Amplitude Energy Limited · ASX:AEL

Amplitude Energy — Corporate Update (August 2021)

11 slides from Amplitude Energy's corporate update, Aug 19, 2021

  1. Slide 1: Orbost Gas Processing Plant: Phase 2B works

    ASX Announcement / Media Release 19 August 2021 Orbost Gas Processing Plant: Phase 2B works Cooper Energy (ASX: COE) provides the following presentation in relation to upcoming Phase 2B works to be undertaken at the Orbost Gas Processing Plant. The Orbost Gas Processing Plant is owned and operated b

  2. Slide 2: Orbost Gas Processing Plant Phase 2B works presentation

    Orbost Gas Processing Plant Phase 2B works presentation1 19 August 2021 1. The information set out in this presentation regarding the Orbost Gas Processing Plant has been prepared by Cooper Energy

  3. Slide 3: Key messages

    Key messages Extensive testing provides confidence in Phase 2B works to significantly improve plant performance ➢ Understanding of the Orbost Gas Processing Plant (OGPP) has greatly improved throughout 2021 ➢ Recent performance and average gas processing rates have improved: ─ H1 FY21: 23 TJ/day ─ H

  4. Slide 4: Snapshot of Phase 2B works

    Snapshot of Phase 2B works Phase 2B approved by Cooper Energy will complete works agreed under the Transition Agreement • Phase 2 works were agreed in accordance with the Transition Agreement signed with APA in 20201 ─ Phase 2A involved reconfiguration of absorbers to enable parallel and / or indepe

  5. Slide 5: A recap: extracting H2S from Sole raw gas

    A recap: extracting H2S from Sole raw gas Process utilises technology under licence from Shell Treated gas to sales pipeline • Sole gas contains H2S (~1,000 ppm1) which requires <4 ppm H2S extraction • Technology uses naturally occurring bacteria to convert H2S into solid sulphur Process solution re

  6. Slide 6: The objective: keep absorbers clean to optimise performance

    The objective: keep absorbers clean to optimise performance Each absorber proven to operate at 34 TJ/day when clean OGPP processing rates and Sole GSA volumes: 1 January 2021 to 18 August 2021 TJ/day 70 60 50 45 TJ/day Cleaning of each absorber every two weeks Ave: 40 TJ/day (i.e. one absorber clean

  7. Slide 7: Phase 2B filters: solids removal package

    Phase 2B filters: solids removal package Designed to remove sulphur solids before solution re-enters the absorbers Treated gas to sales pipeline • The package consists of multiple individual filter cartridges <4 ppm H2S Backwash cycle Solid that cycle between filter mode and backwash mode sulphur se

  8. Slide 8: Phase 2B filters: successful trials at OGPP

    Phase 2B filters: successful trials at OGPP Absorber simulations confirm ability to remove solids Fouling of absorber Absorber packing Foaming simulation using existing packing with with filtered solution OGPP process solution1 unfiltered solution Packing clear of Solid sulphur build- solid sulphur

  9. Slide 9: Phase 2B spray nozzles

    Phase 2B spray nozzles Designed to reduce foaming within the absorbers which may reduce fouling • Process solution sprayed through nozzles at the top of each absorber. • Spray expected to supress foaming within the absorbers and may also have a positive effect on fouling • Sulphur particles have bee

  10. Slide 10: Key messages

    Key messages Extensive testing provides confidence in Phase 2B works to significantly improve plant performance ➢ Understanding of the Orbost Gas Processing Plant (OGPP) has greatly improved throughout 2021 ➢ Recent performance and average gas processing rates have improved: ─ H1 FY21: 23 TJ/day ─ H

  11. Slide 11: Disclaimer

    Disclaimer This presentation may contain forward looking statements, including statements of current intention, statements of opinion and expectations regarding Cooper Energy’s present and future operations, possible future events and future financial prospects. Such statements are not statements of

Amplitude Energy — Corporate Update (August 2021) on 6ix