  1. Slide 1: Fueling the Future: Alta Mesa Acquisition, South Texas

    Fueling the Future: Alta Mesa Acquisition, South Texas January 2023 TSX.V: EU | OTCQB: ENCUF | encoreuranium.com

  2. Slide 2: Disclaimer

    Disclaimer ©2022 enCore Energy Corp., All rights reserved. Unless otherwise noted, “enCore” and all other marks used in this presentation are trademarks of enCore Energy (the “Company”). Any reproduction or dissemination of any feature of this presentation, in whole or in part, or any use of this pr

  3. Slide 3: enCore Energy: Fueling the Future

    enCore Energy: Fueling the Future Reliable, responsible domestic uranium production in 2023 South Texas Focus: Rosita, Advanced Assets: US In-Situ Recovery: Uranium Kingsville Dome, and Alta Production Pipeline Extraction process with proven Mesa facilities 93.4 Mlbs in the M&I category, 25.8 econom

  4. Slide 4: enCore Energy: Fueling the Future

    Uranium Spot Price enCore Energy: 150 FUELING THE FUTURE 100 URANIUM Fully funded uranium production strategy to provide clean, reliable 50 and carbon-free domestic energy 0 enCore’s Goal: 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 To become a 5 million pounds U3O8 producer in 5 years En

  5. Slide 5: enCore corporate summary

    enCore corporate As at January 4, 2023 Market Capitalization (@$3.10) $337,956,345 CDN summary Shares Issued & Outstanding Warrants 109,018,176 8,760,122 Outstanding Subscription Receipts: 23,277,000** **Issued on December 6, 2022 for $3.00/Subscription Receipt. Subject to certain Options 7,153,176

  6. Slide 6: We have a strong board and management

    We have a strong board and management TSX.V: EU | OTCQB: ENCUF 6

  7. Slide 7: Board of directors

    Board of directors William M. Sheriff, MSc Richard M. Cherry, MSc, P.E. Executive Chairman Independent Director Mr. Sheriff was a pioneer in the uranium renaissance as Mr. Cherry is a veteran executive with over 40-years of experience in the co-founder and Chairman of Energy Metals Corp., which nucl

  8. Slide 8: enCore: post transaction production pipeline

    enCore: post transaction production pipeline GOAL : 3 million pounds U3O8/year production by Year 3; 5 million U3O8 pound/year producer in Year 5 8

  9. Slide 9: In-Situ Recovery (ISR): environmentally superior & economically competitive

    In-Situ Recovery (ISR): environmentally superior & economically competitive ISR uses injection wells which add oxygen and carbon dioxide 1 creating a lixiviant solution; uranium dissolves into the solution Recovery wells pump the solution back to the surface to a processing facility 2 Monitoring wel

  10. Slide 10: South Texas production highlights

    South Texas production highlights 3 Fully licensed, constructed 3.6 million pounds U3O8 per and 100% owned production year combined capacity facilities: Rosita, Kingsville Dome, Alta Mesa Production targeted for 2023 with Production expansion potential satellite feed to the Rosita Central with minim

  11. Slide 11: Executing the strategy

    Relocating the filter press to Rosita Executing the strategy Below: Opening an elution column at Rosita Investor Tour at Rosita Rosita Plant Completion Left: William M. Sheriff, Executive Chairman TSX.V: EU | OTCQB: ENCUF 11

  12. Slide 12: Alta Mesa Project: Transaction Pending Close

    Alta Mesa Project: Transaction Pending Close US$120M total consideration, payable as:  US$60M in cash  Cash consideration funded via existing treasury + concurrent  US$60M in a secured vendor convertible promissory note with EFR financing  Closing of the transaction expected in [late Q4 2022] En

  13. Slide 13: Alta Mesa Production History

    Alta Mesa Production History Among largest US ISR mines, operating until uranium prices depressed post-Fukushima 21st Century US ISR Production 24 22.0 22 20 Historic Production (Mlbs U3O8) 18 16 14 12 11.1 10 8 6 4.6 4 2.9 2.8 2 1.3 0.7 0.6 0.4 0 Smith Ranch Crow Butte Alta Mesa Lost Creek Willow C

