  1. Slide 1: Financial Results Presentation

    Financial Results Presentation Half Year Ended 31 January 2013 Robert Neale Managing Director & CEO New Hope Corporation Limited

  2. Slide 2: Disclaimer

    Disclaimer IMPORTANT: The information in this document has been provided to you for information only by New Hope Corporation Limited (“NHC”) and is subject to change without notice. Nothing contained in this document constitutes investment, legal, tax or other advice. The information in this documen

  3. Slide 3: Agenda

    Agenda • Key Financials and Operations Summary • Port Operations • Mining Operations & Projects • Energy Activities • Community & Social Responsibility • Outlook 19 March 2013 3

  4. Slide 4: Key Financials & Operations Summary

    Key Financials & Operations Summary 19 March 2013 4

  5. Slide 5: Highlights of Past Six Months

    Highlights of Past Six Months • Net Profit Before Tax for the half year $93.2m, down 8.5% on the prior corresponding period (PCP). • Net Profit After Tax for the half year $68.8m, a solid performance given low A$ export coal pricing for the period. • Production 3.04 Mt down 5% on PCP. • Management f

  6. Slide 6: Key Financials

    Key Financials Six Months Ended 31 January 2013 2012 Change (A$m) (A$m) Revenue from ordinary activities 322.9 388.5 ‐16.9% Profit before income tax 93.2 101.8 ‐8.4% Net profit after tax 68.8 101.1 ‐31.9% Six Months Ended 31 January 2013 2012 (cents per share) (cents per share) Earnings Per Share Af

  7. Slide 7: Production & Sales Performance

    Production & Sales Performance Full Year Reforecast First Half Only 19 March 2013 7

  8. Slide 8: First Half Production & Sales Tonnages

    First Half Production & Sales Tonnages Six Months Ended 31 January (million tonnes) 2013 2012 Change Raw Coal Production 5.848 6.137 ‐4.7% Saleable Coal Production 3.040 3.206 ‐5.2% Coal Sold 2.740 3.164 ‐13.4% • First half 2012 was a record production half. • Planned two week shutdown over Christma

  9. Slide 9: Production Volumes

    Production Volumes Six Months Ended 31 January (million tonnes) 2013 2012 Change New Acland 2.404 2.581 ‐6.9% New Oakleigh 0.220 0.196 12.2% Jeebropilly 0.416 0.429 ‐3.0% TOTAL 3.040 3.206 ‐5.2% 19 March 2013 9

  10. Slide 10: Sales Volumes

    Sales Volumes Six Months Ended 31 January (million tonnes) 2013 2012 Change Export 2.654 2.909 ‐8.8% Domestic * 0.086 0.255 ‐66.3% TOTAL 2.740 3.164 ‐13.4% * Phase out of CSE (Swanbank) contract in 2012 19 March 2013 10

  11. Slide 11: NPAT Half Year Comparison

    NPAT Half Year Comparison 19 March 2013 11

  12. Slide 12: Australian Dollar Strength & Coal Prices

    Australian Dollar Strength & Coal Prices • Average revenue per tonne sold was down 8.1% over the first half 2013 in comparison with the first half of 2012. • Spot pricing has improved marginally from second quarter lows to be currently around US$92/tonne Newcastle benchmark. 19 March 2013 12 Source:

  13. Slide 13: Port Operations

    Port Operations 19 March 2013 13

  14. Slide 14: QBH Port Facility

    QBH Port Facility Half Year Ended Half Year Ended Year Ended 31 Jan 2013 31 Jan 2012 31 July 2012 (million tonnes) (million tonnes) (million tonnes) Coal Throughput 4.23 4.27 8.67 QBH has exported over 100 million tonnes in the past 30 years 19 March 2013 14

  15. Slide 15: QBH Port Facility

    QBH Port Facility Summary • Agreement reached on 4 year EBA with employees during January without industrial action. • Optimisation studies continuing. • System inloading and outloading availabilities in excess of 97% being achieved. • Installation of a new coal outload sampler completed. • Further

  16. Slide 16: Mining Operations & Projects

    Mining Operations & Projects 19 March 2013 17

  17. Slide 17: Project Locations

    Project Locations Location Map 19 March 2013 18

  18. Slide 18: Mining Operations

    Mining Operations Summary New Acland • Increased focus on improving safety performance. • Announcement in November 2012 of a compromise continuation plan giving New Acland an approval pathway. – Extension of the mine life to about the year 2030 • Mining fleet renewal program underway with delivery o

