  1. Slide 1: Camden Gas Project CCC Update

    Camden Gas Project CCC Update Community Consultative Committee August 2012.

  2. Slide 2: Approvals – MP25 Modification

    1 Approvals – MP25 Modification -DP&I have finalised their assessment, and referred the matter to the PAC for determination. -PAC conducted further consultation with Campbelltown Council. -PAC approved the modification in accordance with the DOPI’s recommendations. -Approval documentation available

  3. Slide 3: Northern Expansion

    Northern Expansion 2 Submissions Stage; -Application to move into new planning system- SSD. Why? - Part 3a was repealed in Sept 2011 to address community concerns with the Part 3a process. -AGL to transition into the current planning regime. - Submissions response & EBPC Referral currently being rev

  4. Slide 4: Groundwater Monitoring

    Groundwater Monitoring 3 -Phase 1 complete. -Phase 2; -Denham Court Monitoring Bore installed. Data to be collated and included in response to submissions. -Varroville monitoring location confirmed. -Currans Hill monitoring location confirmed. - 6 months of data to be collected to develop results fo

  5. Slide 5: Operations Summary

    4 Operations Summary Well status Number (as of 16/08/12) Drilled (total wells) 143 Wells under construction 1 Producing and dewatering 104 wells Suspended 31 Plugged and abandoned 8 › Community Consultative Committee › August 2012

  6. Slide 6: Health, Safety and Environment

    5 Health, Safety and Environment › Staff volunteer day held with Barragal Landcare › PRP 1 Groundwater Attributes submitted to EPA › PRP 2 Groundwater Management Plan submitted to EPA › Site visit to Worth Recycling Treatment Plant › In-house Code Red Emergency Drill undertaken › Environmental Manag

  7. Slide 7: Drilling and well workovers

    6 Drilling and well workovers › Drilling commenced at MP25 in July. » Scheduled for completion in September › Well workovers undertaken: » Spring Farm » Menangle Park » EMAI › Next well workovers: » Menangle Park » Spring Farm » Glenlee › Community Consultative Committee › August 2012

  8. Slide 8: Rosalind Park Gas Plant

    7 Rosalind Park Gas Plant › Quarterly noise monitoring » Conducted in May 2012 » All results compliant » Next scheduled for tonight › Quarterly air emissions monitoring » Conducted in June » All results compliant » Next scheduled for September › Monthly air emissions monitoring reports uploaded to A

  9. Slide 9: Community

    Community 8 Update on past community events • May 26, Camden Community Open Day 15 attendees • July 5, Camden Community Open Day- Media Australian Financial Review, The Land, McArthur Chronicle and Camden Advertiser attended Upcoming community events • Campbelltown Show, September 1 • Camden Communi