Agl Energy Limited · ASX:AGL

Agl Energy — Corporate Update (November 2016)

15 slides from Agl Energy's corporate update, Nov 24, 2016

  1. Slide 1: Coopers Gap Wind Farm Community Consultative Committee

    Coopers Gap Wind Farm Community Consultative Committee Presented by Evan Carless – Power Development Date Thursday, 24 November 2016 4pm

  2. Slide 2: Agenda

    Presentation title | 2 Agenda 1 2 3 4 5 6 Welcome Project status Business and Other business Next Meeting Close update industry information sessions Clare Wilkes November 24 2016

  3. Slide 3: Welcome

    Welcome 1 Confirmation of October minutes

  4. Slide 4: Review Previous Meeting Actions

    Coopers Gap CCC | 4 Review Previous Meeting Actions Action Item CCC meeting Status Who Ensure minutes are posted to Jim Scutt. 13 October Ongoing CM CWA & Rural Fire Brigade catering for Christmas Party 13 October Closed CM Invitations and RSVP Christmas Party 13 October Closed CM Transport for Chri

  5. Slide 5: Project Status Update

    Project 2 Status Update

  6. Slide 6: Project Status Update: Project Team

    Coopers Gap CCC | 6 Project Status Update Project Team – present today (presented by Evan Carless) Neil Cooke – Project manager (outgoing) Evan Carless – Project manager (incoming) Adrian Gibney – Assistant project manger Stuart Galway – Manager land and approvals Clare Mildren – Senior manager gove

  7. Slide 7: Project Status Update: Grid Connection and Tender

    Coopers Gap CCC | 7 Project Status Update Grid Connection and Tender Connection to Grid • Connection Application submitted to Powerlink. Tender Update • Capability statements from local businesses included. • Tender packages submitted to AGL Tuesday 15th November • AGL currently reviewing tenders •

  8. Slide 8: Project Status Update: EIS update

    Coopers Gap CCC | 8 Project Status Update EIS update: (Presented by Neil Cooke) EIS update • Submissions period closed 7th November • AGL preparing responses to submissions and updating EIS to address submissions where required • Final EIS target completion by the end of December • Office of Co-ordi

  9. Slide 9: Business and industry information sessions

    Business and 3 industry information sessions

  10. Slide 10: Business and industry information sessions

    Coopers Gap CCC | 10 Business and industry information sessions 10 November TSBE Event – Dalby • Update on renewable projects within the Western Downs region • Neil Cooke provided an update on Coopers Gap Wind Farm • Approximately 200 in attendance

  11. Slide 11: Other business

    Other 4 business

  12. Slide 12: Other Business: Solar for wind farm neighbours

    Coopers Gap CCC | 12 Other Business Solar for wind farm neighbours - Proposal is that AGL will offer to wind farm neighbours within approximately 2 km’s of the wind farm boundary 5 kW of Solar Panels - Offer dependent upon the wind farm being committed to construction Neil Cooke November 2016

  13. Slide 13: Next Meeting

    5 Next Meeting

  14. Slide 14: Next Meeting

    Coopers Gap CCC | 14 Next Meeting › Date › Time › Location Neil Cooke – November 2016

  15. Slide 15: Close

    6 Close