrik acquired operation license of Madenkoy copper mine in 2004 from Eti Holding, a state-owned entity engaged in mining businesses, for TL9.4 mn. Mine operations started in late 2006 in the copper zone. So far, around 5.1 mn tons of ore was extracted in the copp

Slide 13: Micromine Reserve Report Based On JORC
Micromine Reserve Report Based On JORC According to a JORC (Joint Ore Resources Code) compliant reserve report issued by Micromine Consulting Services in November 2011, based on the drilling and sampling works by Eti Holding (1981), Preussag AG Metall (1988) and Park Elektrik, the total reserves o

Slide 14: Capacity Expansion & Condemnation
Capacity Expansion & Condemnation Concentration Facility 2011 2012 2013 Ore Processing Capacity (ton) 750,000 1,200,000 1,800,000 * Capacity increase to 1,2 mn tons was realized in October 2011. In parallel with growing reserves in the Madenkoy copper zone, the company increased its concentration

Slide 15: 2012 Monthly Production Figures
2012 Monthly Production Figures JAN. FEB. MAR. APR. MAY JUNE JULY AUG. SEP. OCT. NOV. DEC. TOTAL Utilized Ore (wmt) 100.191 84.912 96.148 102.127 104.014 102.232 91.266 75.655 95.524 102.177 97.767 86.128 1.138.141 Produced Ore (dmt) 95.181 80.666 91.340 97.020 98.813 97.206 86.703 71.872 90.748 97.

Slide 16: Production Volumes & Targets
Production Volumes & Targets 2011 2012 2013E Ore (tons, wet) 973,628 1,213,013 1,500,000 Growth - 25% 24% Concentrated Copper (wmt) 77,510 89,253 105,000 Growth - 15% 18% Park Elektrik Madencilik March 2013 16

Slide 17: Shift To Open Pit Mining & Stripping Expenses
Shift To Open Pit Mining & Stripping Expenses Adopting underground mining since the beginning of operations in the Madenköy copper zone, Park Elektrik plans to shift its copper mining operations from underground to open-pit mining by the mid of 2013, while until mid of the year underground mining

Slide 18: 2013 Estimated Expenses In Copper Zone
2013 Estimated Expenses In Copper Zone Expenses TL mn ORE PRODUCTION 88 - Stripping 82 - Others 6 FACILITY 30 OTHER 26 TOTAL 144 Park Elektrik Madencilik March 2013 18

Slide 19: Open Pit Topographic View – I
Open Pit Topographic View – I Topography Main Ore Body Park Elektrik Madencilik March 2013 19

Slide 20: Open Pit Topographic View - II
Open Pit Topographic View - II Main Ore Body Park Elektrik Madencilik March 2013 20

Slide 21: II) Silopi Asphaltite Zone
II) Silopi Asphaltite Zone Asphaltite is a petroleum-origin hydrocarbon with a thermal value of 5,500-5,800 kcal/kg. Park Elektrik has the operational rights of Silopi asphaltite mine until 2033. Estimated asphaltite reserve in Silopi is around 35 mn tons based on Turkish Coal Enterprise (TKI) r

Slide 22: Open-Pit Mining in Silopi
Open-Pit Mining in Silopi Park Elektrik Madencilik March 2013 22

Slide 23: IV. Planned Investments
IV. Planned Investments Park Elektrik Madencilik March 2013 23

Slide 24: Diyarbakır HPP
Diyarbakır HPP Installed capacity will be 50.5 MW. Production license is valid for 49 years. According to recent feasibility studies, estimated investment amount is US$ 100 mn. The compay plans to start HPP investment in the second half of 2013 with an estimated investment amount of TL27mn f

Slide 25: Ceyhan Natural Gas Power Plant
Ceyhan Natural Gas Power Plant Park Elektrik applied to Energy Market Regulatory Authority for a license to establish a NGPP in Ceyhan, Adana. Installed capacity will be 423 MW*. Production license will be valid for 49 years. Estimated investment amount is Euro 250 mn. *The technological adv

Slide 26: Edirne Natural Gas Power Plant
Edirne Natural Gas Power Plant Park Elektrik applied to Energy Market Regulatory Authority for a license to establish a NGPP in Edirne. Installed capacity will be 423 MW. Estimated investment amount is Euro 250 mn. Park Elektrik Madencilik March 2013 26

Slide 27: V. Financial Structure
V. Financial Structure Park Elektrik Madencilik March 2013 27

Slide 28: Annual Concentrated Copper Production (wmt)
Annual Concentrated Copper Production (wmt) * Annual production declined due to production halt of four-month in 2010. Park Elektrik Madencilik March 2013 28

Slide 29: Annual Con. Copper (dmt) & Cathode (ton) Sales
Annual Con. Copper (dmt) & Cathode (ton) Sales * In 2010, there was a production halt of four months. ** 6,613 dmt of concentrated copper were used to produce 1,210 mt copper cathode. This pushes 2011 total sales up to 61,667 dmt. *** 14,296 dmt of concentrated copper were used to produce 2,521 mt c

