Slide 3: Highlights: Q3 FY2010-11
Highlights : Q3 FY2010-11 FY2010 2

Slide 4: Key Highlights (Q3 FY 2010-11)
Key Highlights ( Q3 FY 2010 - 11) 1 Highest ever throughput achieved : 3.73 MMT (9M ( ended Dec, 2010 : 11.10 MMT ) 2 Gross Revenue of Rs. 13809 crore; ( 9M ended Dec, 2010 : Rs 38273 crore) 3 Current Price GRM $7.21/bbl ( 9M ended Dec, 2010 : $ 6.50/bbl ) 4 EBIDTA improved to Rs 827 crore ( 9M ende

Slide 5: Industry Overview
Industry Overview ENERGY

Slide 6: Industry Trends
Industry Trends Petro Product Growth in India Arab Light & Arab Heavy Difference ($/bbl) Gasoline (% growth) Gas Oil (% growth) $4.00 16.0 3.45 13.9 $3.50 14.0 3.10 11.3 $3.00 2.85 3.15 12.0 11.5 2.80 2.85 9.0 $2.50 2.75 2.75 10.0 11.1 7.4 $2.00 2.05 8.0 9.0 6.8 6.7 8.4 $1.50 6.0 4.0 4.8 $1.00 2.0 $

Slide 7: Refinery Operations
Refinery Operations ENERGY

Slide 8: Optimisation of Capacity
Optimisation of Capacity Qty : MMT 14 12 11.10 9.90 10 8 6 4 3.51 3.73 2 - Q3 FY10 Q3 FY11 9M FY10 9M FY11 Highest ever throughput achieved 3.73 MMT, consistently operating above 14 mmtpa annualised capacity 7

Slide 9: Optimization of Crude Mix
Optimization of Crude Mix Crude Slate Ultra Heavy Heavy Light 100% 90% 17% 23% 20% 21% 80% 70% 60% 52% 42% 52% 44% 50% 40% 30% 20% 35% 35% 31% 28% 10% 0% Q3 FY10 Q3 FY11 9M FY10 9M FY11 Processed 20 types of crudes including ultra heavy & tough crudes like Ras Gharib, Merey, Maya, Nowrooz Avg. API (

Slide 10: Product Mix
Product Mix Product Slate Light Middle Heavy 100% 24% 26% 23% 27% 80% 60% 49% 45% 51% 46% 40% 20% 28% 29% 26% 28% 0% Q3 FY10 Q3 FY11 9M FY10 9M FY11 Production of high margin middle & light distillates 9

Slide 11: Sales Performance
Sales Performance Sales Mix 100% 90% Bulk PSUs Exports Retail 80% 9% 70% 8% 7% 7% 60% 7% 7% 6% 61% 5% 56% 50% 56% 51% 40% 30% 20% 37% 30% 32% 10% 23% 0% Q3 FY10 Q3 FY11 9M FY10 9M FY11 Export Sales of Fuel Oil increased due to replacement of FO by natural gas in Domestic Market 10

Slide 12: Expansion of Retail Network
Expansion of Retail Network 1,800 75 1700 1,600 240 1,400 1,200 1,385 1,000 Operation Under Construction Under Planning Total No of Retail Outlets increased to 1385 with 240 under construction providing a clear roadmap to reach the target of 1700 by end of March, 2011 ALPG and CNG pumps through tie-

Slide 13: Allied Services
Non-Fuel Fuel Retail Services Bouquet Lubricants: Servo, Castrol, BP, Total, Elf Allied Services Multi fuel options: Gasoil, Gasoline, CNG and ALPG Auto Components: BOSCH, EXIDE, JK Tyres Services: Car Wash, Servicing Food & Beverage Agricultural Telecom / Banking / Finance Products Internet Non-all

Slide 14: Refinery Expansion Progress
Refinery Expansion Progress 13

Slide 15: Refining Expansion - Phase I
Refining Expansion - Phase I Expansion to 18 MMTPA Complexity to improve to 11.8 from 6.1 Overall progress : 78.13% Engineering : 99.28% Procurement : 83.41% Construction : 67.15% 100% purchase order done for long lead Items Zero Lost Time Incident Cost : within Budget All units on schedule except t

Slide 16: Upgradation of existing unit – CDU/VDU
Upgradation of existing unit – CDU/VDU Overall Progress : 88.30% 107 out of 126 equipments received Erection of all equipments completed Revamp will be completed during the Shutdown 15

Slide 17: Delayed Coker Unit
Delayed Coker Unit Sept -10 Dec-2010 Overall Progress : 70.39% Four Coker drums erected & last two received Major equipments erected : 4 Coke drums, Debutanizer, Absorber, Stripper, Light cycle & Heavy cycle gas oil stripper, Blow down tower, Fuel gas scrubber, etc 179 out of 264 equipments received

Slide 18: VGO – HT (Vacuum Gas Oil Hydrotreater Unit)
VGO – HT (Vacuum Gas Oil Hydrotreater Unit) Sept -10 Dec-2010 Overall Progress : 80.61% 119 out of 177 equipments received Major equipments erected : Kerosene & Diesel Stripper, MP Medium pressure Off Gas Stripper, LP Low pressure Off Gas Scrubber, Recycle gas scrubber, Product fractionators, Recycl

Slide 19: ISOM Unit (Isomerization unit)
ISOM Unit (Isomerization unit) Sept -10 Dec-2010 Overall Progress : 83.59% Major equipments erected- Stabilizer, Net Gas Scrubber, LPG Stripper Deisohexanizer, Methanator Reactor, Feed surge drum & Atm. flash vessel 86 out of 101 equipments received 18