  14. Slide 14: Acquisition of Alta Mesa

    Acquisition of Alta Mesa: enCore positioned to become the leading company focused on US domestic uranium production  Fully licensed past-producing In-Situ Recovery (ISR) uranium plant & existing resource located 80 miles from the Rosita plant and 75 miles from the Kingsville Dome plant presently ow

  15. Slide 15: The Opportunity: Alta Mesa Asset Acquisition

    The Opportunity: Alta Mesa Asset Acquisition In addition to a fully licensed past-producing ISR uranium operation:  US$150M+ historically spent by Mesteña Uranium LLC and Energy Fuels  ~5 million pounds of past production  Radioactive Materials License with the Texas Commission on Environmental Q

  16. Slide 16: History: Alta Mesa Project

    History: Alta Mesa Project Exploration & Production  2006 – construction and commercial start  Expanded in 2008 – increased production capacity to 2 million pounds per year: • Developed a commercial molybdenum recovery circuit. (patent pending) • Increased ion exchange to 1.5 million pounds/yr and

  17. Slide 17: Phase 1: Texas uranium near-term production

    Phase 1: Texas uranium near-term production Three project areas with central plant and satellite feed:  Rosita Central Processing Plant: Modernization Complete with planned production 2023  Upper Spring Creek provides significant feed for Rosita later in 2024  Alta Mesa Processing facility: Produ

  18. Slide 18: Phase 2: Dewey-Burdock project

    South Dakota Phase 2: Dewey-Burdock project Edgemont uranium district in southwest South Dakota, approximately 60 miles from Cameco’s Crow Butte mine in Nebraska Mineral rights and surface rights covering approximately 16,960 acres and 12,610 acres, respectively Well served by infrastructure: Sixtee

  19. Slide 19: Robust project economics

    Dewey-Burdock, South Dakota Robust project economics 16 years 2019 PRELIMINARY ECONOMICS ASSESSMENT Mine Life (incl. 2 year ramp-up)  Initial capital costs of US$31.7m Annual Production 1.0 Mlbs/yr is ‘sector leading’ for a project of this size LOM Production 14.3 Mlbs  Pre-tax IRR of 55% at US$55

  20. Slide 20: Phase 3: Gas Hills project

    Wyoming Phase 3: Gas Hills project NI 43-101 COMPLIANT ISR URANIUM DEVELOPMENT IN RESOURCE A HISTORIC DISTRICT Located in Fremont and Natrona Counties, WY Estimated Measured and  Wyoming has long history of successful Indicated U3O8 mineral ISR operations and is an Agreement resource: 7,705,610 lbs

  21. Slide 21: Gas Hills ISR project

    Wyoming Gas Hills Mine Life 7 years ISR project Annual Production 1.0 Mlbs/yr LOM Production 6.5 Mlbs 2021 PRELIMINARY ECONOMIC ASSSSMENT RESULTS Initial Capital Costs US$26.0M (US$3.99/lb) Potential satellite project to Dewey Burdock ISR Project Cash Operating Costs US$11.52/lb - Plant and well fie

  22. Slide 22: Phase 4: Dominant land position in New Mexico

    New Mexico Phase 4: Dominant land position in New Mexico MOST PROPERTIES IDENTIFIED AS AMENABLE TO ISR, CONSISTENT WITH ENCORE’S ‘ISR FIRST’ STRATEGY New Mexico’s Grants Uranium District Over 400 million pounds of has produced ~350 million pounds unmined mineralization has been U3O8, or nearly 40% o

  23. Slide 23: Crownpoint and Hosta Butte project

    A view of Laramide’s processing facility site on Section 24 New Mexico Crownpoint and Hosta Butte project A large ISR-amenable project that hosts an estimated 26.6 million pounds Indicated mineral resource (12.68Mt at 0.105% eU3O8) and 6.1 million pounds Inferred mineral Crownpoint and Hosta Butte C

