  1. Slide 1: Restructured- APDRP

    Slide 1: Restructured- APDRP

    Restructured- APDRP New Delhi 21st July 2009 An initiative of Nodal Agency Ministry of Power Power Finance Corporation Ltd. Government of India © 2009 KPMG Advisory Services Private Limited, affiliated with KPMG International, a Swiss cooperative. All rights reserved.

  2. Slide 2: Key milestones achieved

    Slide 2: Key milestones achieved

    Key milestones achieved Activity Actual Appointment of IT Advisor / Web Consultant 14.10.2008 Appointment of Process Consultant 23.10.2008 DPR format for Part-A uploaded on web 31.12.2008 Empanelment of IT Consultants (ITC) 09.01.2009 Launch of R-APDRP web portal 25.02.2009 Empanelment of IT Impleme

  3. Slide 3: Schedule - the way forward

    Slide 3: Schedule - the way forward

    Schedule - the way forward Activity Likely/Actual DPR format for Part-B 30.07.2009 Methodology for establishing Base Line Data system 30.07.2009 Appointment of Consultant for Capacity Building of dist. Person 14.08.2009 Appointment of TPIEA-EA 31.08.2009 Empanelment of SCADA/DMS Consultant (SDC) 29.

  4. Slide 4: Appointment of IT Consultant and Part A implementation steps

    Slide 4: Appointment of IT Consultant and Part A implementation steps

    • Appointment of IT Consultant (from empanelled consultants with PFC) • Preparation of DPR for Part A • Appointment of IT Implementation Agency (from empanelled agencies ) • Implementation /Monitoring of project Part-A • Completion of Part A & certification by TPIEA-IT • Ring fencing of Project area

  5. Slide 5: Formation of high level steering committee to monitor IT implementation

    Slide 5: Formation of high level steering committee to monitor IT implementation

    • Formation of a high level steering committee to monitor the implementation of IT project. • Formation of a dedicated core team taking nomination from each department who are involved in business process automation including IT department. • Study of business process and realigning the same to make

  6. Slide 6: Ring-fencing of the project area through metering

    Slide 6: Ring-fencing of the project area through metering

    • Ring-fencing of the project Area (Town) through metering of all import/ export metering points and segregation of agriculture feeders • Installation of new meters for Feeder, Distribution transformer (The new Indian standard based on IEC 62056 open protocol, is being finalized by BIS which will be

  7. Slide 7: Time line for Project Implementation and conversion of loan to grant

    Slide 7: Time line for Project Implementation and conversion of loan to grant

    Time line for Project Implementation and conversion of loan to grant Sanction of Award of contract Completion of Part A 3 Month 18-24 Months Schemes to ITIA contract to ITIA Certification of Conversion of 100% TPIEA loan to grant Completion of Ring Part B fencing and Sanction of Part B Completion of

  8. Slide 8: Activity/Sub Activity timeline for IT Consultants

    Slide 8: Activity/Sub Activity timeline for IT Consultants

    S.No. Activity/ Sub Activity Days A1 Customisation/Preparation of Bid Doc-IT Consultants 0-10 A2 Invitation of RFP from Empanelled IT Consultants 10 A3 Submission of RFP responses 10-25 A4 Evaluation of Technical responses 25-30 A5 Evaluation of Financial responses 30-35 A6 LoA/ Appointment of IT Co

  9. Slide 9: Activity/Sub Activity timeline for IT Implementation Agency

    Slide 9: Activity/Sub Activity timeline for IT Implementation Agency

    S.No. Activity/ Sub Activity Days B1 Customisation/Preparation of Bid Doc-ITImpAgency 0-15 B2 Invitation of RFP from Empanelled IT Imp Agencies 15 B3 Submission of RFP responses 15-45 B4 Pre Bid Conference 25 B5 Evaluation of Technical responses 45-50 B6 Evaluation of Financial responses 50-55 B7 Lo

  10. Slide 10: Ring Fencing of project area

    Slide 10: Ring Fencing of project area

    S.no. Activity/ Sub Activity Months Ring Fencing of project area 1 Verification of electrical Vs physical boundary of project area 0-3 2 Import Export Meters on Boundary Feeders 3 Supply & installation of AMR at S/s, DT & HT Consumers 0-6 4 Completion of Feeder segregation Collecting 3 billing Cycle

