  1. Slide 1: 3Q Presentation

    3Q Presentation 24 October 2025

  2. Slide 2: 3Q 2025 Highlights

    Bonheur ASA group of companies 3Q 2025 Highlights Renewable Energy Wind service Cruise Other Investments • EBITDA NOK 219 mill. (NOK 263 mill.) • EBITDA NOK 577 mill. (NOK 435 mill.) • EBITDA NOK 352 mill. (NOK 255 mill.) • EBITDA NOK -31 mill. (NOK -15 mill.) • Reduced generation, mainly due to dow

  3. Slide 3: Segment Analyses per 3Q 2025

    Bonheur ASA group of companies Segment Analyses per 3Q 2025 Revenues – 12 months rolling EBITDA – 12 months rolling 16 000 5 000 Cruise Renewable Energy Wind Service Other Renewable Energy Wind Service Other Cruise 14 000 4 000 12 000 10 000 3 000 8 000 2 000 6 000 4 000 1 000 2 000 0 0 * * -1 000 *

  4. Slide 4: Revenue and EBITDA per segment

    Bonheur ASA group of companies Revenue and EBITDA per segment NOK million Revenue 3Q25 3Q24 Variance Renewable Energy 477 529 -53 Wind Service 1 471 1 752 (281) Cruise 1 148 1 016 132 Other Investments 310 308 2 Total Revenue 3 406 3 606 (200) EBITDA 3Q25 3Q24 Variance Renewable Energy 219 263 (44)

  5. Slide 5: Consolidated summary 3Q 2025

    Bonheur ASA group of companies Consolidated summary 3Q 2025 NOK million 3Q25 3Q24 Variance Revenues 3 406 3 606 -200 Opex (2 289) (2 669) 379 EBITDA 1 117 938 179 Depreciation (299) (335) 36 EBIT 818 603 215 Results from associates (5) (5) (0) Net Finance (133) (161) 28 EBT 680 438 242 Tax Cost (119

  6. Slide 6: Group Capitalization per 3Q 2025

    Bonheur ASA group of companies Group Capitalization per 3Q 2025 NOK million Cash External debt*) Net cash/(debt) Financial Policy 100% owned entities Renewable Energy 338 0 338 The Company and its financial and liquidity Wind Service 973 297 675 position shall be strong Cruise 605 0 605 Bonheur ASA

  7. Slide 7: Sofie Olsen Jebsen, CEO

    Sofie Olsen Jebsen CEO 7

  8. Slide 8: 3Q Fred. Olsen Renewables

    3Q Fred. Olsen Renewables • Production in Q3 lower than same quarter 2024 ⎯ Crystal Rig I recovery project (early generation turbines) ⎯ Market reasons at Swedish windfarms: ancillary services, low prices, grid export limits as well as blade issues • Lower revenues due to lower REGO prices • Constru

  9. Slide 9: Full Cycle Business Model

    Full Cycle Business Model Site investigation Development Consented Construction Operation UK UK 900 MW UK UK Scotland Norway Portfolio Paul’s Hill II 21 MW Crystal Rig IV 49.1 MW Crystal Rig 62.5 MW Fetteresso 42 MW Windy Standard III 87,6 MW Crystal Rig II 138.0 MW Sweden Norway 1150 MW Rothes III

  10. Slide 10: Market Backdrop

    Market Backdrop Power prices (quarterly average) European power prices held steady in Q3, 400 400 supported by weak demand, strong renewable output, and subdued fuel costs. 350 350 • Nordic prices remained low, while UK prices edged higher but stayed well below early-year levels. 300 300 • Gas price

  11. Slide 11: Production

    Production • Generation below estimates ⎯ Crystal Rig I recovery project with early generation turbines increases availability ⎯ Lower production at Högaliden and Fäboliden mainly due to market (ancillary services and low prices), grid export limits and blade issues • Grid outages ⎯ Planned grid mai

  12. Slide 12: Crystal Rig IV

    Under construction Crystal Rig IV Project information • Good progress - 5 turbines installed • Delayed transport of components postponed 11 49.1 MW installation start Wind turbines Windfarm capacity ⎯ Due to low capacity on police escort. Mitigating actions taken GBP 81 mill. 200m / 150m Total inves

  13. Slide 13: Windy Standard III

    Under construction Windy Standard III Project information • Project progressing well 20 87,6 MW Wind turbines Windfarm capacity • Two wind turbine foundations successfully poured • Civil work progressing according to plan GBP 133 mill. 180m/125m Total investment estimate Two clusters with different

  14. Slide 14: Lars Bender, Fred. Olsen Seawind

    KX¢ Fred. Olsen Seawind Lars Bender CEO

  15. Slide 15: Q3 highlights

    Q3 highlights • Good projects in attractive markets • Diligent development strategies • Request for information (RFI) received for Codling postponing expected consent determination • Landfall and onshore substation land areas secured for Muir Mhòr 15