Slide 30: Annual Asphaltite Sales (ton)
Annual Asphaltite Sales (ton) * Asphaltite operations started in mid 2009. Park Elektrik Madencilik March 2013 30

Slide 31: Total Sales Revenues (TL)
Total Sales Revenues (TL) Park Elektrik Madencilik March 2013 31

Slide 32: Net Earnings (TL mn)
Net Earnings (TL mn) Park Elektrik Madencilik March 2013 32

Slide 33: Breakdown of COGS, as of YE12
Breakdown of COGS, as of YE12 Park Elektrik Madencilik March 2013 33

Slide 34: Annual Margin Comparison
Annual Margin Comparison (TL mn) 2007 2008 2009 2010 2011 2012 Sales 80 111 79 84 173 265 Gross Profit 47 73 32 44 107 134 Gross Margin 59% 66% 41% 52% 62% 51% EBITDA 43 62 24 42 112 165 EBITDA Margin 52% 56% 30% 50% 65% 62% Net Earnings 20 75 19 37 101 107 Net Margin 25% 68% 25% 44% 58% 40% Park El

Slide 35: Sources of Financing (TL mn)
Sources of Financing (TL mn) * Park Elektrik has no financial debt. Park Elektrik Madencilik March 2013 35

Slide 36: VI. Evaluation of 2012 Financial Results
VI. Evaluation of 2012 Financial Results Park Elektrik Madencilik March 2013 36

Slide 37: Evaluation of 2012 Financial Results
Evaluation of 2012 Financial Results In 2012, total copper concentrate production was realized as 89.253 wmt, indicating 15.2 % increase compared to 2011. Asphaltite sales was realized as 363.848, 16.2% less then the previous year, due to the diminished demand by Silopi Elektrik. Total sales for c

Slide 38: Production & Sales Amount
Production & Sales Amount Production 2011 2012 % Concentrated Copper (wmt) 77.510 89.253 15.2 Cathode Copper (MT) 2.829 902 -68.1 Asphaltite (ton) 444.333 363.848 -16.2 Sales 2011 2012 % Concentrated Copper (dmt) 55.054 73.367 33.3 Cathode Copper (MT) 1.210 2.521 108.3 Asphaltite (ton) 363.848 363.8

Slide 39: Sales Breakdown (TL) & Gross Margin by Products
Sales Breakdown (TL) & Gross Margin by Products 2011 2012 % Copper Sales 151.135.664 229.264.821 52 Gross Margin of Copper 68 57 Asphaltite Sales 19.709.514 30.816.836 56 Gross Margin of Asphaltite 20 14 Other Sales 1.676.016 4.805.991 186 Total Sales Revenues 172.521.194 264.887.648 53 Overall Gros

Slide 40: Income Statement (TL)
Income Statement (TL) 2012 2011 % Sales 264.887.648 172.521.194 54% COGS -130.509.149 -65.615.478 99% Gross Profit 134.378.499 106.905.716 26% Gross Margin 50,7% 62,0% Marketing, Distribution Exp -13.481.001 -8.990.046 50% General Adm. Expenses -18.427.471 -17.344.737 6% R&D Expenses -657.270 0 Othe

Slide 41: Summary Balance Sheets (TL)
Summary Balance Sheets (TL) YE11 YE12 Current Assets 297,678,924 296,579,212 Fixed Assets 186,424,631 206,692,571 TOTAL ASSETS 484,103,555 503,271,783 Short Term Liabilities 34,255,807 32,226,892 Long Term Liabilities 6,391,196 20,574,734 Shareholders Equity 443,456,552 450,470,157 TOTAL LIABILITIES

Slide 42: Corporate Governance Rating
Corporate Governance Rating Park Elektrik was rated with 8.82 as a result of the Corporate Governance MAIN SECTIONS: Avg. 88,24 study done by SAHA Kurumsal Rating Agency. According to report done by Board Of Directors 78.77 SAHA, the rating means that the company performs “very good” in terms of Cap

Slide 43: Thank You. Contacts
THANK Y O U. CONTACTS Yesim Bilginturan Selim Erdogan IR Manager IR Manager Phone: +90 216 531 25 33 +90 216 531 25 35 y.bilginturan@cinergroup.com.tr s.erdogan@cinergroup.com.tr www.parkelektrik.com.tr www.cinergroup.com.tr Park Elektrik Madencilik March 2013 43
Source: Internet Archive copy of parkelektrik.com.tr
More decks from Park Elektrik Uretim Madencilik Sanayi ve Ticaret A.S.
Investor Presentation (September 2017)26 slides · September 2017
Investor Presentation (September 2017)26 slides · September 2017
Investor Presentation (January 2013)41 slides · Jan 25, 2013
Ak Investment Investor Conference 201240 slides · Nov 15, 2012
BGC Partners Conference London 201239 slides · September 2012
Investor Presentation (May 2012)38 slides · May 8, 2012
All 11 Park Elektrik Uretim Madencilik Sanayi ve Ticaret A.S decks