  1. Slide 1: BMA: Taking the lead to deliver value and growth

    BMA: Taking the lead to deliver value and growth John Smith CEO BHP Billiton Mitsubishi Alliance Analyst Visit - October/November 2007

  2. Slide 2: Important Notices

    Important Notices Reliance on third party information The views expressed here contain information that have been derived from publicly available sources that have not been independently verified. No representation or warranty is made as to the accuracy, completeness or reliability of the informatio

  3. Slide 3: Presentation Structure

    Presentation Structure – BMA Overview – Deliver – Safety – Production – Cost management – Lead – Resource position – Product range – Grow – Key enablers (people, water, infrastructure) – Growth options BMA – Analyst Visit October/November 2007 3

  4. Slide 4: BMA Overview: Key facts

    BMA Overview Key facts – 9 Mines (7 OC and 2 UG) – 44 Mtpa Hay Point plus other port options – 4,800 employees – 3,000 contractors – 750 Mbcm total overburden – 58 Mt production (100%) – US$1.1 B EBIT (BHP Billiton share) BMA – Analyst Visit October/November 2007 4

  5. Slide 5: BMA Overview: Equipment snapshot

    BMA Overview Key facts Equipment Snapshot Overburden removed `34 draglines FY07 `28 shovels and large excavators 750 Mbcm total (531 Mbcm prime) `107 rear dump trucks to produce `35 haul trucks 80 Mt Raw coal `108 dozers to produce `135 other mobile equipment 58 Mt Product coal BMA – Analyst Visit O

  6. Slide 6: Mission and Strategic Objectives

    BMA Overview Mission and Strategic Objectives Our Strategy RDP OUR STRATEGY RDP v3 To create value through the mining, productionand high marketing quality coal of OUR MISSION resources, and the provision of innovative customer -focused and mark solutions et . O ur St r at egyRDP Strategic O bjectiv

  7. Slide 7: Deliver Full Potential From Existing Business

    BMA Overview Mission and Strategic Objectives Deliver Full Potential From Existing Business BMA – Analyst Visit October/November 2007 7

  8. Slide 8: Deliver: Safety

    Deliver Safety Total Recordable Injury Frequency Rate Number of incidents per million hours worked 45 – 14 per cent reduction in TRIFR 40 in 2006/07 35 – Health and Safety Strategic Plan 30 developed 25 – Fatigue Management a focus 20 – Contractor Management 15 procedure developed and being 10 rolle

  9. Slide 9: Continual production growth

    Deliver Continual production growth 60 Total Production (Mt) 55 50 45 40 2003 2002 2004 2005 2006 2007 FY Project Delivery Broadmeadow Stage 1 Expansion Stage 2 Expansion Poitrel HPX2 BW CHPP BMA – Analyst Visit October/November 2007 9

  10. Slide 10: Cost performance

    Deliver Cost performance ~25% One off ~50% Heated market A$/t product ~25% Sticky 2004 2007 BMA – Analyst Visit October/November 2007 10

  11. Slide 11: Cost Management

    Deliver Cost Management FY07 Cost Breakdown Other Entity Costs G&A <1% – Bulk of operating costs Other site 1% 3% are in earth moving and Offload & Stockpile 1% increasing strip ratios Rail Freight – Focus on lowest cost stripping options and 10% maximising coal recovery Processing Stripping 12% 50%

  12. Slide 12: BMA Stripping Study

    Deliver BMA Stripping Study Current Target – Study completed to identify lowest cost stripping solutions Continuous – Opportunities identified are being Haulage carried forward: – BMA Dragline Strategy T&S* T&S* – Site specific continuous haulage studies DRE^ DRE^ * T&S = Truck and Shovel ^ DRE = Dr

  13. Slide 13: Last Drop

    Deliver Last Drop Placement of charge within ±0.5m Locate TOC 9 – Reduces coal loss Accurate placement 9 – Extensive trials at Peak Variability in Hard Downs proving findings Cap 9 Hardcap protects coal from blast influence of blast – Prioritised program of rollouts has been Hardcap protects coal fr

  14. Slide 14: Reinforce Industry Leadership Position

    BMA Overview Mission and Strategic Objectives Reinforce Industry Reinforce Industry Leadership Position Leadership Position BMA – Analyst Visit October/November 2007 14

