Origin Energy Limited · ASX:ORG

Origin Energy — FY2010 Earnings Presentation

50 slides from Origin Energy's earnings presentation, Aug 24, 2010

  1. Slide 1: 2010 Full Year Results Announcement Media Presentation

    Financial Year Ended 30 June 2010 g 24 August 2010 Celebratingg a decade of growth 2010 Full Year Results Announcement Media Presentation

  2. Slide 2: Important Notice

    Important Notice This presentation does not constitute investment advice, or an inducement or recommendation to acquire or dispose of any g , in anyy jjurisdiction (including securities in Origin, ( g the USA). ) This p presentation is for information p purposes p only, y, is in a summaryy form,, an

  3. Slide 3: Outline

    Outline 1. Performance Highlights 2. Financial Review 3 Operational Review 3. 4. Outlook 3

  4. Slide 4: 1. Performance Highlights

    1. Performance Highlights

  5. Slide 5: Origin's Underlying Profit increased by 10% driven by strong Retail performance

    Origin’s Underlying Profit increased by 10% driven by strong Retail performance and contributions from new projects Statutory Profit (1) $612 million down 91% St t t Statutory E Earnings i g per Sh Share (1) 69 7 cps 69.7 d down 91% Underlying EBITDA $1,346 million up 10% Underlying Profit $585 mill

  6. Slide 6: Access to funds from APLNG dilution and redeployment into operating assets

    Access to funds as a result of the dilution of Origin’s CSG interest in Australia Pacific LNG and their ongoing redeployment into operating assets have been a significant contribution to growth over the last two years … Compound Average Growth Rate since listing: g • Total Shareholder Return: 28% •

  7. Slide 7: Major projects completed during the year

    During the year a number of major projects were successfully completed that added to earnings in the current year … • Completed expansion of the Mt Stuart Power Station • Commenced commercial operations p of the Cullerin Range g Wind Farm • Achieved full commercial production from Kupe • Contact com

  8. Slide 8: New opportunities to access additional resources

    We have created new opportunities to access additional resources … • Acquired 100% interest in the Ironbark CSG exploration permit (formerly Pangaea) • Achieved drilling success at Trefoil and Rockhopper in the Bass Basin and Redback South and Redback in the Perth Basin • Increased interest in shall

  9. Slide 9: 2. Financial Review

    2. Financial Review

  10. Slide 10: 2010 Financial Highlights

    2010 Financial Highlights Statutory Profit $612 million down 91% EPS – Statutory 69.7 cps down 91% Revenue $8,534 million up 6% Underlying y g EBITDA $1,346 $ , million up p 10% Underlying EBIT $896 million up 9% Underlying Profit $585 million up 10% EPS – Underlying 66.6 cps up 10% Group OCAT(1) $9

  11. Slide 11: Underlying Financial Performance

    Underlying Financial Performance ($ million) Jun 10 Jun 09 Change Revenue 8,534 8,042 6% U d l i EBITDA Underlying 1 346 1,346 1 219 1,219 10% Underlying EBIT 896 819 9% Underlying net financing costs (13) (32) -59% Underlying tax expense (232) (183) 27% Non-controlling Interests(1) share of Underly

  12. Slide 12: Underlying EBITDA up 10% to $1,346 million

    Underlying EBITDA up 10% to $1,346 million Segment ($ million) Jun 10 Jun 09 Change Exploration & Production 250 264 -5% Generation 182 107 70% Retail 568 479 19% Contact Energy 346 369 -6% Total 1,346 1,219 10% • Exploration & Production: Contributions from Kupe and increased interest in Otway were

  13. Slide 13: Increase in expenditure on acquisitions led to higher total capital expenditure

    A significant increase in expenditure on acquisitions led to an increase in total capital expenditure of 17% … Growth Capex • 28% lower than the prior year • Reductions in Generation resulting from Darling 2,837 Downs progressing from construction to 2,426 commissioning, completion of Uranquinty and

  14. Slide 14: Fully franked final dividend of 25 cps

    A fully franked final dividend of 25 cps, in line with the prior year, has been declared … • Ex-dividend date 31 August 2010 • Date of record 6 September 2010 • Payment Date 28 September 2010 • Dividend payout ratio of 75% of Underlying EPS • Dividend Reinvestment Plan will apply to this final divid

  15. Slide 15: 3. Operational Review

    3. Operational Review

  16. Slide 16: Exploration & Production

    Exploration & Production origin

  17. Slide 17: Exploration & Production: EBITDA reduced 5%

    Exploration & Production: EBITDA reduced 5% as contributions from new assets were offset by APLNG dilution, production constraints and higher exploration expense … • Underlying y g EBITDA reduced 5% to $ $250 million with positive contributions from Kupe and Otway offset by APLNG dilution, productio

