    OTCQX: COPAF TSX-V: CPAU KINSLEY GOLD PROVEN POTENTIAL CLEAR PATH FORWARD NEVADA FOCUSED

  2. Slide 2: Forward Looking Statement

    Forward Looking Statement This presentation contains forward looking information within the meaning of Canadian securities laws and within the meaning of the U.S. Private Securities Litigation Reform Act of 1995 (collectively “forward-looking statements”). Forward-looking statements are necessarily

  3. Slide 3: CopAur is transitioning from Explorer to a near-term Nevada gold mine Developer

    CopAur is transitioning from Explorer to a near-term Nevada gold mine Developer Location of Kinsley Mountain Property, Eastern Nevada OTCQX:COPAF TSX.V:CPAU 3

  4. Slide 4: CopAur Minerals Inc.

    CopAur Minerals Inc.  Experienced Leadership – Management team led by CEO Andrew Neale, an experienced mining executive with over 35 years of international experience in all aspects of mining, and COO Chris Babcock with over 40 years experience in the design, construction, commissioning and operati

  5. Slide 5: Corporate Structure

    OTCQX:COPAF TSX.V:CPAU Corporate Structure Issued and Outstanding 120,509,609 Warrants 29,274,600 Finder Warrants 360,350 Options 12,010,500 Fully diluted 162,155,059 5

  6. Slide 6: Mineral Resource Estimate

    Mineral Resource Estimate 52% increase in total MRE ounces 89% of all ounces in the Indicated category 93% of all Indicated ounces within open pit constraints Only ~26% of total Indicated ounces are included in the initial PEA mine plan Oxide ounces recoverable on a heap leach Sulfide ounces will re

  7. Slide 7: Pit Constrained Resource

    Pit Constrained Resource Oxide resource in the Main Pit Western Flank & Main Pit Extension East Ridge Main Pit & Extension Sulfides located below the oxides. Western Flank resource amenable to open pit mining Open pit mining – lower cost and lower risk than underground mining OTCQX:COPAF TSX.V:CPAU

  8. Slide 8: Exploration Potential

    Exploration Potential  Gold (left) and arsenic (right) rock chip sampling results  Oxide resource to the north of Main Pit remain open and largely untested  Additional drilling could expand the oxide resource and extend the heap- leach mine life  Mining and processing of sulfides will be subject

  9. Slide 9: CopAur PEA Financial Metrics

    CopAur PEA Financial Metrics  Base case confirms viability  Consensus/current gold price materially improves returns  Capital intensity and initial mine life are optimization opportunities PEA Results Summary Units Base Case Consensus Spot Price Financials Gold Price US$/oz $3,200 $4,000 $4,500 P

  10. Slide 10: PEA Production Metrics

    PEA Production Metrics PEA Results Summary Units Production - Open Pit Mining and Heap Leach Stacking Total Waste Rock Tonnes Mined kt 53,069 Total Ore Tonnes Mined & Stacked kt 7,179 Total Tonnes Mined kt 60,248 Strip Ratio W:O 7.39 Nominal Life of Mine (LOM) years 4 LOM Average Daily Stacking Rate

  11. Slide 11: OPEX & CAPEX Estimates

    OPEX & CAPEX Estimates PEA Results Summary Units Operating Costs Mining Costs (total tonnes) US$/t $2.34 Mining Costs (ore tonnes) US$/t $14.99 Heap Leach Costs (ore tonnes) US$/t $7.17 G&A Costs (ore tonnes) US$/t $1.17 Contingency (ore tonnes) US$/t $2.33 Total Operating Costs (ore tonnes) US$/t $

  12. Slide 12: CAPEX Details

    PEA Results Summary Units Percent Capital Costs Mine US$M $0.65 0.6% CAPEX Details Mine Capitalized Waste US$M $33.09 28.2% Infrastructure US$M $6.38 5.4% G&A US$M $26.99 23.0% Plant US$M $34.96 29.8% Contingency US$M $15.31 13.0% Total Capital Costs US$M $117.38  Mine – all contract mining, pre-st

  13. Slide 13: Divestment – Williams Property to Omega Pacific (OMGA.CSE)

    Divestment – Williams Property to Omega Pacific (OMGA.CSE)  Located in the heart of BC’s Golden Horseshoe, located within the Stikine Terrane of north-central BC, linking the Golden Triangle with the Toodoggone District  Two “discovery holes” – WM24-01 (1.69 g/t over 104 m) & WM22-02 (2.16 g/t ove

  14. Slide 14: Divestment – Troy Canyon to Pravda Strategic Minerals Ltd.

    Divestment – Troy Canyon to Pravda Strategic Minerals Ltd.  Troy Canyon, former gold producer comprised of 59 contiguous claims (493 Ha), 150 km east of Tonopah, Nevada  Pravda (privco) can earn a 51% interest over 24 months by expending C$1.5M, and issuing 9.9% of I&O Pravda shares to CopAur  Pr

  15. Slide 15: Management

    Management ANDREW NEALE– CHIEF EXECUTIVE OFFICER & DIRECTOR CHANTELLE COLLINS – CHIEF FINANCIAL OFFICER Andrew is a mining executive with 35+ years of international Ms. Collins holds a Bachelor’s degree in Accounting and experience from exploration through to engineering, is a member of the Chartere

  16. Slide 16: CopAur Board of Directors

    CopAur Board of Directors ANDREW NEALE– CHIEF EXECUTIVE OFFICER Andrew is a mining executive with 35+ years of international experience from exploration through to engineering, construction, and operations. He has held senior leadership roles with Freeport-McMoRan, Hemco Nicaragua, Merdeka Copper &

  17. Slide 17: CopAur - Summary

    CopAur - Summary Permitting is the critical path to production and can now advance following completion and filing of the PEA No obvious fatal permitting issues have been identified at this stage The Kinsley Heap-Leach Project uses conventional, well-understood mining and processing methods in an es

  18. Slide 18: Contact Us