  15. Slide 15: Resource base to support ongoing sales growth

    Lead Resource base to support on going sales growth 60 Poitrel 50 South Walker Creek Total Sales (Mt) 100% Gregory 40 9.2% CAGR Norwich Park 30 Saraji Peak Downs 20 Riverside Goonyella 10 Sth Blackwater Blackwater 0 2007 1969 – 1.7 Bt Marketable Reserves (850 M attributable to BHP Billiton) – 9.8 Bt

  16. Slide 16: Resource Position

    Lead Resource Position Notes • Poitrel, South Walker Creek and Wards Well are BMC assets. • Total resource and reserve numbers exclude the Ridgeland and Humboldt properties BMA – Analyst Visit October/November 2007 16

  17. Slide 17: Product range

    Lead Product range Coal Type Coals HQHCC Peak Downs ~ 53% Goonyella Saraji HCC Norwich Park ~ 15% Gregory Crinum SHCC Blackwater ~ 8% Poitrel PCI South Walker Creek Price ~ 5% Poitrel SSCC Blackwater ~ 9% Note: thermal coal accounts for remaining 10% of production BMA – Analyst Visit October/Novembe

  18. Slide 18: Risk profile advantage

    Lead Risk profile advantage FY07 Queensland HCC and SHCC Sales Origin 100% Underground 50% Open Cut 0% Source: BMA Analysis BMA Managed Queensland Competitors – BMA’s higher proportion of open cut sales delivers a lower risk and less volatile EBIT stream – BMA Resource is expected to sustain >80% op

  19. Slide 19: Manage for Future Growth and Volatility

    BMA Overview Mission and Strategic Objectives Manage for Future Growth and Volatility BMA – Analyst Visit October/November 2007 19

  20. Slide 20: People – a key enabler

    Grow People – a key enabler – We need to attract and retain good people to deliver – Ongoing training and development of the workforce a priority – The focus of our community programs is to improve the quality of life in our towns BMA – Analyst Visit October/November 2007 20

  21. Slide 21: Water supply – a key enabler

    Grow Water supply – a key enabler Burdekin Dam Eungella Dam Goonyella Riverside Mine Broadmeadow Mine SWC Mine Braeside Moranbah region Poitrel Mine Borefield Peak Downs Mine Saraji Mine Dysart Norwich Park Mine Gregory Crinum Mine Selma Weir Emerald Bedford Weir Bingengang Weir Blackwater Blackwate

  22. Slide 22: Logistics – a key enabler

    Grow Logistics – a key enabler ABBOT POINT 14 / 21 / 35 Bowen 0 100km Collinsville Newlands System Mackay DBCT 60 / 68 / 85 HAY POINT 44 / 55-57.5 Northern Missing Link Moranbah Goonyella System Key XX / XX / XX Blackwater System Current Capacity (Mt) Rockhampton Committed Capacity (Mt) Emerald Blac

  23. Slide 23: Deep inventory of projects and future options

    Grow Deep inventory of projects and future options Proposed capex as at Nov 2007 $<0.5B $0.5–1B >$1B Greenfield Brownfield BW UG SRX GRX 3 Mtpa BMA GRX Incremental Kennedy 5 Mtpa Daunia HPX2 Poitrel HPX 3 PDX 8 Mtpa BW CHPP Red Hill Wards UG Well Feasibility Execution Pre-Feasibility Future Options

  24. Slide 24: Goonyella Expansion

    Grow Goonyella Expansion Goonyella Expansion • BMA ownership • Brownfield Expansion • 5-8 Mtpa HCC • Open cut (dragline and truck shovel) ± Underground (longwall) • New CHPP capacity & supporting infrastructure BMA – Analyst Visit October/November 2007 24

  25. Slide 25: Peak Downs Expansion

    Grow Peak Downs Expansion Peak Downs Expansion • Moving toward feasibility • BMA ownership • Mix of Brownfield & Greenfield Expansion • Up to 8 Mtpa HCC • Open cut (dragline and truck shovel) • New CHPP capacity & supporting infrastructure BMA – Analyst Visit October/November 2007 25

  26. Slide 26: Daunia

    Grow Daunia Daunia • Concept • BMA ownership • Greenfield Expansion • WCC / Thermal • Open cut (truck shovel) • New CHPP capacity & supporting infrastructure BMA – Analyst Visit October/November 2007 26

