Stelco — Corporate Update (January 2024)
11 slides from Stelco's corporate update, Jan 31, 2024
Slide 1: Lake Erie Works Community Liaison Committee (CLC) Meeting
Lake Erie Works Community Liaison Committee (CLC) Meeting January 31, 2024 1
Slide 2: Agenda
Agenda Discussion Topics for Today’s Meeting 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 1 November 2023, Meeting 4. Coke Battery Performance – Q4 2023 5. Community Feedback 6. Adjournment 2
Slide 3: Agenda
Agenda Discussion Topics for Today’s Meeting 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 1 November 2023, Meeting 4. Coke Battery Performance – Q4 2023 5. Community Feedback 6. Adjournment 3
Slide 4: Coke Battery Performance – Method 303: Daily (Q4 2023)
Coke Battery Performance – Method 303 Performance Review – Daily (Q4 2023) Doors Lids Off-takes Date (% Leaks) (% Leaks) (% Leaks) 2015 Thresholds 54% 2% NA (July 2 start) 2016 Thresholds 32% 2% NA 2017-2019 Thresholds 10% 2% 5% 2020 - 2023 Thresholds 5% 1% 4% October 1 – December 31, 2023 0 – 8.89%
Slide 5: Coke Battery Performance – Method 303: 30-Day Rolling Average (Q4 2023)
Coke Battery Performance – Method 303 Performance Review – 30-Day Rolling Avg. (Q4 2023) Doors Lids Off-takes Charging (sec) Date (% Leaks) (% Leaks) (% Leaks) (log avg) 2015 Limits (July 2 start) 38% 0.8% 25% 12 sec 2016 Limits 22.5% 0.8% 15% 12 s 2017-2019 Limits 7% 0.8% 4.2% 12 s 2020 - 2023 Limi
Slide 6: Coke Battery Performance – Method 303: Daily Observations (Q4 2023)
Coke Battery Performance – Method 303 Performance Review – Daily Observations. (Q4 2023) Pushing Emission Date (opacity %) 2015 Threshold (July 2 start) ≥ 50% 2016 – 2018 ≥ 50% 2019 ≥ 40% 2020 - 2023 ≥ 30% October 1 – December 31, 0 – 39.17% 2023 (10.82%) (Average) Q4 2023 Operational Adjustments •
Slide 7: Coke Battery Performance: Additional Items
Coke Battery Performance Additional Items • There were no community complaints for the period of Q4 2023 related to the Cokemaking operations • MECP invited to provide any verbal comments 7
Slide 8: Additional Updates
Additional Updates • Additional feedback received from neighbors in Q4 2023: • Dust (1) • Proposed 2024 CLC Meeting Schedule • Wed. Jan. 31 • Wed. May 1 • Wed. July 31 • Wed. Oct. 9 8
Slide 9: Agenda
Agenda Discussion Topics for Today’s Meeting 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 1 November 2023, Meeting 4. Coke Battery Performance – Q4 2023 5. Community Feedback 6. Adjournment 9
Slide 10: Agenda
Agenda Discussion Topics for Today’s Meeting 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 1 November 2023, Meeting 4. Coke Battery Performance – Q4 2023 5. Community Feedback 6. Adjournment 10
Slide 11: Stelco – The Steel Company of Canada
STELCO . The Steel Company of Canada