  18. Slide 18: Gas production from Kupe and Otway offset production constraints

    Increases in gas production from Kupe and Otway have offset production constraints in the Bass and Cooper basins and declines in other minor assets • APLNG has increased production rates to in excess of 270 TJ/day • Kupe commenced production in January 2010; Origin’s share of gas production totalled

  19. Slide 19: Origin's 2P reserves increased 38% to 6,207 PJe

    Origin’s 2P reserves increased by 38% over the year to 6,207 PJe with a 40% increase in CSG reserves … Proved plus Probable Gas LPG Cond Oil TOTAL Reserves (PJ) (kT) (kbbls) (kbbls) (PJe) 30-Jun-09 4,267 1,650 17,312 6,691 4,484 Additions & revisions 1,774 510 5,887 (395) 1,827 Production (89) (94)

  20. Slide 20: Australia Pacific LNG increased production capacity

    Australia Pacific LNG has increased production capacity to supply the Darling Downs and Rio Tinto contracts … • APLNG remains Australia’s largest producer of CSG as it meets domestic market contracts • Production capacity has increased to over 300 TJ/day, and is expected to increase to 350 TJ/day or

  21. Slide 21: Australia Pacific LNG progressing toward final investment decision

    Australia Pacific LNG project continues to progress on track in readiness for a final investment decision at the end of the year Timing Milestone (Calendar Years)) 9 Initial Advice Statement (IAS) submitted Q1 2009 Project declared as Significant by the 9 Queensland Government Q Q2 2009 9 Curtis Isl

  22. Slide 22: Progress on regulatory approvals, FEED studies and early works contracts

    Significant progress has been made on regulatory approvals, FEED studies and early works contracts … Significant FEED and Early Works Contracts Awarded • $220 million contract signed with Savanna Energy Services for the provision of proprietary hybrid drilling and workover rigs for a five year term

  23. Slide 23: APLNG 2P reserves increased 40% over the year

    APLNG continues to mature its reserves and resources base with Proved plus Probable reserves increasing by 40% over the year • APLNG remains the largest holder of CSG reserves in Australia • APLNG participated i i d iin 317 wells ll dduring i the h year • 2P reserves increased by 2,878 PJe to 10,143

  24. Slide 24: New LNG projects from 2015 placed to meet growing gas demand

    New LNG projects coming online from 2015 are well placed to meet the expected growing worldwide demand for gas … bcm Capacity of New LNG Projects • Substantial volumes of new LNG capacity 100 has reached the market in recent years, however relatively limited capacity will be 80 added between now and

  25. Slide 25: Kupe production and increase in initial reserves

    Kupe has delivered six months production and an increase in initial reserves … Kupe • Construction and commissioning completed • Reliable plant operation established • Origin share of 6 months production was 4 4.8 8 PJ of gas, and around 620 kbbls of liquids • Initial 2P reserves increased by 11% in

  26. Slide 26: Bass Basin production constrained by maintenance program

    Production from the Bass Basin was constrained due to an extended maintenance program and subsequently recommenced production from one well … Maintenance activities being undertaken at BassGas Floodwaters in Coopers Creek BassGas Project Cooper Basin • Maintenance campaign at BassGas completed durin

  27. Slide 27: Expanded offshore and international exploration program

    In FY 2010 Origin commenced an expanded offshore and international exploration program Khorat Plateau Bang Nouan-1 B N 1 was suspended d d iin M May 2010 pending testing of the gas encountered in the Triassic Kachanarai sands. Costs capitalised at 30 June. Tested in August 2010 and found to be tight

  28. Slide 28: FY2011 offshore and international drilling activity

    In FY 2011 Origin will continue with the elevated level of offshore and international drilling activity seen in FY 2010 Khorat Plateau Two onshore appraisal wells on the Dao Ruang gas discovery in Block L15/50, Northeast Thailand, will be drilled towards the end of calendar year 2010 Offshore Vietna

  29. Slide 29: Generation

    Generation origin

  30. Slide 30: Generation: new capacity provided a 70% increase in EBITDA

    Generation: Investments in new generation capacity provided a 70% increase in EBITDA with all new capacity contracted to the Retail segment … • Underlying EBITDA increased 70% or $75 million to $182 million reflecting increased capacity payments f from the th Retail R t il segmentt as O Origin i i i

  31. Slide 31: Cullerin Range Wind Farm and Mt Stuart expansion

    The Cullerin Range Wind Farm commenced commercial operations on 1 July 2009 and provided a full year’s contribution … Cullerin Range Wind Farm Mt Stuart Power Station Expansion • Commercial Operation date of 1 July 2009 • Completed in November 2009 • Annual capacity factor of 41% for full year • Loc

  32. Slide 32: Darling Downs Power Station commissioned in June 2010

    Darling Downs Power Station was successfully commissioned in June 2010 becoming the largest combined cycle gas turbine plant in Australia • 630 MW baseload combined cycle gas plant including three 120 MW gas turbines and a 270 MW steam turbine • Emits less than half the greenhouse gas and requires l

