Larsen & Toubro Limited · NSE:LT

Larsen & Toubro — FY2002 Earnings Presentation

50 slides from Larsen & Toubro's earnings presentation, June 2002

  1. Slide 1: Larsen & Toubro Limited Performance for FY 2002

    Larsen & Toubro Limited Performance for FY 2002 June 2002 1

  2. Slide 2: Disclaimer

    Disclaimer This presentation contains certain forward looking statements concerning L&T’s future business prospects and business profitability, which are subject to a number of risks and uncertainties and the actual results could materially differ from those in such forward looking statements. The r

  3. Slide 3: Highlights of FY 2002 performance

    Highlights of FY 2002 performance X Order book grew by 4.7% to Rs.109.22 billion X Sales and service income at Rs.83.59 billion registered a 6.8% increase X Profit before taxes of Rs.4.01 billion higher by 18.3% – Reduction in interest cost by Rs.0.45 billion X Profit after taxes increased by 10% to

  4. Slide 4: Economic scenario

    Economic scenario X Industrial sector registers a marginal growth of 2.7% – Capital goods sector had a negative growth of 4.1% X Overall GDP growth of 5.4% on the back of a higher agricultural growth and services sector X Fiscal situation affected by shortfall in tax collections and disinvestment re

  5. Slide 5: Business Scenario

    Business Scenario X Lackluster growth in investments – Many projects either shelved or delayed – Overcapacity in many industries stifle new investments X Activity in infrastructure sector subdued as yet – Spending on road projects yet to take off – Housing continued to show robust growth X No signif

  6. Slide 6: Initiatives to meet the challenges of today and tomorrow

    Initiatives to meet the challenges of today and tomorrow X Major thrust on exports – Almost trebled over the last three years – Exports grow by 56% to Rs. 11.1 billion over the last year X Manpower rationalization – Over 1500 people opt for Voluntary Retirement Schemes over 3 years – Management Lead

  7. Slide 7: Segmental review

    Segmental review 7

  8. Slide 8: Engineering and Construction

    Engineering and Construction 8

  9. Slide 9: The year that was

    The year that was X Order book and sales grow by 2% and 6% respectively – Longer gestation orders resulting in significant increase in average execution cycle – “Zero dates” delayed in certain large value projects X Margins dropped to 10.1% from 11.7% – Change in project mix – Under utilization of r

  10. Slide 10: Highlights

    Highlights X Landmark jobs completed – Khandala-Lonavala bypass – “Most Outstanding Structure” awards for Narmada,Yamuna,Kune bridges – Country’s largest coal handling plant at Paradip Port – 500 MW First End Shields for TAPP delivered to NPCIL – Heaviest DHDS Reactor ( 295 MT) delivered on time – I

  11. Slide 11: Major orders executed FY 02

    Major orders executed FY 02 HRC Compressor Module For ONGC (785 Mt) Clamp-on Structures For ONGC First Time Fabricated In India (1900 MT), 12 Platforms Completed 20 Days Ahead Of Schedule First Time Executed By L&T • 11 Completed 69 Days Ahead Of Schedule

  12. Slide 12: Reels (840 Mt) For Wellstream, UK

    Reels (840 Mt) For Wellstream, UK Completed 22 Days Ahead Of Schedule 12

  13. Slide 13: Indian School of Business, Hyderabad; Paradip Coal Terminal

    Indian School of Business, Hyderabad Jack Welch R&D Center for GE – ITC, Bangalore PARADIP COAL TERMINAL:BELT CONV. SYSTEM & YARD MACHINES Pre Heater Building, Chettinad Cements, Karikkali, TN FIRST FULLY MECHANISED COAL TERMINAL IN INDIA 13

  14. Slide 14: S.S. Desalination Eqpt. (580 Mt) for SIDEM, France

    S.S. Desalination Eqpt. (580 Mt)-70 Nos. For SIDEM, France First Time Manufactured & Exported 14 Completed 30 Days Ahead Of Schedule

  15. Slide 15: DHDS Reactor for KRL-295 Tonnes

    DHDS Reactor for KRL-295 Tonnes 15

  16. Slide 16: Recycle Column for Bechtel, USA-610 Tonnes

    Recycle Column for Bechtel, USA-610 Tonnes 16

  17. Slide 17: Sector-wise order backlog

    Sector-wise order backlog End Mar '01 End Mar '02 Others Others 9% Pow er 13% Pow er 19% 25% Process & Hydrocarbon Process & 20% Hydro carbon Infrastructure 16% Infrastructure 52% 46% 17

  18. Slide 18: Execution cycle analysis

    Execution cycle analysis Major orders in backlog Mar ‘01 Mar ‘02 11% 0-12 months 20% 25% 12-24 months 43% 38% 24-36 months 22% 13% 36-48 months 5% 13% > 48 months 10% 18

  19. Slide 19: Projects where Zero Date has been delayed

    Projects where “Zero Date” has been delayed Rs.billion Tirupur Water Supply 4.85 Konaseema Power Project 4.07 Essar Projects Limited 1.69 19