  24. Slide 24: enCore Energy: investment summary

    enCore Energy: investment summary Phased Expansion Clean, Reliable Energy Path to Production 3.6 million pounds/yr Funded to planned 2023 Favorable conditions for production potential with production; high grade ISR domestic uranium market ability to increase capacity; resources to fuel the future w

  25. Slide 25: Other assets

    NI 43-101 mineral resources Other assets Marquez-Juan Tafoya Project, New Mexico2 Project Million Tons Grade eU3O8% Attributable U3O8 (M lbs.*) Indicated mineral resource (Minimum GxT = 0.60) 7.10 0.127 18.10 Juniper Ridge Project, Wyoming13 Project Million Tons Grade eU3O8% Attributable U3O8 (M lbs

  26. Slide 26: Other assets

    Other assets  Investing in new technology: Significant ownership (34%) in Group 11 Technologies, working to revolutionize environmentally-friendly mineral extraction of other metals by combining two proven technologies; in-situ recovery with environmentally-friendly solvents;  Exclusive access to

  27. Slide 27: Addressing Uranium & Critical Metals Demand

    Addressing Uranium & Critical Metals Demand www.nuclearfuels.energy 27 27

  28. Slide 28: Global uranium & nuclear environment

    Global uranium & nuclear environment Uranium supply in a ~200 nuclear reactors under construction or planned – net deficit position an increase of more than 40% of current operating nuclear fleet.1 “Global realignment away from Russia in the nuclear fuel supply chain…new emphasis on western, and in

  29. Slide 29: US uranium sector renaissance

    US uranium sector renaissance Bi-Partisan Support Domestic Supply Needed Department of Energy Nuclear Fuel • Bi-partisan Infrastructure Law 1: 60% of US uranium flows through Russia Strategic Uranium Reserve 2020 Energy Act: funding 3 and is “no longer a trustworthy source of Small Modular Reactors

  30. Slide 30: Global uranium supply

    Global uranium supply Uranium Production U.S. uranium supply to commercial nuclear reators (1950-2017) By Country (2019) Million pounds U3O8 Kazakhastan, 6.1% Canada, and 5.3% 7.3M 80 Australia produce 6.4M Nearly 70% of the 5.6% 70 world’s uranium. 6.7M 60 Kazakhstan 6.5% 42.1% 42.1% 7.7M 50 Canada

  31. Slide 31: Windmills vs nuclear energy

    Windmills vs nuclear energy TSX.V: EU | OTCQB: ENCUF 31

  32. Slide 32: 1 nuclear energy plant vs wind power

    1 nuclear energy plant vs wind power TSX.V: EU | OTCQB: ENCUF 32

  33. Slide 33: Safe nuclear power

    Safe nuclear power Comparative death rates per unit of electricity production Based on deaths from accidents and air pollution per terawatt-hour (TWh) of electricity. TSX.V: EU | OTCQB: ENCUF 33

  34. Slide 34: enCore Energy in the nuclear fuel cycle

    enCore Energy in the nuclear fuel cycle TSX.V: EU | OTCQB: ENCUF 34

  35. Slide 35: In-situ Recovery and Central Processing Plant

    In-situ Recovery and Central Processing Plant 35

  36. Slide 36: Advancing to become the next leading producer of American Uranium.

    Advancing to become the next leading producer of American Uranium. TSX.V: EU | OTCQB: ENCUF encoreuranium.com info@encoreuranium.com enCore Board and Management at Rosita Processing Plant 778.383.6746 TSX.V: EU | OTCQB: ENCUF 36

  37. Slide 37: References

    enCore Energy References 1. NI-43-101 Technical Report, Crownpoint and Hosta Bute 9. Behre Dolbear & Company (USA) Inc., 2011, Technical Report P. (Terry) McNulty. P.E, D.Sc., T.P McNulty and Associates Uranium Project, McKinley County, New Mexico, USA on the West Largo Project of Uranium Resources