  16. Slide 16: Summary - Status and update

    Summary - Status and update CODLING WIND PARK MUIR MHÒR Large Scale Bottom Fixed Project in Ireland 1000 MW Floating Project in Scotland • Codling Wind Park a 50/50 Joint venture with EdF. • 50/50 Joint Venture with Vattenfall • Codling Wind Park has secured site exclusivity, grid access • Muir Mhòr

  17. Slide 17: Codling Wind Park

    Status and Update Codling Wind Park Dublin Greystone Wicklow • Consent application process ongoing and followed closely. • Codling Wind Park have received a RFI from the Irish government, postponing the expected consent determination. • Irish Government remains committed to offshore wind buildout. C

  18. Slide 18: Muir Mhòr Project

    Status and Update Muir Mhòr Project • Land option agreements signed for both landfall and onshore substation area north of Peterhead Peterhead • Onshore consent awarded – offshore consent progressing • Following final consent award for offshore, the project will be in position for bidding into CfD a

  19. Slide 19: Per Arvid Holth, Fred. Olsen 1848

    IX Fred. Olsen 1848 LLL Per Arvid Holth CEO

  20. Slide 20: Status and Update

    Status and Update FLOATING SOLAR • IEA 2025 ⎯ Electricity produced ⎯ Installed capacity • Floating solar PV reflections 20

  21. Slide 21: Solar power becoming largest renewable energy source

    IEA projection Solar power becoming largest renewable energy source Installed capacity Generated electricity IEA (2025), Renewables 2025, IEA, Paris https://www.iea.org/reports/renewables-2025, IEA (2025), Renewables 2025, IEA, Paris https://www.iea.org/reports/renewables-2025, 21 Licence: CC BY 4.0

  22. Slide 22: Solar PV showing high availability

    Solar PV Solar PV showing high availability ▪ Unlike other renewable energy sources, overcapacity in supply chain. ▪ This has resulted in PV price reduction of 60% since 2023, currently down to USD 0.09/Wp. IEA (2025), Renewables 2025, IEA, Paris https://www.iea.org/reports/renewables-2025, 22 Licen

  23. Slide 23: Wide range of opportunities

    The Floating PV Power Production System BRIZO Wide range of opportunities PV-Utility • Utility scale in suitable markets • Hybrid solution with hydro PV-Distributed Project information • Displacement of hydrocarbons in island communities. Robust Design Versatile application Designed to resist to win

  24. Slide 24: Samantha Stimpson, Fred. Olsen Cruise Lines

    IX Fred.Olsen Cruise Lines Samantha Stimpson CEO

  25. Slide 25: 3Q Highlights

    3Q Highlights Revenue growth by improved utilization and yield Improved customer satisfaction Cost control results in EBITDA growth Good future booking performance 25

  26. Slide 26: Quarterly performance 3Q 2025 vs. 3Q 2024

    Quarterly performance 3Q 2025 vs. 3Q 2024 • Passenger numbers +19% • Yield per passenger per day +13% • Utilization of 81% (77%) • EBITDA of NOK 352 mill (NOK 255 mill) • Net Promoter Score increased to 68 from 63 +5 point • Cumulative sales for 2025, 2026 and 2027 departures +12% 26

  27. Slide 27: Status and Update

    Status and Update BOREALIS BOLETTE BALMORAL • Cruises this Quarter: 9 • Cruises this Quarter: 9 • Cruises this Quarter: 12 Azores & Madeira x 2, British Isles, Norway x 2, Scottish Isles x 2, France & Norway x 4, French Rivers x 2, UK short Iceland, Spain, Amalfi Coast and Norway Britain coastline,

  28. Slide 28: Haakon Magne Ore, Fred. Olsen Windcarrier

    KX Fred. Olsen Windcarrier Haakon Magne Ore CEO

  29. Slide 29: 3Q highlights

    3Q highlights Good performance Two new T&I contracts signed Volatility on demand side persist 29

  30. Slide 30: Status and Update

    Status and Update BOLD TERN BRAVE TERN BLUE TERN BLUE WIND • Commenced work offshore • In yard to prepare generic 3 • O&M campaign with SGRE • Completed the Hai Long under the Saipem monopile turbine seafastning and carry throughout the quarter. project drilling campaign over work from Navantia Comm

  31. Slide 31: Quarterly Financials

    Quarterly Financials Impacted by Yard activity • Good operational and financial performance • High activity but one vessel in yard for full quarter ⎯ 67% contractual utilization Revenue & EBITDA (EUR million) ⎯ 99% commercial utilization 400 300 EUR million • Quarterly revenue of EUR 60,3 million an

  32. Slide 32: Backlog Development

    Backlog Development • Backlog FOWIC vessels is EUR 360 million (2Q 2025: EUR 357 million) ⎯ Excluding vessel reservation agreements • Signed two new turbine T&I contracts during the quarter ⎯ Vessel reservation agreement to install 63 15MW turbines at the Gennaker project in 2028 ⎯ Firm contract for

  33. Slide 33: Q&A

    KX Bonheur ASA Q&A