  27. Slide 27: Some other options

    Grow Some other options Wards Well • Concept, BMC ownership • Underground HCC Red Hill • Pre-concept, BMA ownership • Underground HCC Saraji Expansion • Concept, BMA ownership • Open cut HCC Blackwater Underground • Pre-concept, BMA ownership • Underground HCC / WCC Kennedy • Concept, BMA ownership

  28. Slide 28: Summary

    Summary – Current assets performing strongly – priority is safety, production and cost performance – Large, high quality resource base with growth options – Strong infrastructure positioning – Diverse portfolio to deliver reliability & quality to our customers BMA – Analyst Visit October/November 20

  29. Slide 29: Mark Chambers, General Manager, Blackwater Mine

    Mark Chambers General Manager, Blackwater Mine Analyst Visit - October/November 2007

  30. Slide 30: Important Notices

    Important Notices Reliance on third party information The views expressed here contain information that have been derived from publicly available sources that have not been independently verified. No representation or warranty is made as to the accuracy, completeness or reliability of the informatio

  31. Slide 31: Presentation Topics

    Presentation Topics – Overview – Safety (Zero Harm) – Geology – Coal quality – Mining equipment and production – Mine site cost break-up – Innovation / improvements BMA – Analyst Visit October/November 2007 31

  32. Slide 32: Overview – key statistics

    Overview – key statistics – Operations commenced 1967 – BWM and SBC merged 2001 – Annual production and sales approx. 13 Mt (Met + Thermal) – 90% of sales in the seaborne export market – Export coal is railed 300 km to ports at Gladstone for shipping – Approx 800 employees – 600 FTE contractors – 17

  33. Slide 33: Overview

    Overview – Coal extracted by open cut methods – Multi Seam operation with operating strike length of almost 60 km – Coal processing will be centralised at new Coal Handling & Processing Plant – Site product & dedicated port stockpile capacities of approx 450 Kt and 1 Mt tonnes respectively BMA – Ana

  34. Slide 34: Overview – strategic planning process

    Overview – strategic planning process BMA Mission To create value through the mining, production and marketing 5 YEAR BUSINESS PLA N 2008-2012 v3 OUR MISSION W E VALUE O URTHEME 17 Oct. ‘06 To crea te va ul et hrou gh th e mi ni ng, produc ti on and ma rke ti ng of hig h qual ti y • S afet y& t he •

  35. Slide 35: Safety (Zero Harm)

    Safety (Zero Harm) Total Recordable Injury Frequency Rate 60 – FRCP – Hazard awareness/identification 50 – Near miss reporting/analysis 40 – Accident/incident investigation 30 – Fatigue management 20 – Contractor Management (CMS) 10 – Safe Leadership program 0 2002 2003 2004 2005 2006 2007 BMA – Ana

  36. Slide 36: Geology – resources & reserves

    Geology – resources & reserves FY07 Marketable Reserve (256Mt) FY07 Measured, Indicated, 19 and Inferred (1,832Mt) Mine Life Based on 19 Marketable Reserve (yrs) BMA – Analyst Visit October/November 2007 36

  37. Slide 37: Geology - selective mining

    Geology - selective mining – Due to relatively flat dipping nature of deposit and good seam thicknesses coal seams maybe selectively mined or split – This provides processing flexibility plus ability to react to product type requirements Central and Southern Pit Areas Top Seam Northern Pit Areas (0.

  38. Slide 38: Coal Processing

    Coal Processing M L17 7 1 Industrial Town of Blackwater P Facility M L M L1 792 17 CAPRICORN HIGHWAY 62 ML M L1 1 86 600 ML ML MDL155 70 1907 10 73 ML 3 17 67 ML ML 17 70139 ML 1800 ML 17 59 ML 17 72 ML70091 ML70091 North ML1812 M L18 29 ML 1760 ML 70104 Plant South Plant Thermal New Plant CHPP ML70

  39. Slide 39: Mining Equipment

    Mining Equipment Equipment Snapshot – 8 draglines – 1 shovel and 2 large excavators – 15 rear dump trucks – 11 haul trucks – 22 dozers – 31 other mobile equipment BMA – Analyst Visit October/November 2007 39

  40. Slide 40: Production

    Production Thermal 14% Blackwater Coking 37% Blackwater Weak 49% 2007 Production – 12.276 Mt BMA – Analyst Visit October/November 2007 40