  11. Slide 11: ITC will handhold the utility from concept to commissioning

    Slide 11: ITC will handhold the utility from concept to commissioning

    • ITC will handhold the utility for implementation from concept to commissioning of the project under Part A by ; • Assisting in ‘As is study’ of Utility System • Assisting in DPR preparation and populating the data • Business Process re-engineering • Deciding the scope of work for ITIA & Bid proces

  12. Slide 12: Expectation from IT Consultants

    Slide 12: Expectation from IT Consultants

    Expectation from IT Consultants S. Scope as Expectation of MOP / PFC No. per RFP 1 “As is” •Extent of computerization study •Identification of resources that can be reused •Identification of communication type •Checking the availability of SWAN •Design of WAN and LAN of utility and identification of

  13. Slide 13: Expectation from IT Consultants

    Slide 13: Expectation from IT Consultants

    Expectation from IT Consultants S. Scope as per Expectation of MOP / PFC No. RFP 2 Business Process •Assist utility in Business process re-engineering re-engineering •G2 section of SRS to be customised based on the new system, procedure and DOP. 3 DPRs •DPRs to be prepared on „as-is‟ study and Prepa

  14. Slide 14: Expectation from IT Consultants

    Slide 14: Expectation from IT Consultants

    Expectation from IT Consultants S. Scope as per Expectation of MOP / PFC No. RFP 4 Customization • Customize model RFP document as per the guideline of Model Bid given in SRS and RFP document. document • Section G-2 of SRS to be aligned with utility‟s (Technical business process spec) • Selection of

  15. Slide 15: Expectation from IT Consultants

    Slide 15: Expectation from IT Consultants

    Expectation from IT Consultants S. Scope as Expectation of MOP / PFC No. per RFP 5 Customiz •Only minor instances like name of utility/state, date of tender, page ation of number, etc. needs to be customized. Model Bid •Modification of the parts to change the intent of the original clause document i

  16. Slide 16: Expectation from IT Consultants

    Slide 16: Expectation from IT Consultants

    Expectation from IT Consultants S. Scope as per Expectation of MOP / PFC No. RFP 6 Timely placement • RFP finalization & Bid process activity to be of ITIA expedited. • While technically evaluating bids, do consider the disclaimer clause of SRS document that any component of bids meeting functional

  17. Slide 17: Expectation from IT Consultants

    Slide 17: Expectation from IT Consultants

    Expectation from IT Consultants S. Scope as per Expectation of MOP / PFC No. RFP 8 Procurement • Support utility in selecting sub vendor, finalization assistance of quality plan and pre despatch inspection, acceptance of materials at site as per contract. 9 Acceptance • Finalize the testing plan in

  18. Slide 18: Non APDRP towns and Union Territories integration

    Slide 18: Non APDRP towns and Union Territories integration

    • Non APDRP towns may be included as per revised RfP/ SRS provisions • For Union Territories, it is proposed to integrate its Towns under Part-A with the DC/DR of neighbouring States Union territory Neighboring State Chandigarh Punjab / Haryana Poducherry Tamilnadu Andaman-Nicobar Islands Tamilnadu

  19. Slide 19: 'As Is' Study and Preparation of DPR Part A timeline

    Slide 19: 'As Is' Study and Preparation of DPR Part A timeline

    Activity Months ‘As Is’ Study of Utility System/ Assets (-)3.5 Preparation of DPR – Part A To (-)2 Implementation/integration of legacy system (-)2-22 Customisation/Preparation of RfP Bid Doc-ITIA Development of enabling infrastructure by Utility (-) 2 - 0 Assist Utility in bid confer/ technical bid

  20. Slide 20: Activity/Sub Activity timeline in months

    Slide 20: Activity/Sub Activity timeline in months

    S no. Activity/ Sub Activity Months 1 LoA for appointment of ITIA & Mobilization at site 0-0.5 2 System Design/ Pre-Imple Plan and Approval from the owner 0.5-3 Field Survey for Consumer Indexing & Asset mapping & GIS System 3 3-18 Implementation 4 Establishment of Data Center 6-18 5 Establishment o

  21. Slide 21: Thank You

    Slide 21: Thank You

    THANK YOU 21