    GE T&D India Limited L31102DL1957PLC193993 T-5 & T-6 , Plot I-14, Axis House, Jaypee Wishtown, sector-128, Noida-201304, Uttar Pradesh T +91 120 5021500 F +91 120 5021501 https://www.ge.com/in/ge-td-india-limited August 17, 2021 The Secretary The Manager BSE Limited Listing Department Phiroze Jeejee

  2. Slide 2: Enabling India's Energy Transition

    GE T&D India Limited ENABLING INDIA’S ENERGY TRANSITION Analyst Presentation Q1 Financial Year 2021-22

  3. Slide 3: Disclaimer

    DISCLAIMER This presentation has been prepared solely for the use at analyst/ investor presentation. By attending the meeting where this presentation is made, or by reading the presentation slides, you agree to be bound by the following limitations- • The forward-looking information and statements c

  4. Slide 4: Safety is Our Top Priority

    Safety is Our Top Priority Appreciation certificates from National Safety Avaada Bikaner Project Team received Annual GA Pallavaram facility achieved 20 million Council of India for KSEB Kochi & Sterlite Tripura Safety Award from customer Safe Man hours in Apr’21 Packages Received various EHS apprec

  5. Slide 5: Executive Summary

    Executive Summary Q1 Sales at 6.4 BINR Q1’2021-22 loss After Tax at 193 MINR vs Loss After Tax of 203 MINR in Q1’2020-21 Net debt reduction of 245 MINR in Q1 2021- 22 Continuous Focus on operational excellence including lean implementation Order Intake impacted by shift of market due to Covid 19 Ord

  6. Slide 6: Covid 19 Wave 2 Update

    Covid 19 Wave 2 Update GETDIL Plants and Sites Padappai (AIS/GIS) Plant shutdown for 9 days due to lock down in Tamilnadu. Manufacturing activities fully operational now Pallavaram (GA) Plant shutdown for 9 days due to lock down in Tamilnadu. Manufacturing activities fully operational now Hosur (AIS

  7. Slide 7: Creating the Grid of Future | Key Commissioning

    Creating the Grid of Future | Key Commissioning PGCIL, Phagi, Rajasthan PGCIL, Bhuj, Gujarat BPC, Dochula, Bhutan • First GE Make 765KV GIS • 765kV AIS • 5 x 66kV GIS bays commissioned • 400kV/220kV GIS • 3x25MVA, 66/11kV PT • 10x5MVA, 11KV/415V Trafo © GE T&D India Limited

  8. Slide 8: Making In India for the World

    Making In India for the World Factory Spotlight : Vadodara • Manufacturing state-of-the-art world-class power transformers • Inauguration of LTI Vadodara factory by the then Chief Minister Shri Narendra Modi in March 2009 • Manufactured the 1st 800 kV HVDC under ‘Make in India’ initiative in March 2

  9. Slide 9: Order Intake

    ORDER INTAKE Q1’ FY 2021-22 Key Orders booked during Q1, FY 21-22 (₹ in millions) Six 500MVA 765KV Power Transformers from PowerGrid Corporation of India under the Transmission System Strengthening Scheme for evacuation of power from Solar Energy Zones in 4,723 Rajasthan (8.1 GW) under Phase-II 4,43

  10. Slide 10: Orders and Sales Details

    Orders and Sales Details (₹ in millions) Q1’ FY 2021-22 Q1 Orders Q1 Sales 1310, 21% 1690, 36% Domestic Domestic Exports Exports 3033, 64% 5071, 79% Order in Hand 7334, 17% Private State Utilities 8673, 20% Central Utilities & PSU 27487, 63%

  11. Slide 11: Financial Data

    Financial Data Q1’ FY 2021-22 (₹ in millions) Q1 Q1 Change 2021-22 2020-21 Sales 6,381 6,428 -0.7% EBITDA 14 3 346.9% % of Sales 0.2% 0.0% +0.2 pts Profit Before Tax (253) (262) 3.6% % of Sales -4.0% -4.1% +0.1pts Profit After Tax (193) (203) 5.2% % of Sales -3.0% -3.2% +0.2 pts Net Debt* of ₹1,366