  41. Slide 41: Mine site cost breakdown – FY07

    Mine site cost breakdown – FY07 Other Offload & 3% Stockpile Rail Freight 1% 15% Processing 10% Stripping 57% Coal Mining 14% BMA – Analyst Visit October/November 2007 41

  42. Slide 42: Improvements - CHPP project

    Improvements - CHPP project – Feasibility completed October 2003 – Project Approval January 2004 – Commissioning from April 2007 – Full production from late 2007 – Commissioning underway early indications suggest improved yield, increased efficiency and cost management – New technology – Health and

  43. Slide 43: Improvements - Dragline project

    Improvements - Dragline 41 project – Purchased by BMA in 2005 – 74,000 hrs of operation – Significant upgrade and overhaul of machine during reassembly – Additional dragline to offset more truck and shovel stripping costs – Dragline operating at 120% RSL but upgrade will permit 125% RSL – First prod

  44. Slide 44: Improvements - Low density explosives

    Improvements - Low density explosives – Trials nearing completion – 2 Products – Loadex (Dry hole product) – XLoad (Wet hole product) – Results so far favourable – Potential for BMA wide replication LOADEX XLOAD – BMA100 Emulsion – BMA100 Emulsion – Rice Hulls – EPS Polystyrene – ANFO – ANFO BMA – A

  45. Slide 45: Improvements - Last Drop

    Improvements - Last Drop – Technical Studies and geological investigation - start of 3rd Qtr FY08 – Introduction of blasting methodologies to create “hard caps” - 3rd Qtr FY08 – Implementation (Removal of hard caps) - FY09 – Implementation reduces pit advance rate and maximises resource, improves co

  46. Slide 46: Summary

    Summary – Large mine and resource base with long life – Important asset for BMA in the long term – Range of coal products – Flexibility to respond to demand due to infrastructure platform – Business improvement initiatives delivering improved cost management BMA – Analyst Visit October/November 2007

  47. Slide 47: Sam Bonanno, VP Operations, Ports & Business Improvement

    Sam Bonanno VP, Operations, Ports & Business Improvement Analyst Visit - October/November 2007

  48. Slide 48: Important Notices

    Important Notices Reliance on third party information The views expressed here contain information that have been derived from publicly available sources that have not been independently verified. No representation or warranty is made as to the accuracy, completeness or reliability of the informatio

  49. Slide 49: Presentation Topics

    Presentation Topics – Safety – Environment & Community – Overview – Capabilities – Competitive Advantages – Expansion Capability BMA – Analyst Visit October/November 2007 49

  50. Slide 50: Safety (Zero Harm)

    Safety (Zero Harm) Total Recordable Injury Frequency Rate – FRCP 60 – Hazard awareness/identification 50 40 – Near miss reporting/analysis 30 – Accident/incident investigation 20 – Fatigue management 10 – Contractor Management (CMS) 0 – Safe Leadership program 2002 2003 2004 2005 2006 2007 BMA – Ana

  51. Slide 51: Environmental and Community Strengths

    Environmental and Community Strengths – Dust – Noise – Spillage – Water management BMA – Analyst Visit October/November 2007 51

  52. Slide 52: Overview of Operations

    Overview of Operations – 17 primary products and 22 blends – 64 customers in 21 countries – Hay Point – 24 hr x 365 days – Inloading ~ 4,000 trains – Outloading ~ 900 parcels on 400 ships – “Quality Terminal” not just a “Throughput Terminal” – Responsibility for the quality of all cargoes loaded, as

  53. Slide 53: Our advantages

    Our advantages – Strategic asset enabling control of the whole logistics chain – Linked and responsive to mine production and delivery – Capability to co-ordinate trains – Control the scheduling and berthing order of vessels BMA – Analyst Visit October/November 2007 53

  54. Slide 54: Stockyard allows flexibility

    Stockyard allows flexibility Our flexibility allows for options when confronted by variability – Designated stockpiles to minimise cross-contamination – Over 1,000 combinations available for efficient coal delivery – Stockyard Capacity with 14-16 Coal Types – Dry Season 1.45 Mt – Wet Season 1.0 Mt B