  33. Slide 33: Mortlake development continues to progress

    The Mortlake development continues to progress with commissioning expected to commence in the December Quarter 2010 … Mortlake PS • 550 MW gas-fired peaking plant • Designed for conversion to CCGT at a later stage if required • Final project costs approximately $710 million(1) • Enables Origin to ma

  34. Slide 34: Mortlake will take thermal generation capacity above 3,600 MW

    The completion of Mortlake Power Station in FY 2011 will take thermal generation capacity available to Origin to over 3,600 MW … MW Origin's Thermal Generation Portfolio 7,000 • Darling Downs Power Station increased 6,000 Origin’s operating thermal generation capacity to 2,220 MW 5,000 2,670 • The M

  35. Slide 35: Wind generation expected to be dominant renewable source

    In the absence of a competitive alternate renewable technology, wind generation is expected to be the dominant source of energy to meet the Renewable Energy Target • Exercised option to acquire the Yass Valley Wind Farm project from Epuron with a capacity of between 222 MW and 420 MW, depending upon

  36. Slide 36: Retail

    Retail origin

  37. Slide 37: Retail: gross profit for gas and electricity increased

    Retail: Gross profit for gas and electricity increased from the combined impact of effective wholesale portfolio management and tariff increases … • Underlying EBITDA increased 19% to $568 million driven by higher gross profit and contributions from solar PV sales,, while cost to serve p per custome

  38. Slide 38: Integrated strategy across the energy supply chain

    Origin continues to develop its integrated strategy in Australia thereby optimising value across the energy supply chain Origin Owned/Contracted EPIC QSN Pipeline contract Gas-Fired Power Stations Enables Qld gas to be transported Uranquinty, Roma, Ladbroke to southern gas and electricity Grove Quar

  39. Slide 39: Customer numbers remained largely stable

    Customer numbers remained largely stable against increasing market competition with a decline of 0.8% relative to June 2009 Account Numbers (000’s) Natural Gas Electricity Total • A marginal net increase in gas customers was Jun 2009 867 1,743 , 2,610 , more than offset by a net decrease in Change +

  40. Slide 40: Sales of solar photovoltaic panels more than doubled

    Sales of solar photovoltaic panels in the year has more than doubled … • Origin has grown its solar business over the past five years and is beginning to see the benefits of this strategy with a doubling of residential and commercial sales revenue over the last 12 months to in excess of $100 million

  41. Slide 41: Additional sustainable energy offerings

    Origin has introduced additional sustainable energy offerings … • During the year Origin completed the acquisition of Cogent Energy, a niche provider of co- and tri-generation solutions • The business was integrated into the Origin business and two new plants installed and commissioned Illustration

  42. Slide 42: Contact Energy

    Contact Energy @) origin

  43. Slide 43: Contact Energy: earnings were lower

    Contact Energy: Earnings were lower due to higher energy, network and take-or-pay p yggas costs not fullyy recovered in the wholesale and retail markets due mainly to higher than normal rainfall • EBITDA was $346 million, million down 6% on last year, year primarily due to a lower margins in the Ele

  44. Slide 44: Major projects will restore portfolio flexibility

    A number of major projects due for completion in the coming year will restore flexibility to the portfolio … • Te Huka (23 MW, NZ$100m): The first phase of low- variable cost geothermal generation from the Tauhara resource area completed early early, below budget and operating above expected capacit

  45. Slide 45: 4. Outlook

    4. Outlook

  46. Slide 46: Development projects and acquisitions to contribute in the coming year

    In the coming year a number of development projects and acquisitions are expected to make initial, or increased contributions, to Origin’s performance • A full year contribution from the Kupe in New Zealand; • A full year contribution from Origin’s higher equity in Otway which increased from 31% to

  47. Slide 47: $3.4 billion of available liquidity

    Origin has significant financial capacity to fund future growth with $3.4 billion of available liquidity including cash and undrawn facilities • Completed C l t d refinancing fi i off A$2 A$2.00 billion billi of FY2011 debt and A$0.6 billion of additional financing in April 2010 • A$150 million bank

  48. Slide 48: Pursuing a wide range of opportunities to drive growth

    Over the next year Origin is pursuing a wide range of opportunities to drive continued growth … • A final investment decision by Australia Pacific LNG on its LNG project • The New South Wales Government’s energy asset sales process • Pursuit of a substantial portfolio of renewable energy opportuniti

  49. Slide 49: 2010 Full Year Results A Decade of Growth

    Full Year Ended 30 June 2010 g 24 August 2010 Celebratingg a decade of growth 2010 Full Year Results A Decade of Growth

  50. Slide 50: Further Information

    Further Information Media Lina Melero General Manager, Corporate Communication g gy Email: lina.melero@originenergy.com.au Telephone: +61 2 8345 5217 Mobile: +61 427 017 798 Website www.originenergy.com.au 50

Origin Energy — FY2010 Earnings Presentation on 6ix