10 slides from Canacol Energy's corporate update, Aug 30, 2021
Slide 1: EPM Contract and Medellin Pipeline Project
EPM Contract and Medellin Pipeline Project August 2021
Slide 2: Advisories
Advisories This presentation is provided for informational purposes only during the Medellin Pipeline Project Announcement Conference Call held on the 30th of August 2021, is not complete and may not contain certain material information about Canacol Energy Ltd. (“Canacol" or the "Company"), includi
Slide 3: Advisories
Advisories Oil and Gas Information Barrels of oil equivalent (“boe”) and thousands of cubic feet equivalent (“MCFe”) Boe and MCFe may be misleading, particularly if used in isolation. A boe or MCFe conversion ratio of cubic feet of natural gas to barrels of oil equivalent and from barrels of oil to
Slide 4: Diversifying and Growing Canacol's Gas Market
Diversifying and Growing Canacol’s Gas Market Interior Market Coastal Market - Larger market (60% of Colombia’s Natural Gas - Canacol has grown to supply >50% of the coastal Demand) - lots of room to grow market share gas market, supporting increasing demand at a - Stable market demand with large re
Solving Cost-Prohibitive Transportation – Jobo-Medellin Pipeline Existing Pipeline Network Fees Prevent Canacol From Supplying the Interior Market Existing network transport fees from the Caribbean to Interior: $5.3-$6.6 USD/Mcf Jobo-Medellin pipeline fees expected to be: - <50% of current Jobo-Mede
Slide 6: Strategic Gas Sales Contract Signed with EPM
Strategic Gas Sales Contract Signed with EPM Signed strategic contract with the largest utility company EPM: - Take or Pay Contract - Duration: 11 years - Start Date: December 1, 2024 - End Date: November 30, 2035 - 1 year initial volume: ~21 million MMscfpd - Escalates to ~54 MMscfpd on December 1,
Jobo – Medellin Pipeline: Project Outline New 20” pipeline will be built between Canacol´s gas treatment plant at Jobo to the city of Medellin located 285 kilometers to the south CAPEX: ~ US$450 million Capacity: 100 mmscfd (option to expand to 200 mmscfd) Target Start-up: December 2024 June 2023 1Q
Slide 8: $75 Million Senior Unsecured Bridge Term Loan
$75 Million Senior Unsecured Bridge Term Loan Bridge Term Loan Original Terms: • $75 million 2-yr term $25 million drawn to support first 12 months of Medellin pipeline project Interest Rate: LIBOR +4.25% on drawn amounts 1.275% on undrawn amounts Bridge Term Loan Amendment: Amended to extend both t
Slide 9: Project Finance
Project Finance Cornerstone infrastructure project in Colombia’s economy that supports the Government’s ambitions to transition its energy matrix 1. Canacol can not legally own more than 25% of the pipeline. Our intention is to own from 0%-25% depending on the terms of the winning consortium 2. Give
Slide 10: Canacol Energy
~ CANACOL —— ENERGY ————