  55. Slide 55: Stacking and Reclaiming

    Stacking and Reclaiming – 5 Stacker Reclaimers, all capable of 6,000 tph automatic or manual stacking – Reclaim capacities of 2 x 6,000 tph, 1 x 5,000 tph and 2 x 3,500 tph – Flow splitters on each transfer point and yard machine to facilitate blending and maximise flow rate and direct loading oppor

  56. Slide 56: Functional Unit Capacities

    Functional Unit Capacities –Rail contracts are sufficient to meet current needs –Ongoing negotiation to meet growth profile –Nominal inloading capacity >50 Mtpa –Stockyard throughput capacity >50 Mtpa –Shiploading capacity of 43 - 45 Mtpa dependant on ship size and blending requirements BMA – Analys

  57. Slide 57: Shiploading Capability

    Shiploading Capability – Maximum Ship Size: Berth1: 175 k DWT, Berth2: +200 k DWT – Largest ship loaded: “Iron Pacific” (230,000 DWT) – Largest cargo : 207,769 t on “Iron Pacific” – Average Cargo Size : Approx 95,000 t BMA – Analyst Visit October/November 2007 57

  58. Slide 58: Cargo Destinations

    Cargo Destinations Over 64 Customers 21 Countries For FY07 Parcels sold 830 Ships loaded 370 Full Cape (100 – 230 kt) 33% Part loaded Cape 12% Panamax (55 – 100 kt) 35% Europe Korea Handysize (< 55 kt) 20% Middle East Japan China India Taiwan South America South Africa BMA – Analyst Visit October/No

  59. Slide 59: Competitive advantage

    Competitive advantage – Unique quality smoothing capability through the coal tracking system BMA – Analyst Visit October/November 2007 59

  60. Slide 60: Coal tracking

    Coal tracking – Visual representation of the individual stockpile BMA – Analyst Visit October/November 2007 60

  61. Slide 61: Competitive advantage

    Competitive advantage – Coal tracking - New High Resolution Quality View BMA – Analyst Visit October/November 2007 61

  62. Slide 62: Our advantages: Total Terminal Cost Index

    Our advantages – Low cost position versus all other coal exporting terminals Total Terminal Cost Index 2.50 2.00 Cost Index/tonne 1.50 1.00 0.50 0.00 HPCT BMA – Analyst Visit October/November 2007 Source: Barlow Jonker 62

  63. Slide 63: Competitive advantage: Tonnes per employee

    Competitive advantage – Hay Point productivity versus all other coal export terminals 300000 250000 Tonnes/Employee 200000 150000 100000 50000 0 Coal Export Terminals HPCT BMA – Analyst Visit October/November 2007 Source: CETOA 63

  64. Slide 64: Demurrage – Ships at anchor

    Demurrage – Ships at anchor BMA – Analyst Visit October/November 2007 Source: Coalsync Operations 64

  65. Slide 65: Expansion Execution Capability

    Expansion Execution Capability – HPX1 & 2 – Project plan - completed BMA – Analyst Visit October/November 2007 65

  66. Slide 66: Expansion Execution Capability

    Expansion Execution Capability – Completed HPX1 & 2 - on budget and in acceptable time frame After Before BMA – Analyst Visit October/November 2007 66

  67. Slide 67: Expansion Execution Capability: Tonnes shipped v capacity

    Expansion Execution Capability – We are shipping at expanded capacity Tonnes shipped v Capacity 11 10 9 Tonnes (Million) 8 7 6 Capacity 5 Actual 4 3 2 1 0 Qtr June 07 Qtr Sept 07 Quarter BMA – Analyst Visit October/November 2007 67

  68. Slide 68: Expansion Capability

    Expansion Capability – HPX3 could deliver 55-57.5 Mtpa total nominal capacity BMA – Analyst Visit October/November 2007 68

  69. Slide 69: Summary

    Summary Summary Summary – Hay Point Coal Terminal is a strategic asset for BMA: – allows us to manage the whole logistic chain from pit to customer – competitive advantages – low cost, high productivity, increased quality control – capacity to expand and a history of delivering on expansion activiti

  70. Slide 70: Dave Murray, President Coal

    Dave Murray President Coal Analyst Visit - October/November 2007

  71. Slide 71: Summary: In conclusion

    Summary In conclusion – Strong market driven by demand from India, China and Brazil – Product quality key - portfolio biased to premium end of the market – Premier assets in the world’s best metallurgical coal basin – Large, long life, high margin, expandable resource base – Strong portfolio of grow