Santos Limited · ASX:STO

Santos — Corporate Update (July 2014)

9 slides from Santos's corporate update, Jul 23, 2014

  1. Slide 1: Energy NSW – Leewood Project Update

    Energy NSW – Leewood Project Update 23rd July 2014 CCC

  2. Slide 2: Agenda

    Agenda Leewood Phase 1 – Update Leewood Phase 2 – Proposed Activity ─ Introduction ─ Site Overview ─ Leewood Phase 1 - Update ─ Leewood Phase 2 - Proposed Activities 2 | SANTOS 2014

  3. Slide 3: Field Layout Overview

    Field Layout Overview Wilga Park Wilga Park and Tintsfield • Power station – pilot gas • Pilot wells Leewood Leewood • Ponds • Proposed water treatment Other Activities • Proposed irrigation • Rehabilitation Bibblewindi • Drilling and Bibblewindi Area completions • Pilot well collection point • Gath

  4. Slide 4: Leewood Objectives and Strategy

    Leewood Objectives and Strategy SANTOS 2014 4 |

  5. Slide 5: Leewood Strategy: The Process

    LEEWOOD STRATEGY THE PROCESS Phase 1 Phase 2 Phase 3 Water Pilot Leewood treatment wells ponds facility Water extracted Water will be pumped during exploration from the ponds to the pumped via water treatment facility underground flowlines Reverse Fresh Brine from pilot wells to water osmosis will L

  6. Slide 6: Leewood Phase 1 - Progress

    Leewood Phase 1 - Progress Leewood Ponds Pipeline to Bibblewindi ~2 cells complete Leewood 2 cells remaining 95% 100% +80% 6 | SANTOS 2014

  7. Slide 7: Leewood Phase 2 - Proposal

    Leewood Phase 2 - Proposal Leewood Phase 2 Scope Construction of Leewood Phase 2 will take about six to eight months. Infrastructure will include:  Water treatment plant, including a reverse osmosis and brine treatment plant;  Associated pipework to transfer water and brine around the facility; 

  8. Slide 8: Leewood Phase 2 Schedule

    Leewood Phase 2 Schedule Indicative staging of the works: Access and preliminary civil works Site office and administration buildings Underground services Surface facilities installed Generator and fuel gas conditioning skids Control centres and process units Commissioning of facilities 8 | SANTOS 2

  9. Slide 9: Assessment and Approval Process

    Leewood Phase 2 Assessment and Approval Process 1 • Initial desktop investigations and scout 2 • Detailed environmental surveys 3 • Prepare REF with input from specialists 4 • Submit REF to OCSG • OCSG and government agencies assess REF 5 6 • Further information may be provided 7 • If approved, OCSG