Slide 20: DHDT Unit (Diesel Hydrotreater Unit)
DHDT Unit (Diesel Hydrotreater Unit) Overall Progress : 71.30% 69 equipments out of 122 equipments received Major equipments erected : Recycle gas compressor, Recycle gas scrubber, Stripper, Product fractionators, Feed surge drum, Recycle gas compressor Project Schedule currently lagging by a quarte

Slide 21: HMU Unit (Hydrogen Manufacturing Unit)
HMU Unit (Hydrogen Manufacturing Unit) Overall Progress : 67.20% 53 equipments out of 74 equipments Major equipments erected : Process condensate stripper, Process gas boiler, Pre reformer, Common LPG Surge drum, Flare knock out drum, Fuel gas knock out drum, HP condensate flash drum, Start-up Start

Slide 22: Desalination Unit and Pipe Racks Progress
Desalination Unit : 98% Erection Completed & Pipe Racks : 87% completed Sept -10 Dec-2010 21

Slide 23: Supporting Infrastructure: Commissioning of Power Plant
Supporting Infrastructure: Commissioning of Power Plant Power Plants (Owned by Essar Power) Existing Power Plant : 77 MW & steam @ 230 TPH Commercial operation of Vadinar Phase – I Expansion of 380 MW completed; synchronized with Grid, ready to supply power to Refinery Expansion Project. 22

Slide 24: Supporting Infrastructure Facilities
Supporting Infrastructure Facilities Ports & Terminals (Owned by ESPLL) Current facilities 5 road & 1 rail gantry : 7 mmtpa 1 berth at Jetty for product evacuation : 7 mmtpa 1 SPM with crude intake capacity : 27 mmtpa Tankages, Pipelines & other facilities New Additional facilities 5.5 mmtpa tankage

Slide 25: Train 1 Optimisation Project to 20 MMTPA
Train 1 Optimisation Project to 20 MMTPA 24

Slide 26: Optimization to 20 MMTPA
Optimization to 20 MMTPA Rationale for Expansion Improvement in economics due to maximum utilization of low priced Ultra Heavy Crude Capacity expansion to 20 MMTPA in minimum time and cost Optimum utilization of available infrastructure & support facilities New Units/ Facilities CDU/VDU-1 Debottlene

Slide 27: Unit Configuration
Unit Configuration 10.5 MMTPA Unit Configuration 20 MMTPA (Operating @ 14.5 MMTPA) CDU 10.5 18.0 VDU 7.2 10.9 VBU / Converted CDU 1.9 2.0 (CDU) NHT 1.6 1.8 CCR 0.9 1.1 FCC 2.9 3.9 DHDS 3.7 5.3 SRU 440 TPD 1115 TPD ARU - 11.9 SWSU - 3.5 DHDT - 4.0 VGOHT - 6.5 DCU - 7.5 ISOM - 0.7 HMU,Nm3/hr - 155,000

Slide 28: CBM Project
CBM Project ENERGY

Slide 29: Status of CBM Production at Raniganj
Status of CBM Production at Raniganj 36 15 test wells are presently producing & 10 well Production Wells 35 35 are under production & dewatering. 34 Actual production increased to 30000 scmd 33 from 18000 scmd. 32 31 31 Hydrofacturing of 12 wells with 74 jobs also 30 completed during the quarter. 29

Slide 30: Financial Performance
Financial Performance ENERGY 29

Slide 31: Financial Results
Financial Results ( Rs Crore ) Particulars Q3 FY10 Q3 FY11 9M FY10 9M FY11 Throughtput-Million Tonnes 3.51 3.73 9.90 11.10 INCOME Income from Operation 11,420 13,809 30,460 38,273 Less: Excise Duty & Taxes 1,494 1,576 4,409 4,600 Net Income from Operation 9,926 12,233 26,050 33,673 Other Income 39 1

Slide 32: Key Financials
Key Financials Current Price GRM (USD/bbl) Gross Sales & EBITDA (Rs Crores) $8.00 Gross Sales EBITDA $7.21 16000 900 827 $7.00 $6.49 800 14000 $5.79 667 681 634 $6.00 12000 700 $5.79 600 $5.00 10000 $5.37 407 500 $4.24 8000 359 $4.00 400 6000 228 $3.00 300 4000 200 $2.00 7895 11144 11420 11942 12048

Slide 33: Essar Oil – Financial Indicators
Essar Oil – Financial Indicators Rs crore Rs crore Particulars 31-Dec-10 Expansion 31-Dec-10 Debt Refinery Equity/Internal Accruals 3210 7,347 Expansion 3,229 Debt 4600 E&P & Others 968 Total 7,810 Total Debt 11,544 •Total cash spent including bills accepted uner L/Cs: Rs 6377 crore • LCs opened, ye

Slide 34: éver/ ac Anevement
éver/ ac Anevement . but the beginning of @ new journey / fa F rE! | A . | a ey —=., = = a * 4 ; ! = |;
Source: Internet Archive copy of essar.com
More decks from Essar Shipping Limited.
Essar — Investor Presentation (January 2026)44 slides · January 2026
Essar — Investor Presentation (January 2026)43 slides · January 2026
Essar — Investor Presentation (January 2025)42 slides · January 2025
Essar — Investor Presentation (September 2024)43 slides · September 2024
Essar — Investor Presentation (July 2024)44 slides · July 2024
Essar — Investor Presentation (February 2024)27 slides · February 2024