Kgl Resources Limited · ASX:KGL
Kgl Resources — Kentor Gold — Investor Presentation (February 2011)
21 slides from Kgl Resources's investor presentation, Feb 7, 2012
Slide 1: Kentor Gold Investor Presentation
For personal use only Kentor Gold February 2011 Investor Presentation
Slide 2: Agenda
Agenda For personal use only 1. Andash Gold Copper Project - Kyrgyzstan 2. Jervois Copper Gold Project – Australia 3. Murchison Gold Project - Australia 2
Slide 3: Company Strategy: Acquire Develop Operate
Company Strategy For personal use only Acquire Develop Operate 3
Slide 4: Corporate Structure
Corporate Structure For personal use only KENTOR GOLD 80% 100% Andash Mining Company (Kyrgyz Republic) Jinka Minerals (Australia) 100% 100% 100% Kyrgyz Republic Andash Murchison Gold Copper Jervois Copper Gold Silver Gold Lead X Zinc Jervois X X Murchison
Slide 5: Andash Project Economics (KGL 80%)
ANDASH PROJECT Andash Project Economics (KGL 80%) For personal use only Operating Costs (US$/t) Capital Cost US$96m * Cost component Phase 1 Phase 2 (US$/t) (1.5mtpa) (3mtpa) Cash cost US$29/oz Au Mining 3.46 3.46 (after Cu credits and royalty - Copper US$2.75/lb) Processing 8.62 7.09 G&A 3.38 1
Slide 6: Andash Summary
ANDASH PROJECT Andash Summary For personal use only Developing one of the world’s lowest cost gold mines Growing the resource base Final negotiations with local community 12 month construction programme 6
Slide 7: Jervois Copper Project
JERVOIS PROJECT Jervois Copper Project For personal use only • 100% Interest • Granted Mining License • Land Holding 38 km2 • 12km of prospective strike Outcropping Copper Ore 7
Slide 8: Reward Ore body Long Section
JERVOIS PROJECT Reward Ore body Long Section For personal use only Inferred Copper Resource of 11.9 Mt @ 1.3% Cu and 25.2 g/t Ag 150,500t of contained copper and 9.7 m oz contained silver Additional Exploration Potential of 5.0 – 10.0Mt @ 0.75 to 1.25% Cu and 10 to 25g/t Ag at a 0.5% Cu cut of
Slide 9: Bellbird ore body Long Section
Bellbird ore body Long Section For personal use only Green circles are drill hole pierce points 9
Slide 10: Murchison Gold Project
Murchison Gold Project Murchison Gold Project For personal use only • Consists of the Burnakura and Gabanintha sites • 700,000 ounce Inferred Resource • Plan to commence production in June 2012 10
Slide 11: Existing Infrastructure
Murchison Gold Project Existing Infrastructure For personal use only 11
Slide 12: Project Resource
Murchison Gold Project Murchison Gold Project Resource For personal use only Inferred Resource (0.5 g/t gold cut off) Mt Au g/t Au oz 15.1 1.5 719,000 20,000 m RC drill programme underway to infill and increase resource 12
Slide 13: Stage Growth Strategy
Murchison Gold Project 4 Stage Growth Strategy For personal use only 1. Refurbish and restart existing CIL Plant 2. Add a heap leach circuit to treat low grade ore 3. Expand plant to 500,000 tpa 4. Flotation of copper gold ore 13
Slide 14: Stage 1 Restart CIL Plant
Murchison Gold Project Stage 1 Restart CIL Plant For personal use only Convert from CIP to CIL Expand to 260,000 tpa Commence production in June 2012 Initial Production Rate 24,000 oz gold p.a. Capital cost $14.8m ($2m spent already) Stage 1 cash cost $1,224 / oz High grade production
Slide 15: Crushing and Heap Leaching Equipment
Murchison Gold Project Crushing and Heap Leaching Equipment For personal use only Note: Photographs of equipment on site at the Indee mine site 15
Slide 16: Gabanintha HeliTem Survey
Murchison Gold Project Gabanintha HeliTem Survey For personal use only HeliTem Results Northern Leases 16
Slide 17: HeliTem Survey Southern Leases
Murchison Gold Project HeliTem Survey For personal use only HeliTem Results Southern Leases 17
Slide 18: Kentor Group Resources
Kentor Group Resources For personal use only Grade Grade Grade Gold Copper Silver Tonnes (mt) Au g/t Cu% Ag g/t (oz) (t) (Oz) Andash Inferred 0.38 0.93 0.25 11,350 950 Jervois Inferred 11.9 1.3 25.2 150,500 9,700,000 Burnakura Inferred 10.6 1.5 516,000 Gabanintha Inferred 4.5 1.4 203,000 Andash Indi
Slide 19: Conclusion
Conclusion For personal use only • Near term gold production • Active exploration programmes at all Australian sites • Strong news flow • Strong cash position • Pipeline of projects • Increasing resources 19
Slide 20: Key Contacts
KEY CONTACTS For more information contact For personal use only Simon Milroy on +61 7 31213206 or visit www.kentorgold.com ASX Code: KGL Level 9, 40 Creek Street, Brisbane, QLD, AUSTRALIA 4000 Fax: +61 7 3121 3030 Forward-Looking Statements: This presentation includes certain “Forward-Looking Statem
Slide 21: Competent Persons Statements
For personal use only Competent Persons Statements The information in this report that relates to mineral resource estimation for Gabanintha and Burnakura is based on work completed by Mr Jonathon Abbott is a member of the Australasian Institute of Mining and Metallurgy. Mr Abbott has sufficient