Slide 1: Community Consultative Committee April 2018
Community Consultative Committee April 2018
Slide 2: Agenda item 3 – Correspondence (since November)
Agenda item 3 – Correspondence (since November) - Department of Planning and Environment - AEMR 2017 issued - Request for road transport of overburden for Aglime - Request for road transport of rocks to Bungonia for Soil Conservation service work - Advice of noise levels exceeding criteria and volun
Slide 3: Agenda item 4 – Operations
Agenda item 4 – Operations Safety - Achieved zero LTI’s since last CCC (Nov 2017) Overburden - Overburden works continuing to open the pit eastwards and placement in the southern overburden area Pit update - Mine plan remains a consistent Easterly direction with additional load and haul of roc
Slide 4: Agenda item 5 – OH&S Performance
Agenda item 5 – OH&S Performance No loss time injuries Two DPI audits conducted: - Electric shock and Arc burns - Explosives Control Plan conducted Dedicated pedestrian areas established around site to improve pedestrian safety 4
Slide 5: Environmental Performance Incidents
Agenda Item 6 - Environmental Performance Incidents Nov 2017 - 1 hydraulic hose spill Dec 2017 – 1 hydraulic hose spill March 2018 – 1 diesel spill during refuelling 5
Slide 6: Environmental Performance Complaints
Agenda item 6 – Environmental Performance Complaints October 2017 – 1 regarding traffic March 2018 – Noise 6 texts regarding noise as part of our noise investigations at a residential receiver 6
Slide 7: Environmental Performance Air
Agenda item 6 – Environmental Performance Air Annual Average goal of 4gm2/month not in compliance at the site however majority of insoluble solid is organic Annual average would be below goal at the boundary Report received advising relocation of the bottle to the boundary 7
Slide 8: Environmental Performance Air
Agenda item 6 – Environmental Performance Air Annual Average goal of 4gm2/month In compliance 8
Slide 9: Environmental Performance Air
Agenda item 6 – Environmental Performance Air Annual Average goal of 4gm2/month In compliance However Bottle continues to have a high organic content. Report has been received advising relocation of bottle. 9
Slide 10: Air – Particulate Matter <10 microns – annual average
Agenda item 6 – Environmental Performance Air – Particulate Matter <10 microns – annual average In compliance with the annual average goal Gap in data due to failure of the sampler to operate – additional samples have been run 10
Slide 11: Air – Particulate Matter <10 microns – 24 hour criteria
Agenda item 6 – Environmental Performance Air – Particulate Matter <10 microns – 24 hour criteria 2 samples over 24 hour criteria 23 Jan 2018 - predominantly westerly 28 Dec 2017 – very little wind Due to weather conditions at the time not believed to be due to the quarry 11
Slide 12: Air - Total Suspended Particulates
Agenda item 6 – Environmental Performance Air - Total Suspended Particulates TSP below Annual average goal 12
Slide 13: Noise - quarterly noise monitoring Dec 2017 - daytime
Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring Dec 2017 - daytime Operational Criteria Receiver Date Site Noise Level Contribution (dB(A)) EPL ID Leq , 15 minute (dB(A)) daytime R2 12-Dec-17 23 35 R2 12-Dec-17 23 35 R2 13-Dec-17 30 35 R8 13-Dec-17 26 41 R17 12th Decembe
Slide 14: Noise - quarterly noise monitoring December 2017 – evening
Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring December 2017 – evening Receive Operational Criteria r Date Site Noise Level Contribution (dB(A)) EPL ID Leq , 15 minute (dB(A)) evening R2 14-Dec-17 30 35 R2 14-Dec-17 28 35 R2 14-Dec-17 30 35 R8 14-Dec-17 26 35 R17 14th d
Slide 15: Noise - quarterly noise monitoring December 2017 evening min
Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring December 2017 evening 1min Receive Operational Criteria r Date Site Noise Level Contribution (dB(A)) EPL ID LA1, 1 minute (dB(A)) evening R2 14-Dec-17 32 45 R2 14-Dec-17 26 45 R8 14-Dec-17 32 45 R17 14th december 2017 25 45
Slide 16: Noise - quarterly noise monitoring January 2018 daytime
Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring January 2018 daytime Operational Criteria Receiver Date Site Noise Level Contribution (dB(A)) EPL ID Leq , 15 minute (dB(A)) daytime R2 30/01/2018 26 35 R2 30/01/2018 26 35 R2 31/01/2018 16 35 R2 31/01/2018 18 35 R8 30/01/2
Slide 17: Noise - quarterly noise monitoring January 2018 evening
Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring January 2018 evening Receive Operational Criteria r Date Site Noise Level Contribution (dB(A)) EPL ID Leq , 15 minute (dB(A)) evening R2 1/02/2018 19 35 R2 1/02/2018 20 35 R8 31/01/2018 30 35 R8 31/01/2018 30 35 R17 1/02/20
Slide 18: Noise - quarterly noise monitoring January 2018 evening 1min
Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring January 2018 evening 1min Receive Operational Criteria r Date Site Noise Level Contribution (dB(A)) EPL ID LA1, 1 minute (dB(A)) evening R2 19 45 1/02/2018 R2 20 45 1/02/2018 R8 31/01/2018 33 45 R8 31/01/2018 33 45 R17 1/02
Slide 19: Blast monitoring
Agenda item 6 – Environmental Performance Blast monitoring All in compliance 19
Slide 20: Blast monitoring
Agenda item 6 – Environmental Performance Blast monitoring All in compliance 20
Slide 21: Surface water
Agenda item 6 – Environmental Performance Surface water Quarterly monitoring round undertaken in December 2017 and March 2018 Due to lack of rain only 3 sites sampled in December– no flow onto the site. All 4 sites sampled for March 2018 due to rain Marulan south creek has been introduced as a “back
Slide 22: Surface water
Agenda item 6 – Environmental Performance Surface water Total dissolved solids in compliance – decrease in 2018 due to rain Turbidity In compliance – increase due to rain 22
Slide 23: Surface water
Agenda item 6 – Environmental Performance Surface water pH fluctuates for the dam but T1 downstream is in compliance Total phosphorus - In compliance for T1 but increase at the end of 2017 and early 2017 for the dam. May be due to changes in water level introducing nutrients from above the site and
Slide 24: Ground water
Agenda item 6 – Environmental Performance Ground water No draw down of ground water from sentinel well .i.e. no impact on local groundwater. 24
Slide 25: Ground water
Agenda item 6 – Environmental Performance Ground water Monitoring conducted October 2017 and January 2018 Measured against trigger levels Continue to have Exceedances of total nitrogen and total phosphorus at some bores (background levels are higher than guidance standards) Continue to have
Slide 26: Environmental flow
Agenda item 6 – Environmental Performance Environmental flow All in compliance 26
Slide 27: Heritage
Agenda item 6 – Environmental Performance Heritage Heritage salvage works have now been completed Scar tree identified in the footprint of the southern overburden emplacement. Review of the tree has been undertaken Next step is to collate and catalogue the artifacts commencing in July 2018 27
Slide 28: Ecology
Agenda item 6 – Environmental Performance Ecology Initial benchmark survey undertaken and photo points identified Next planting on the eastern OB held off till April / May 2018 due to weather 28
Slide 29: Stakeholder Engagement
Agenda item 6 – Stakeholder Engagement HASP project – now part of the Marulan Village plan CVA schools program being arranged Tallong Apple Festival Chevalier College STEM visit National Trust Tour Outward Bound – May 2018 Woodwards Creek erosion management - (Bungonia Park trust and soi
Slide 30: Agenda item 7 – Plans for the next three months
Agenda item 7 – Plans for the next three months Safety - Maintain zero harm to our employees and contractors Overburden - Tender for 2018/19 FY overburden works is now being priced. This will take the pit towards the South again near the site entrance. Expected to follow on directly behind the e
Slide 31: Agenda item 8 – General Business
Agenda item 8 – General Business Weather station update - Review of the weather station to be undertaken as part of Voluntary Undertaking - Relocation also now required Marulan South Limestone update - Still being prepared Peppertree Quarry Modification 5 - The proposal comprises: developing a
Slide 32: Agenda item 8 – General Business
Agenda item 8 – General Business 32
Slide 33: General Business – Next meeting dates
Agenda item 8 – General Business Next meeting dates – - August 2018 - November 2018 33