  19. Slide 19: New Acland Coal Mine

    New Acland Coal Mine Acland Continuation Project Project Progress • Original plan to expand New Acland from 4.8 to 10.0 MTPA (NAC03). • State significant project, EIS completed. • Supplementary EIS was due for submission to CoG in April 2012. • New LNP Government indicated an unwillingness to let th

  20. Slide 20: About the New Acland Project

    About the New Acland Project • Key Facts: Compromise Plan – Approx. Local jobs: 400 direct, 170 FTE contract and 2,850 indirect – Approx. $530 million per annum direct economic injection* – Circa $8 billion economic contribution for life of mine – Self sufficient for water * Goods & services, wages,

  21. Slide 21: New Acland project site layout

    CPP Upgrade + Materials handling MIA upgrade Power line Road relocation Diversion Train Load Out Rail Extension 22

  22. Slide 22: Project Development

    Project Development 1. Coal Developments • Colton — 0.5 Mtpa open cut coking coal mine near Maryborough – Environmental approvals and mining lease being sought – Exploration and design well advanced • Elimatta – 5 Mtpa open cut thermal coal mine near Taroom – EIS in the public domain for consultatio

  23. Slide 23: Acland Pastoral Company

    • Acland Pastoral Company – 9200 hectares • Current activities: – Cattle 2250 head – Cropping for cattle fodder‐500 hectares – Cropping for grain & mung beans‐1200 hectares – Rehabilitation: 215 hectares completed 113 hectares due for completion, 2013 • Growth activities: – Detailed land use plan un

  24. Slide 24: Cost Containment Achieved

    Cost Containment Achieved • Cost per BCM of overburden moved across all operations during the first half 2013 was down 6.3% in comparison with the first half of 2012. • Production cost per tonne sold was down 11.7% over the first half 2013 in comparison with the first half of 2012. • Transport costs

  25. Slide 25: Reducing Costs via Improvements

    Reducing Costs via Improvements • Redesign of dozing methods at QBH reduced dozer usage by 10-15% and downsizing from D11 to D10 sized dozers. • Haul Truck strut sensor trialled to improve operator safety, machine and tyre longevity and reduce costs. • Resource optimiser (Non-linear programming comp

  26. Slide 26: New EX106 Bucket

    New EX106 Bucket • Commenced operation 29th January • Cycle times decrease 3% Pay‐load increase 10% • Truck loading cycle decrease by 8% Average Total Loading Cycle: 138.8 Sec Old Bucket Average Bucket Cycle Time: 31.7 Sec Average Truck Payload: 191.6 Tonnes Average Total Loading Cycle: 127.7 Sec Ne

  27. Slide 27: Energy Activities

    Energy Activities • Energy Overview & NHC Objectives • Bridgeport Energy Limited (BEL) • CTL Projects 19 March 2013 28

  28. Slide 28: Energy Overview

    Energy Overview • Two most common forms of energy in Australia are electricity and transportation fuels. – Both becoming increasingly expensive • Generally, energy is the next highest cost centre for industrial and manufacturing businesses after wages. • Competitive mining operations are dependent o

  29. Slide 29: Australian Imported Oil Dependence

    Australian Imported Oil Dependence Singapore 40% from Middle East & Australia 57% from Singapore 19 March 2013 30 Source: NRMA

  30. Slide 30: Breakdown of Australian Fuel Consumption

    Breakdown of Australian Fuel Consumption By Source & Sector 19 March 2013 31 Source: NRMA

  31. Slide 31: Australian Petrol and Diesel Fuel

    Australian Petrol and Diesel Fuel Supplies & Stocks 19 March 2013 32 Source: NRMA and Australian Institute of Petroleum

  32. Slide 32: Historical USA Gasoline Prices

    Historical USA Gasoline Prices (Global Events Impact on Prices) 19 March 2013 33 Source: NRMA and United States Energy Information Administration

  33. Slide 33: Import Supply Chain Vulnerabilities

    Import Supply Chain Vulnerabilities 19 March 2013 34 Source: NRMA

  34. Slide 34: World Transport Fuel

    World Transport Fuel Supply ‐ Demand Massive Change in Supply Mix Diesel and Jet Fuel Growth 40 potential mb/d short Demand Supply Unconventional gas supply will change global supply side dynamics 19 March 2013 35 Source: NRMA, Exxon Mobil’s 2012 The Outlook for Energy: A View to 2040 and IEA World

  35. Slide 35: NHC Future Energy Objective

    NHC Future Energy Objective Prefer NHC site operations to be power and fuel independent with competitive lower cost reliable supply. • Power – Grid supply – Waste heat? (ex CTL) – Gas auxiliary supply (ex CTL) • Diesel – Contract fuel supply – CTL and GTL – BEL conventional petroleum • Readily avail

