  2. Slide 2: Two Rivers

    Two Rivers T he Two Rivers Platinum Mine (Two Rivers) is a joint venture between African Rainbow Minerals (ARM) (55%) and Impala Platinum Marula Platinum Holdings Limited (Implats) (45%). Two Rivers The operation is situated on the farm Dwarsrivier on the southern part of the eastern limb of the Bus

  3. Slide 3: Geology

    GEOLOGY Both the Merensky Reef and underlying UG2 Reef occur on the property. The UG2 outcrops in the Klein Dwarsrivier valley over a north-south strike length of 7.5 kilometres and dipping generally to the west at about 10 degrees. The extreme topography results in the UG2 occuring at a depth of 93

  4. Slide 4: Mining

    MINING The underground mine is accessed via a decline shaft system comprising a footwall conveyer decline and two on-reef declines – one for vehicle access and the other a chairlift installation for the transport of employees. Underground mining operations are fully mechanised and the bord and pilla

  5. Slide 5: Metallurgy; Black Economic Empowerment

    METALLURGY Two Rivers has a concentrator plant on site, where initial processing is done. It comprises a standard MF2 design as generally used in the industry. Planned modifications to the plant following various teething problems will enable it to process at least 225 000 tonnes per month from FY20

  6. Slide 6: Sustainable Development

    SUSTAINABLE DEVELOPMENT Two Rivers is committed to social development initiatives and engages in, develops and builds community relationships. It takes responsibility for economic, social and environmental issues that impact its people, communities and environments and is involved in a number of com

  7. Slide 7: Two Rivers – Key Statistics

    TWO RIVERS – KEY STATISTICS TWO RIVERS – KEY STATISTICS FY2009 FY2008 Production ex mine Tonnes milled (000 t) 2,616 2,366 Headgrade 5PGE+Au 4.10 3.99 Platinum in concentrate production (000 oz) 118.0 98.6 PGM in concentrate production (000 oz) 246.3 206.5 Mining cost of sales On-mine and concentrat

  8. Slide 8: Contact Details

    CONTACT DETAILS For further information visit www.implats.co.za Group Executive: Corporate Relations Group Corporate Relations Manager Bob Gilmour Alice Lourens Tel: +27 (11) 731 9013 Tel: +27 (11) 731 9033 E-mail: bob.gilmour@implats.co.za E-mail: alice.lourens@implats.co.za HEAD OFFICE 2 Fricker R