Slide 1: Duralie Coal CCC Meeting Presentation – Company Report & Overview of Activities
Duralie Coal CCC Meeting Presentation – Company Report & Overview of Activities August 2021 Michael Plain Environment & Community Superintendent
Slide 2: Table of Contents
Table of Contents 1. Agenda Item 7a - Progress at the Mine 2. Agenda Item 7b - Environmental Reporting 3. Agenda Item 7c - Environmental Management Plans & Monitoring 4. Agenda Item 7d - Community Complaints 5. Agenda Item 7e - Community Programs 2 3 August 2021 2
Slide 3: 1. Progress at the Mine
1. Progress at the Mine Total Waste Total ROM Coal (BCM) (T) Q2 2021 322,000 45,000 Mining 2nd Quarter 2021 ▪ Mining operations continued at Duralie in the Weismantel pit. ▪ First coal mined in April 2021. ▪ Railing is scheduled to commence 16th August 2021. ▪ Rehabilitation works are planned to be
Slide 4: 2. Environmental Reporting & Regulators
2. Environmental Reporting & Regulators Management Project Status Area Reporting • Duralie Coal Mine Independent • The 3-yearly audit undertaken in December 2020 by Ken Holmes of Barnett & May has Environmental Audit been accepted by DPIE. Copies of the audit report have been distributed to the CCC
Slide 5: 3. Environmental Management Plans & Monitoring
3. Environmental Management Plans & Monitoring a) Air Quality Management b) Blast Management c) Noise Management d) Water Management e) Rehabilitation Management f) Biodiversity Management g) Mine Closure Planning 5 3 August 2021 5
Slide 6: 3a. Air Quality Management
3a. Air Quality Management Management Area Project Status Air quality monitoring • Real-time air quality system • The real-time air quality TEOM monitor on Martins Crossing Rd continues to operate. • HVAS & dust gauge • General ambient PM10 dust levels have been very low throughout monitoring networ
Slide 7: Duralie Dust Gauge Monitoring - Annual Rolling Average
3a. Air Quality Management Duralie Dust Gauge Monitoring - Annual Rolling Average 12 Months to July 2021 4.5 4.0 Dust (g/m2/month) 3.5 3.0 2.5 2.0 1.5 1.0 0.5 0.0 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 D3 D4 D5 D7 D8 D9 D10 D12 D13 DP&E limit Jun-20 D3 Ve
Slide 8: Duralie HVAS Monitoring (PM10)
3a. Air Quality Management Duralie HVAS Monitoring (PM10) 60 12 Months to July 2021 40 PM10 (µg/m3) 20 0 29-May-20 28-Jul-20 26-Sep-20 25-Nov-20 24-Jan-21 25-Mar-21 24-May-21 23-Jul-21 -20 High Noon Twin Houses Hattam Edwards DP&E Limit Duralie HVAS Monitoring (PM10) Annual Rolling Average - 12 Mont
Slide 9: 3b. Blast Management
3b. Blast Management Management Project Status Area Blasting • Blast monitoring • Blast activities at the DCM were recommenced on 17/3/2021 • Blasting will be undertaken in discrete periods during 2021 with only a limited number of blasts required. Ground Overpressure Overpressure Ground Fisher-Webs
Slide 10: 3c. Noise Management
3c. Noise Management Management Project Status Area Noise • Routine Monitoring • Quarterly monitoring continued during Q2 2021. All results were compliant with noise Monitoring criteria. • Noise reports are made available on the Duralie Coal website. • Routine quarterly noise monitoring of operation
Slide 11: 3d. Water Management
3d. Water Management Management Project Status Area Site Water • Annual water balance review. • The 2020 annual site water balanced has been prepared. A summary will be included in Management the Annual Review 2020/21 and will be available on the Duralie Coal website. Surface Water • Routine monitor
Slide 12: Monthly Rainfall and Surface Water Monitoring
3d. Water Management Duralie Mine Site - Monthly Rainfall Duralie Surface Water Monitoring - pH 3 months to July 2021 500 10 9 400 8 300 Rainfall (mm) 7 200 6 100 5 0 2021 25-Mar-21 14-Apr-21 04-May-21 24-May-21 13-Jun-21 03-Jul-21 2020 JAN MAR SW2 - DCPL (CSC) SW2 RC - Rail Culvert DCPL (CSC) MAY J
Slide 13: 3e. Rehabilitation Management
3e. Rehabilitation Management Management Area Project Status Rehabilitated Waste • Rehabilitation Works • Currently rehabilitation works involve bulk shaping to achieve final landform designs. emplacements Bulk shaping of 5 hectares above the water fill point has been completed. • Rehabilitation Pla
Slide 14: 3f. Biodiversity Management
3f. Biodiversity Management Management Project Status Area Biodiversity • Revegetation works • 2021 Revegetation planting has been completed. Approximately 36,100 native tubestock over Offset 114 hectares on the eastern side of Johnsons Creek Road have been planted during H1 2021 in the biodiversity
Slide 15: 3f. Biodiversity Management
3f. Biodiversity Management Management Project Status Area Flora/Fauna • Nest Box Program • An additional 28 nestbox were installed in the established Duralie native rehabilitation area during May 2021. Reporting will be included in the Annual Review 2021 • Quarterly Nest box monitoring was undertak
Slide 16: 3g. Mine Closure Planning
3g. Mine Closure Planning Note: *Refer to Duralie Mining Operations Plan & Rehabilitation Management Plan Table 13 Mine Closure Planning Schedule. *Further detail on mine closure planning progress is included in the Annual Review 2019/20. Management Project Status Area Mine Closure • Stakeholder • C
Slide 17: 3g. Mine Closure Planning
3g. Mine Closure Planning Note: *Refer to Duralie Mining Operations Plan & Rehabilitation Management Plan Table 13 Mine Closure Planning Schedule. *Further detail on mine closure planning progress is included in the Annual Review 2019/20. Management Project Status Area Environmental • EMP reviews fo
Slide 18: 4. Community Complaints
4. Community Complaints Duralie Complaint Summary Period: 01/04/2021 - 31/6/2021 Period: 3 Months Total No. of Complaints: 0 (0 noise, 0 blast, 0 air quality, 0 other) Total No. of Complainants: 0 Date/Time of Method of Nature of Complaint Complainant Location Complaint Complaint Investigation/Outco
Slide 19: 5. Community Programs
5. Community Programs Management Area Project Status Support Programs Stratford Coal • The Stratford Coal Community Support Program will run again in 2022. Applications will open Community Support in October 2021. Program Stratford Coal • The Stratford Coal Education Support Fund will be running aga