  36. Slide 36: Future NHC Fuel Supply Options

    Future NHC Fuel Supply Options Electricity Supply INPUTS Cooper Basin Carbon Contract Refining & Waste Refining/Imports (Bridgeport) Conversion (Major & Third Party) (CTL & GTL) NHC Operations & Projects Reliable Diesel Supply Diversification Matrix Regional Supply?? Surplus Domestic Agricultural Fu

  37. Slide 37: Oil

    Oil • Bridgeport Energy Limited (BEL) is 100% owned by New Hope Corporation – Small oil producer in Eromanga Basin, Queensland – Actively exploring in Utopia and Inland Fields – Produces 6000 barrels of crude oil per month – Expansion underway 19 March 2013 38

  38. Slide 38: Bridgeport Energy

    Bridgeport Energy Summary • New Hope Corporation completed the acquisition of Bridgeport Energy Limited on 23 August 2012. • During the half, completed a six ‐well drilling campaign on the Inland and Utopia fields. All wells indicated good oil columns. The wells were suspended for future completion

  39. Slide 39: Bridgeport Energy

    Bridgeport Energy Field Seismic Charts I-18 I-16 I-17 Utopia Murta M2 Top Reservoir Depth Map Inland Field Hutton Sandstone Depth Structure Map 19 March 2013 40

  40. Slide 40: Coal to Liquids Project

    Coal to Liquids Project Technology Status 1 Direct Liquefaction • Dry commissioning complete • Wet commissioning complete • Batch coal commissioning complete Direct Liquefaction Plant - USA • Full continuous coal commissioning underway • Original technology applications likely to have marginal comme

  41. Slide 41: Coal to Liquids Project

    Coal to Liquids Project Technology Status 2 Indirect Liquefaction (Proof of Concept Plant) • Production of power and diesel • 80% of plant components on site • Remaining 20% expected in June/July • 40% of plant assembled • Commissioning trials in August 19 March 2013 42 Indirect Liquefaction Plant -

  42. Slide 42: Coal to Liquids Project

    Coal to Liquids Project Indirect Liquefaction – Intermediate Stage Pre Liquefaction Storage Tanks Gasifier Input Lines De-sulphurisation Tanks 19 March 2013 43

  43. Slide 43: Coal to Liquids Project

    Coal to Liquids Project Next Steps Direct Liquefaction • Complete trials and assess data • Determine future plans Indirect Liquefaction • Complete plant construction • Undertake commissioning trials • Initiate next phase of engineering design subject to plant performance 19 March 2013 44

  44. Slide 44: Direct Cost Technology Incentive

    Direct Cost Technology Incentive Annual Operating Costs ($’s million) FY 2013 FY 2006 ‐ 2013 Diesel Fuel Costs (net of rebate) $ 46 $227 Site Electricity Costs $ 7 $ 29 Explosive Costs $ 16 $ 80 TOTAL $ 69 $336 $8.20 per tonne Technology Funding Costs ($’s million) FY 2013 FY 2006 ‐ 2013 Cost 2006 –

  45. Slide 45: Community & Social Responsibility

    Community & Social Responsibility 19 March 2013 46

  46. Slide 46: Community & Social Responsibility

    Community & Social Responsibility Significant ramp up of activities: Community Engagement • Oakey Community Information Office & Community Liaison Officer • New Acland Community Reference Group • Regular community information meetings • Project website, newsletters, fact sheets • Memberships: Toowoo

  47. Slide 47: Local Business Support

    Local Business Support • Active Local Purchasing Policy • In FY2012, 25% of total spend on goods and services(>$100m) was made to local suppliers Government Program Promotion • Women in Hard Hats • “Tuckshop shift” for local Oakey residents Infrastructure Support • Rebuilt and maintain Jondaryan/Mul

  48. Slide 48: Community Engagement

    A cuowartmes COMMUNIty Engagement

  49. Slide 49: Outlook

    YN New Hope Corporation Limited Outlook 19 March 2013 50

  50. Slide 50: Outlook

    Outlook 1 • The current operating environment is challenging for all Australian thermal coal producers. – Carbon Tax – MRRT Compliance costs – Historically High A$:US$ exchange rate – Constrained thermal coal pricing (A$ terms) • New Hope has been able to significantly restrain operating costs witho

  51. Slide 51: Outlook

    Outlook 2 • Japanese benchmark price negotiations and the AUD:USD exchange rate will significantly impact second half financial performance. – Security of thermal coal supply is critical to Japan • In the medium to longer term the recovery in global industrial production will drive energy demand. –

  52. Slide 52: 6 February 2013

    y_N New Hope Corporation Limited wk val ) Ta 6 February 2013 New Hope Group 53