  20. Slide 20: Divisional Performance Summary

    Divisional Performance Summary •Rs.billion FY 2002 FY 2001 % change Order Booking Domestic 63.40 55.59 14.0% Export 8.86 16.42 (46.0)% Total 72.26 70.93 1.9% Sales Domestic 39.23 40.23 (2.5)% Export 8.47 4.68 81.0% Total 47.70 44.91 6.2% Order Backlog 118.05 92.22 28.0% PBDIT/Sales 10.1% 11.7% PBIT

  21. Slide 21: Efforts on cost reduction

    Efforts on cost reduction X Extensive global sourcing X In-house efforts on design optimisation – Cost advantage X Major IT initiatives – Efficiency improvements – eProcurement – Knowledge Management – Customer relationship management O All projects to move to the module in a phased manner X Reducti

  22. Slide 22: Electrical & Electronics

    Electrical & Electronics 22

  23. Slide 23: The year that was

    The year that was X Overall electrical sector registers a marginal growth of 1.7% – Switchgear market had a negative growth X Divisional Sales grows marginally by 2% X Drop in margins – Predatory pricing by MNCs to gain market share – Efforts on product development and export market development – Ri

  24. Slide 24: Efforts on export market development

    Efforts on export market development X Deeper penetration into overseas markets – Major countries being UK, France, China, Qatar, Oman, Kuwait, Myanmar, Bangladesh, Africa – Order booking grew from Rs.250 mio to Rs.460 mio – Sales from Rs.226 mio to Rs.380 mio X International accreditation for produ

  25. Slide 25: Technology edge facilitated by a strong R&D

    Technology edge facilitated by a strong R&D X Life cycle management of products X State-of-the-art R&D facilities – ProE workstation networked with Tool Room – Balanced design skills in electronics, electrical and mechanical streams – EmSyS for high end Electronics, Embedded Software and Systems X U

  26. Slide 26: Divisional Performance Summary

    Divisional Performance Summary •Rs.billion FY 2002 FY 2001 % change Sales Domestic 6.67 6.79 (1.8)% Export 0.38 0.22 72.7% Total 7.05 7.01 0.6% PBDIT/Sales 12.8% 16.5% PBIT 0.79 - Segmental Assets(Net) 4.36 - 2% drop in PBDIT for FY 02 due to change in expense allocation basis 26

  27. Slide 27: Several initiatives to mitigate dropping margins

    Several initiatives to mitigate dropping margins X Efficiency improvements and cost cutting – Value engineering O Savings in materials cost by around 1% for standard products during FY 02 – Use of Six Sigma, First-time-right approach, Kanban X 90% of vendors and 7% of stockists do business thru’ int

  28. Slide 28: Cement

    Cement 28

  29. Slide 29: Market Scenario

    Market Scenario X Demand growth of 9.6% during the fiscal year – Demand from infrastructure sector subdued as yet – Housing remained the main driver for demand – Gujarat reconstruction also helped X Over capacity still persists – New capacities aggravated the situation X Prices were volatile since J

  30. Slide 30: Divisional Performance

    Divisional Performance X Domestic sales volume grows by 6.5% X Margins improves from 16.9% to 18.5% – Ex-factory realisation up by 4% – Several Cost reduction initiatives X Higher exports of cement –better value addition – 1.01 mt against 0.7 mt X Continued efforts to improve operating efficiencies

  31. Slide 31: Volatile cement prices

    Volatile cement prices Ahmedabad Mumbai 180 180 160 RS. per bag 160 Rs per bag 140 140 120 120 100 100 r r r n n l l ct ct Ju Ju Ap Ap Ap Ja Ja O O r r r n n l l ct ct Ju Ju Ap Ap Ap Ja Ja O O Kolkota Chennai 200 200 180 180 Rs. per bag Rs. per bag 160 160 140 140 120 120 r r r n n r r r l l n n l l

  32. Slide 32: Towards a fully optimised business

    Towards a fully optimised business X L&T’s cement is among the most preferred – Consistent Quality – Commands a premium price in all markets X L&T is already among the lowest cost producer, if not the lowest – Continuing efforts to reduce cost further X A strong and well spread distribution net work

  33. Slide 33: Consistent quality is our strength

    Consistent quality is our strength X State of art Control & Automation systems with computer controlled operations. X Systems at Awarpur and Hirmi upgraded X On-line quality control to manage quality of the product. X X-Ray Fluorescence analyzers to enable rapid and accurate quality control. X Use o

  34. Slide 34: Consistent improvement in operating efficiencies

    Consistent improvement in operating efficiencies Heat Consumption Power Consumption 750 100 98 734 96 726 725 714 708 95 92 701 90 700 90 87 675 85 650 80 FY 98 FY 99 FY 00 FY 01 FY 02 FY 98 FY 99 FY 00 FY 01 FY 02 Kcal per tonne of cement Units per tonne of cement 34

