  1. Slide 1: Dragon Mining Limited: Positioned for Growth

    DRAGON MINING LIMITED Positioned for Growth Zurich Z i hCConference f 26 February 2010 The information in this presentation that relates to Exploration Results, Mineral Resources or Ore Reserves is based on information compiled by Mr Neale Edwards BSc (Hons), a Member of the Australian Institute of

  2. Slide 2: Disclaimer

    Disclaimer The purpose of this presentation is to provide general information about Dragon Mining Limited (the "Company"). Unless otherwise stated herein, the information in this presentation is based on the Company Company's s own information and estimates. estimates This presentation does not cons

  3. Slide 3: Scandinavian Gold Producer

    Scandinavian Gold Producer Svartliden Gold Mine • 40,000 ounces per annum Vammala Production Centre • Orivesi 25,000 ounces • Jokisivu 10,000 ounces Unhedged from September 2009 Cash & bullion (31 Dec 09) $10.5m Produce 75,000 oz in 2010

  4. Slide 4: Corporate Overview

    Corporate p Overview I Issued d Capital C it l • Fully Paid Ordinary Shares 737.3m • Options (exercise prices 14c – 21c) 13.4m • Convertible Notes (Feb 2011) 11 1m 11.1m • Market Capitalisation (19 Feb 2010) A$66.4m Substantial Shareholders • Nicolas Mathys 130.4m 17.7% • B i kl Mi Brinkley Mining i

  5. Slide 5: Corporate Overview: Directors

    Corporate p Overview Directors Andrew Daley Tapani Järvinen Non- Executive Chairman Non-Executive Director Mr Daley is a mining engineer and worked for Anglo Mr Järvinen retired as President and CEO of Outotec Oy in American and Rio Tinto in Africa before moving to Australia. December 2009 and is cu

  6. Slide 6: Svartliden Gold Mine: Location

    Svartliden Gold Mine Location Dragon’s Dragon s Cash Engine

  7. Slide 7: Svartliden Gold Mine: Statistics to December 2009

    Svartliden Gold Mine Statistics to 31 December 2009 Project to Date 2009 Ore Processed 1,487,665 t 337,945 t H dG Head Grade d 4 86 g/t 4.86 /t 3 91 g/t 3.91 /t Recovery 90.78 % 88.10 % Gold Produced 210,901 oz 37,400 oz 7% • 2009 Cash Cost US$584 2% Mining 42% • 2009 Selling Price US$905 Crushing P

  8. Slide 8: Svartliden Gold Mine: Transitioning underground in 2010

    Svartliden Gold Mine Transitioning underground in 2010 Aug 08 Jan 09

  9. Slide 9: Svartliden Gold Mine: Mine Plan

    Svartliden Gold Mine Mine Plan • 1 kkm underground d d exploration l ti d decline. li • 100,000 tonne test mining.

  10. Slide 10: Svartliden: Increase mine life

    Svartliden Gold Mine Increase mine life more than 5 years 1. Eastern Zone Open Cut Extension 4,600m - A$0.5m (expectation 10,000 oz) 1 2. North & Main Lode Depth Extension 0m 10,000m - A$1.0m (expectation100,000 oz) 2 Level 100m Level 3 200m 3. North & Main Lode Depth Extension Level 4,000m - A$0.5m

  11. Slide 11: Mine Corridor – Svartliden West & Tallberget

    Svartliden Gold Mine Mine Corridor – Svartliden West & Tallberget • Strike extensions of Svartliden host sequence. • Bedrock and reconnaissance drilling across areas of gold anomalism.

  12. Slide 12: Svartliden Gold Mine: Regional

    Svartliden Gold Mine Regional • 214 1 km² regional holding 214.1 holding. • 50 km strike of highly prospective geological sequences centrally l located t d within ithi th the “G “Gold ld Li Line”. ” • Potential to host a number of gold deposits. p • Extensive coverage by detailed airborne geophysics

  13. Slide 13: Svartliden Gold Mine: Open Pit

    Svartliden Gold Mine Open Pit Apr 08 Oct 09

  14. Slide 14: Svartliden Gold Mine: Tailings Dam

    Svartliden Gold Mine Tailings Dam Jan 08 Oct 09

  15. Slide 15: Finland

    ORIVESIL ' VAMMALA Kaapelinkulma ie JOKISIVU Gold Project KAAPELINKULMA Jokisivu Gold Mine

  16. Slide 16: Vammala Production Centre

    Vammala Production Centre Statistics to 31 December 2009 Project to Date 2009 Ore Processed 437,744 t 222,018 t H dG Head Grade d 6 04 g/t 6.04 /t 5 51 g/t 5.51 /t Recovery 83.25 % 82.77 % Gold Produced 70,859 oz 28,749 oz 3% • 2009 Cash Cost US$690 17% Mining • 2009 Selling S lli P Price i US$971 T

  17. Slide 17: Orivesi Gold Mine: Increasing Mine Life

    Orivesi Gold Mine Increasing Mine Life 1 2 4 3

  18. Slide 18: Orivesi Gold Mine: Exploration Strategy

    Orivesi Gold Mine Exploration Strategy Potential new pipe cluster • Drilling to follow up intercepts intercepts. • Exploratory drive to open up mineralisation.

