  1. Slide 1: Bomboré: Burkina Faso's Newest Gold Mine

    SS"OREZONE Bombore Burkina Faso’s Newest Gold Mine (All $ figures in this presentation are in USD unless otherwise noted) TSX: ORE OTCQX: ORZCF

  2. Slide 2: Forward Looking Statements and Qualified Persons

    Forward Looking Statements and Qualified Persons This presentation contains certain information that constitute “forward-looking information” within the meaning of applicable Canadian securities legislation and “forward looking statements” within the meaning of applicable U.S. securities laws (toget

  3. Slide 3: Bomboré: Q1-2023 Operation and Financial highlights

    Bomboré: Q1-2023 © Q1-2023 Operation and Financial highlights * Gold production of 41,3010z * Gold sales of 43,1390z at an AISC of $926/oz * Plant operated “13% above nameplate * Zero lost-time injuries * Cash of $45.2M at quarter end * $9.8M of principal repaid on senior loans ® Advancing all growt

  4. Slide 4: Health and Safety

    Health and Safety & Solid Safety Record * Q1-2023: zero LTIs with 928,000 hours worked * 9.9 million hours and 1,612 days worked without a LT! & Ongoing safety initiatives * Emergency response training * Mine rescue training * Local community training & awareness 4 | Bomboré — Burkina Faso's Newest

  5. Slide 5: Non-IFRS measure. See “Non-IFRS Measures” section in Orezone’s MD&A for the quarter ended March

    1. Non-IFRS measure. See “Non-IFRS Measures” section in Orezone’s MD&A for the quarter ended March 31, 2023 for additional information.

  6. Slide 6: The Bomboré Mine entered into commercial production on December 1, 2022. Unit cash costs

    1. The Bomboré Mine entered into commercial production on December 1, 2022. Unit cash costs during pre- commercial production are not representative of cost performance expected under steady-state operations. Cost figures presented for Q4-2022 include a blend of costs before and during commercial pr

  7. Slide 7: 2023 Guidance

       1. AISC is a non-IFRS measure. See “Non-IFRS Measures” section in Orezone’s MD&A for the quarter ended March 31, 2023 for additional information. 2. Foreign exchange rates used to forecast cost metrics include XOF/USD of 625 and CAD/USD of 1.30. 3. Government royalties included in AISC assumes

  8. Slide 8: Projects Update: Phase II Expansion Study

    Projects Update: Phase II Expansion Study «© Updated Feasibility Study on schedule for Q3-2023 Study to include an additional 100,000m of drilling © Resource modeling well advanced, with mine design and planning now underway © Metallurgical studies nearing completion * — Results confirm more rapid l

  9. Slide 9: Phase II: Brownfields Expansion

    Phase II: Brownfields Expansion © 2019 Feasibility Study Brownfields Expansion — 2023 FS 5.2Mtpa oxide plant reduced to 3.0Mtpa in Year 3 } Current 5.7Mtpa oxide throughput maintained 2.2Mtpa hard rock plant construction in Year 2 Separate 4.4Mtpa hard rock plant contemplated Hard:Rock Exp ie | Bomb

  10. Slide 10: Projects Update

    Projects Update Grid Power Connection All long lead equipment orders placed Installation contracts awarded and mobilization has commenced Powerline alignment survey completed Ground clearing for 23km spur line to commence in May Grid power connection scheduled for Q4-2023 Future energy savings estim

  11. Slide 11: Community agriculture and livelihood programs

    Vegetable garden MV3, MV4, MV5 Natinga Agro-Pastoral Complex Natinga 3.4ha rice paddy farm developed Longrin Land restoration Nobsin, MV4, MVS Fertilizer and improved seeds donation Nobsin, MV4 MV5 Community nursery MV4, MV5,MV2, Nobsin, BV1 Poultry project Ipala, MV4,&MV2 Sheep fattening MV5,MV4, B

  12. Slide 12: Livelihood Restoration Programs

    Livelihood Restoration Programs ®& Income generating activities Weaving MV4, MV5, MV3, MV2, BVI, 102 BV2 Cosmetic (Body Lotion &Soap) | Nobsin & MV2 61 Spices 1 cooperative (MV2) 42 Tailors (For OBSA safety MV4, MV5, MV3, MV2, BV1, 45 uniform) BV2, Nobsin ® Local suppliers promotion Mobile equipment

  13. Slide 13: Project timeline and upcoming milestones

    2021 2022 2023 2024 2025 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Phase I - Oxide Plant Construction First Gold 2023 Results & Projects Drill Results Updated FS Grid Power Connection Phase II & III RAP Phase II - Hard Rock Plant FEED/Procurement Construction First Gold

  14. Slide 14: For more information on Orezone, please contact

    NS OREZONE For more information on Orezone, please contact: Vanessa Pickering vpickering@orezone.com 604-202-2940 www.orezone.com