Boral Ltd.

Boral — Technical Presentation (October 2020)

48 slides from Boral's technical presentation, Oct 28, 2020

  1. Slide 1: Dunmore Sand & Soil Modification 2 - Stage 5

    Dunmore Sand & Soil Modification 2 - Stage 5 Independent Planning Commission Applicant Presentation - Planning 28 October 2020

  2. Slide 2: Dunmore Sand & Soil: A brief overview of our project

    01 - Dunmore Sand & Soil A brief overview of our project

  3. Slide 3: Dunmore Sand & Soil: no change

    01 - Dunmore Sand & Soil ● NO CHANGE ● Extraction and works remain the same ● NO CHANGE ● Our consent is valid for 25 years ● NO CHANGE ● 800,000 tonnes per annum unchanged ● NO CHANGE ● Road and rail distribution remains the same ● NO CHANGE ● Use of the same excavators and dredge

  4. Slide 4: Key Facts

    01 - Dunmore Sand & Soil ● Stage 5 will allow existing facilities at the Dunmore Sand & Soil Tabbitta Road site to continue operating ● Existing infrastructure at Tabbitta Road will be used, removing Key Facts the need for additional disturbance within the Stage 5 areas. ● High level of environmenta

  5. Slide 5: The Constraints

    02 - The Constraints Factors which guided our framing of the project

  6. Slide 6: The Constraints

    02 - The Constraints « 2 e é 2 3 2 oS

  7. Slide 7: The Constraints

    02 - The Constraints dification 2 tland tland proximity

  8. Slide 8: The Constraints

    02 - The Constraints [Site boundary Coastal wetland ~ proximity area Proposed modification 2 (Stage 5) Surface water management Inflow/outflow spillway Flood protection bund

  9. Slide 9: Planning Considerations: Vegetation & Mitigation

    03 - Planning Considerations Vegetation & Mitigation

  10. Slide 10: Vegetation

    03 - Planning Considerations - Vegetation

  11. Slide 11: Vegetation

    03 - Planning Considerations - Vegetation Management Plans Inspections Weed Management Offset Credits Nest Boxes Rehabilitation Collectively Pre-clearing Ongoing Purchasing and Offsetting Effectively developed inspections management securing impacts implemented offsets Prepared in We will be conduct

  12. Slide 12: Planning Considerations: Flooding

    04 - Planning Considerations Flooding

  13. Slide 13: Flooding

    04 - Planning Considerations - Flooding

  14. Slide 14: Flooding

    04 - Planning Considerations - Flooding

  15. Slide 15: Flooding

    04 - Planning Considerations - Flooding

  16. Slide 16: Flooding

    04 - Planning Considerations - Flooding

  17. Slide 17: Planning Considerations: Groundwater

    05 - Planning Considerations Groundwater

  18. Slide 18: Groundwater

    05 - Planning Considerations - Groundwater

  19. Slide 19: Groundwater

    05 - Planning Considerations - Groundwater

  20. Slide 20: Planning Considerations: Cultural Heritage

    06 - Planning Considerations Cultural Heritage

  21. Slide 21: Cultural Heritage

    06 - Planning Considerations - Cultural Heritage

  22. Slide 22: Cultural Heritage

    06 - Planning Considerations - Cultural Heritage

  23. Slide 23: Planning Considerations: Traffic & Transport

    07 - Planning Considerations Traffic & Transport

  24. Slide 24: Traffic & Transport

    07 - Planning Considerations - Traffic & Transport

  25. Slide 25: Key Facts

    07 - Planning Considerations - Traffic & Transport ● Stage 5A will be the first area for extraction and rehabilitation activities. ● The land will be returned to its present state, with vegetation to be Key Facts established for grazing purposes ● Traffic impacts during rehabilitation activities only ● W

  26. Slide 26: Traffic & Transport

    07 - Planning Considerations - Traffic & Transport

  27. Slide 27: Traffic & Transport

    07 - Planning Considerations - Traffic & Transport

  28. Slide 28: Other Considerations: Issues raised by the community

    08 - Other Considerations Issues raised by the community

  29. Slide 29: Other Considerations

    08 - Other Considerations ● NO IMPACT ● The nest is 280m+ away from Stage 5B ● NO IMPACT ● Our proposal will not impact Council’s toxic plume ● NO EXTRACTION ● No impacts on the river or its associated ecosystems ● NO CHANGE ● Our project is completely isolated from the River ● COMMITTED TO GREAT OU

  30. Slide 30: Thank you.

    Build something great Thank you.

  31. Slide 31: Dunmore Sand & Soil Modification 2 - Stage 5: Business

    Dunmore Sand & Soil Modification 2 - Stage 5 Independent Planning Commission Applicant Presentation - Business 28 October 2020

  32. Slide 32: The Resource

    01 - The Resource How this sand resource could be utilised

  33. Slide 33: The Resource: Key Facts

    01 - The Resource The size of the sand deposit in this area is significant and extends all the way to the banks of the Minnamurra River The fine sand we’re seeking to extract is a small but essential Key Facts ingredient in the manufacture of concrete and asphalt Our stage 5 activities are focused on

  34. Slide 34: The Resource

    01 - The Resource

  35. Slide 35: Dredging Process

    02 - Dredging Process A brief explanation of our processes

  36. Slide 36: Dredging Process

    02 - Dredging Process BORAL Dredge operator lowers the boom to the pit floor A rotating cutter bar uses teeth to loosen settled material, as a suction pump removes sand Groundwater exposed and dredge floated Site is cleared and bunds are established The sand is transported via pipeline for final pro

  37. Slide 37: Dredging Process

    02 - Dredging Process Extraction Wash Recirculation Cyclone Drying Distribution Sand Water Mix The Mix is Water returns Water goes Dried overnight Road and Rail Arrives cleaned to ponds back to ponds for sale The resource is The screen and tub Water that is The remaining The sand which is Once dried

  38. Slide 38: Environmental Management

    03 - Environmental Management How we ensure minimal impacts to the environment

  39. Slide 39: Environmental Management

    03 - Environmental Management Water Rehabilitation and Fauna 04 Guides how we manage and monitor both groundwater and surface water to Plans that guide how we manage our riparian zones, landforms, water ensure we are not impacting these along channels, compensatory habitats and with erosion & sedime

  40. Slide 40: Audit, Monitor, Report

    03 - Environmental Management AUDIT Annual audits of all management plans to ensure best practice MONITOR Regular and real time monitoring of environmental parameters REPORT Transparent and accessible reporting to everyone

  41. Slide 41: Consultation

    04 - Consultation How we communicate with the community

  42. Slide 42: Consultation

    04 - Consultation Community Public Meetings Consultation Committee Regular meetings to discuss We’ve held numerous project site operations and upcoming specific briefings and Q&A projects and any concerns sessions Dunmore Sand and Soil is committed to continuing to be a responsible operator and an int

  43. Slide 43: Consultation

    04 - Consultation Shellharbour Council Staff Kiama Council Staff DPIE and IPC Site Tours Community Groups

  44. Slide 44: Rehabilitation

    05 - Rehabilitation Outcomes we’ve delivered over the years

  45. Slide 45: Rehabilitation

    05 - Rehabilitation

  46. Slide 46: Rehabilitation

    05 - Rehabilitation

  47. Slide 47: Questions

    BORAL 06 - Questions

  48. Slide 48: Thank you.

    Build something great Thank you.