  35. Slide 35: Cost increases well below inflation

    Cost increases well below inflation Variable cost index 100 100 95 91 87 88 90 83 85 80 75 FY 98 FY 99 FY 00 FY 01 FY 02 35

  36. Slide 36: Further reduction in costs

    Further reduction in costs X Opportunistic purchases to manage costs – Switch from imported coal to indigenous coal – Purchase from smaller coal miners X “Total Productive Maintenance” practiced in Gujarat and Andhra plants for “Comprehensive Asset Care Regime” – Employee ownership of plant, ensures

  37. Slide 37: Further reduction in costs

    Further reduction in costs X Packaging costs reduced through value engineering – Specifications optimised – Use of laminated bags in place of pure paper bags X Fixed costs reduced by Rs. 320 million during FY 02 37

  38. Slide 38: Minimize the Total Delivered Cost

    Minimize the Total Delivered Cost X Reduce the number of stocking points and increase direct despatches – Reduce secondary freight – Reduce handling cost – Reduce backtracking – Reduce operating cost of dumps X Maximize backhauling X Optimisation software in place to manage the net work to minimise

  39. Slide 39: Divisional Performance Summary

    Divisional Performance Summary FY 2002 FY 2001 % change Sales-Mio Tonnes Domestic 9.53 8.95 6.5% Exports 2.40 2.36 1.7% 11.93 11.31 5.5% Sales - Rs. Billion 24.59 22.77 8.0% Ex-factory realistion * 1303 1251 4.2% PBDIT/Sales 18.5% 16.9% PBDIT/Sales ( Incl.Fiscal benefits) 19.8% 19.0% PBIT 2.48 - Seg

  40. Slide 40: Summary Financial Performance

    Summary Financial Performance 40

  41. Slide 41: Profit & Loss Account

    Profit & Loss Account FY02 FY01 %Change Order Booking 109.22 104.27 5% Sales 83.58 78.25 7% Other Income 2.20 2.07 6% Total Revenue 85.78 80.32 Cost of sales 75.25 70.19 Operating Margin 10.53 10.13 % to total revenue 12.3% 12.6% Interest 3.16 3.61 (12)% Depreciation 3.36 3.13 PBT 4.01 3.39 18% Tax

  42. Slide 42: Savings in financing costs

    Savings in financing costs X Refinancing and pre-payment of various high cost borrowings – More than Rs.7 billion refinanced – Prepayment of Rs.3.4 billion X Judicious use of derivatives to hedge costs X Effective monitoring of capital employed 42

  43. Slide 43: Balance Sheet

    Balance Sheet Rs. Billion 31-Mar-02 31-Mar-01 SHAREHOLDERS' FUNDS Share Capital 2.49 2.49 Reserves 30.95 37.51 Net Worth* 33.44 40.00 LOAN FUNDS Secured Loans 27.91 30.02 Unsecured Loans 7.53 12.61 Deferred Tax Liabilities (net) 8.52 TOTAL SOURCES 77.40 82.63 Net Block incl. CWIP 43.06 46.71 Investm

  44. Slide 44: Cash Flow Statement

    Cash Flow Statement Rs.billion FY 02 FY 01 Net Profit before tax and extraordinary item 4.01 3.39 Operating Profit before working capital changes 9.76 9.44 Change in working Capital 2.65 (3.14) Operating Cash Flow 12.41 6.30 Direct Taxes Paid 0.70 (0.68) Investment in Fixed Assets (2.86) (3.89) Free

  45. Slide 45: Outlook FY 2003

    Outlook FY 2003 45

  46. Slide 46: E&C outlook: strong backlog, 15% revenue growth in FY 03

    E&C X Strong backlog of over Rs.110 billion X Revenue growth of 15% in FY 03 X Following sectors will offer new opportunities – Refineries & Petrochemicals O Postponed expansion plans expected to take off – Power – Infrastructure – Roads, Bridges, Airports, Water – International Project Business X S

  47. Slide 47: Order prospects

    Order prospects X Likely value prospects in various sectors – Infrastructure Rs.35 billion – Refineries & Petrochemicals Rs. 36 billion – Power Rs.20 billion – International Rs. 15 billion L&T well positioned to exploit these opportunities 47

  48. Slide 48: Electricals

    Electricals X Price cuts seem to have abated – Margins could improve if competitive pressures ease X Two new products to be introduced – Both these products won award for “Good Design” in the recent Elecrama Exhibition X Ongoing cost cutting measures 48

  49. Slide 49: Cement

    Cement X Continued strong demand growth of 8-10% – Low interest rates would encourage investments in housing – Investments in roads and other infrastructure projects X Capacity addition slowing down – No major greenfield/brownfield capacity planned – Most upgradation efforts completed – Blended ceme

  50. Slide 50: We make the things that make India proud

    We make the things that make India proud 50

Larsen & Toubro — FY2002 Earnings Presentation on 6ix