  19. Slide 19: Orivesi Gold Mine: Decline Portal

    Orivesi Gold Mine Decline Portal Jan 10 Aug 08

  20. Slide 20: Orivesi Gold Mine: Ore Loading for Transport

    Orivesi Gold Mine Ore Loading for Transport to Vammala Aug 07

  21. Slide 21: Jokisivu Gold Mine

    Jokisivu Gold Mine • Resource 1,576,000 tonnes @ 6.46 g/t gold (324,000 ounces). • Decline development in 2010 • Produce 10,000 ounces in 2010.

  22. Slide 22: Jokisivu Gold Mine

    Ka Jokisivu Gold Mine Dragon Mining z Es : HUE. 307. HU/IS-345 eHUAS 319 HUNIS-344 HUNSS-343 —smeN8 HULIS—246 HUIS 382 HUST AT ~eHOUS 288, i | \ 6 779 500 mN = \ \ \ a74, 386 e377 »372 369 0373 371 9375 Pi 2.426 500 427 000 mN ! al 2.425 500 mN | 2 426 000 mN

  23. Slide 23: Jokisivu Gold Mine: Drill targets

    Jokisivu Gold Mine 1. Area between Arpola and Kujankallio 1 3,000m - A$0.4m (expectation 50,000 oz) 2. Kujankallio 250-500m 8,000m - A$1.0m (expectation 100,000 oz) 3 Arpola 200-500m 3. 3 5,000m - A$0.6m (expectation 150,000 oz) 2 • Open pit mining commenced in 2009 at Kujankallio. • Drilling to est

  24. Slide 24: Kaapelinkulma Gold Project

    Kaapelinkulma p Gold Project j • R Resource off 161 161,000t 000t att 6 6.2 2 g/t /t - 32,000 oz. • Down plunge and along strike potential. t ti l • Production in 2012. • Underground potential. • 4,200m of drilling commenced.

  25. Slide 25: Kuusamo: The Next Production Centre

    Kuusamo The Next Production Centre • Established resources of 178,800 ounces. • Resources open at depth. • Warrants an agressive exploration program over 3 years to significantly increase resources. • Potential to be next production centre.

  26. Slide 26: Hanhimaa

    Hanhimaa • Holding encompasses 20 kilometres strike of the Hanhimaa Shear Zone. • Gold potential identified in the early 2000’s. • Discovery of three gold prospects - Kiimalaki, Kellolaki, Kiimakuusikko. • Significant number of untested gold anomalies. • Local and worldwide analogies.

  27. Slide 27: Finland: Exploration

    Finland Exploration Dec 07 Jun 08

  28. Slide 28: Production Project Pipeline

    Production Project j Pipeline p

  29. Slide 29: DRA – 40 Percent Interest

    DRA – 40 Percent Interest • Consolidation of all mineral rights under one entity. • Substantial inventories of chromium, iron and nickel for the development and production of refined stainless alloys. • Access to proposed rail line to service Oakajee Industrial Estate and proposed deep water port.

  30. Slide 30: DRA – 20 Percent Free Carried Interest: Zara Project, Eritrea

    DRA – 20 Percent Free Carried Interest Zara Project - Eritrea • Koka Deposit – Indicated Resources of 5 Mt at 5.8 g/t gold for 944,000 ounces. • Scoping Study results in annual production of 110,000 ounces at a cash cost of US$424 an ounce. • Feasibility Study to be completed in mid 2010.

  31. Slide 31: Overview

    Overview • Svartliden, Sweden and Vammala, Finland Production Centres. • Immediate potential to add to mine reserves reserves. • Excellent exploration potential – near mine & regional. • Unhedged. • Positioned for Growth.

  32. Slide 32: Appendices: Gold Resource Inventory

    Appendices Gold Resource Inventory as at 1 August 2009 Project Tonnes Gold (g/t) Gold (ounces) SVARTLIDEN Measured 171,700 3.3 18,500 Indicated 1,154,700 2.9 108,100 Inferred 280,000 3.3 29,300 Total 1,606,400 3.0 155,900 VAMMALA Measured 167,500 , 6.7 36,000 , Indicated 1,296,700 5.7 238,900 Inferr