Slide 1: Stakeholder Consultation Meeting
Stakeholder Consultation Meeting Oakdale West Estate July 2020 1
Slide 2: Overview
Overview Welcome and Introductions Project Update – OWE – Burton Contractors Project Update – WNSLR – Robson Contractors Project Update – Project Waratah - Qanstruct Environmental Performance Safety Update Consultation and Community Interactions Stakeholder Feedback & Questions 2
Slide 3: Welcome and Introductions
Welcome and Introductions Project Team: Organisation Goodman AT&L SLR Consulting Ersed Role Proponent Project Manager & Contract Stakeholder Engagement Environmental Superintendent Representative Key Contacts Stephanie Partridge Alex Lohrisch Dan Thompson Carl Vincent Kym Dracopoulos Dane Segail Kat
Slide 4: Project Progress To Date - OWE
Project Progress To Date - OWE • Precinct 1 Earthworks – 85% completed. • Precinct 2 Earthworks – 85% completed. • Precinct 3 Earthworks – 90% completed. • Precinct 4 Earthworks – 20% completed. • Sewer Works – 75% completed. • Stormwater – Commenced on Road 1. • Retaining wall construction – ongoin
Slide 5: July/August Project Program – OWE
July/August Project Program – OWE • Complete bio basin 2/3. • Continue with earthworks to all Precincts. • Trim pads as lots are completed. • Continue with sewer works. • Continue with retaining wall works. • Continue stormwater works. • Commence transmission works. 5
Slide 6: Project Progress To Date - WNSLR
Project Progress To Date - WNSLR North: Bridge: • Stormwater and underground services • Bridge piling installation north of Chainage 400 • Bulk earthworks and gravel placement for • Bulk earthworks north of Chainage 600 internal access road South: • Bio-basin bulk earthworks 6
Slide 7: July/August Project Program – WNSLR
July/August Project Program – WNSLR North: South: • Complete Lenore Drive intersection works • Complete services and stormwater installation • Complete pavement construction works to connect Lockwood Road • Complete bio-basin construction to Lenore Drive • Commence retaining wall construction • Comp
Slide 8: Project Progress To Date – Project Waratah
Project Progress To Date – Project Waratah Site activities to date: • Detailed earthworks ongoing • Footings to main structure 30% complete • Main Warehouse steel pre- assembly stage 1 part complete • Shear stud welding approx. 15% complete to primary members • Structural steel erection to commence
Slide 9: July/August Project Program – Project Waratah
July/August Project Program – Project Waratah Forecasted Activities: • Complete hardstand stormwater • Start in-ground hydraulics • Start external grated drain to hardstand • Sewer rough in to B5-B6 • Start perimeter fence • Start retaining wall 1 • Erect steel - grids F to N, 1 to 5 • Footings - gr
Slide 10: ER Inspections and Audits: SSD7348
ER INSPECTIONS AND AUDITS: SSD7348 ER INSPECTIONS 2019 TOTAL 3 2020 QTR1 (JAN-MARCH) 16 2020 QTR 2(APRIL-JUNE) 10 JULY (PART) 2 TOTAL TO DATE 31 ER AUDITS THIS PERIOD JUNE 18 • OWE (INFRASTUCTURE) CTMP • WNSLR MATERIAL HANDLING FIP & WMP Copyright © ErSed 2011
Slide 11: Environmental Performance: SSD7348
ENVIRONMENTAL PERFORMANCE: SSD7348 NON COMPLIANCES, NON COMPLIANCE # 002 18/06/20 : CONDITION D37 THE APPLICANT MUST COMPLETE THE LANDSCAPE BUND ALONG THE WESTERN BOUNDARY OF THE SITE AS SHOWN ON FIGURE 4 IN APPENDIX 2 WITHIN SIX MONTHS OF COMMENCING ANY CONSTRUCTION INCLUDING BULK EARTHWORKS. • THE
Slide 12: ER Inspections and Audits- Waratah
ER INSPECTIONS AND AUDITS- WARATAH INSPECTIONS AUDITS THIS PERIOD 2 JULY 20 WARATAH SITE MEETING 4 JUNE 20 INTIAL SITE MEETING TO GO THROUGH CEMP AND INSPECTION /REPORTING OBJECTIVES Copyright © ErSed 2011
Slide 13: Environmental Performance- Waratah
ENVIRONMENTAL PERFORMANCE- WARATAH INCIDENTS AND COMPLAINTS AS DETAILED IN THE MONTLY REPORTS INCIDENTS JUNE 20 NIL JULY 20 – PART NIL NON COMPLIANCE 10 –JUNE 20 B13. THE APPLICANT MUST ENSURE: (B) CONSTRUCTION TRAFFIC DOES NOT USE BAKERS LANE DURING THE HOURS OF 8 AM – 9.30 AM AND 2.30 PM – 4 PM, M
Slide 14: Safety
Safety • No external safety incidents • Minor internal safety incidents – No injuries 14
Slide 15: Consultation and Community Interactions
Consultation and Community Interactions • Resident of Aldington Road – Enquiry to PCC regarding safety of Aldington Road • Emmaus Village Managers on behalf of Resident – Enquiry regarding removal date/timing of temporary acoustic fencing • Emmaus College – Incident involving truck accessing disused
Slide 16: Communications and Consultation Channels
Communications and Consultation Channels Sources of information and complaints/enquiries via: • Website: oakdaleopportunities.com • Email: community.oakdalewest@goodman.com • Phone: 1300 002 887 • Post: Level 17, 60 Castlereagh Street, Sydney, NSW 2000 • Community Meetings: Subject to scheduling • E
Slide 17: Stakeholder Feedback & Questions
Stakeholder Feedback & Questions 17