Slide 1: Construction Update
Construction Update September 2016 (US$ in Millions, Unless Otherwise Indicated) Lydianinternational.co.uk | TSX:LYD 1
Slide 2: Cautionary Statements
Cautionary Statements Forward Looking Information & Estimates of Reserves and Resources Certain information contained in this presentation, including any information relating to Amulsar's expected future performance, is "forward looking". All statements in this presentation, other than statements of
Slide 3: Amulsar Gold Project – Armenia
Amulsar Gold Project – Armenia Compelling Asset Generating Value Through Construction • 100%-owned, emerging as a leading gold development project • Large scale operation to be Armenia’s largest gold mine • Low cost production profile benefiting from: • Conventional mining and processing • Low waste
Slide 4: Amulsar Gold Project – Location
Amulsar Gold Project – Location Exceptional Access & Regional Infrastructure • 170 km southeast of Yerevan • Located on Armenia’s primary infrastructure corridor • Paved access to site Georgia • Local workforce • High-voltage power on site • Internet connection in place Azerbaijan • Water on site fo
Slide 5: Large Scale Oxide Deposit
Large Scale Oxide Deposit Initial 10-Year Mine Plan from 2.4 Million Oz P+P Reserves • Pit design optimized at $912/oz gold; economic evaluation at $1,150/oz gold • Excellent operating profile • Waste : Ore ratio at 2.4 – including 26 million tonnes of inferred classified as waste • Life-of-mine gol
Slide 6: Amulsar Feasibility Study
Amulsar Feasibility Study Initial Capital Optimized at $369.9 Million • Capital efficiencies achieved • Site layout for constructability and operability • Crushing plant – supported by column leach tests and blast fragmentation study • Mine fleet aligned with ramp-up US$ in Millions and stage of ope
Slide 7: Amulsar Feasibility Study
Amulsar Feasibility Study Amulsar Mine Profile and Economics Q4 2015 Operating Profile NI 43-101 Initial Mine Life (Years) 10.0 Annual Tonnes Processed 9,700,000 Waste : Ore Ratio 2.4 Gold Grade (g/t) 0.78 Gold Recovery 87.2% Annual Gold Produced (oz) 211,000 All-in Sustaining Costs ($/oz) $585 Econ
Slide 8: Growth Potential
Growth Potential Upside within Inferred Resource and at Depth • Resource Conversion • Within current pits: 26 million tonnes at 0.57 g/t inferred. • Optimizing to include inferred adds: 40 million tonnes at 0.73 g/t. Mostly limited by drilling density • Open potential below pit limits (below East-We
Slide 9: Project Financing
Project Financing Flexible Financing Plan Nearing $440 Million Equity • RCF / Orion: $ 80 million • Public Offering: $ 29 million • EBRD: $ 10 million Term Loan & COF • Orion / RCF $160 million US$ in Millions • Libor + 6.5%; 5.5 year term • COF @ Libor + 9.5% Equipment Leasing, $75 Equity, $119
Slide 10: Mining, Access & Construction Rights
Mining, Access & Construction Rights Strong Support for Amulsar Development at All Levels National Level rights fully approved • Mining Right through the Ministry of Energy & Natural Resources • Environmental Impact Assessment through the Ministry of Nature Protection • Technical Safety Program th
Slide 11: Amulsar Project Design & Engineering
Amulsar Project Design & Engineering Key Engineering Underway; Leveraging 2015 Value Engineering Heap Leach Facility • Most advanced from Value Engineering (Samuel) • Detailed engineering +80% complete Material Handling Systems • Vendor engineering reducing timelines (Sandvik) • Basic engineering by
Slide 12: Organizational Development
Organizational Development Rapidly Building Core Competencies for Construction • Construction engineering Construction • Project controls • Construction management • Health & safety Sustainability • Environmental compliance & monitoring • Community relations • Human resources Project Support • Procu
Slide 13: Drilling: 2016 Program
Drilling: 2016 Program Multiple Objectives Supporting Mine Development & Upside • Infill Drilling: Convert inferred to indicated, bring down Tigranes/Artavasdes wall • Grade Control: 20 metre centers for early mine planning • Geotechnical: Confirmatory in key construction footprints Measured Indicat
Slide 14: Mining Fleet
Mining Fleet Vendor Selected & Orders to Start in Q4 2016 • Trade-off study completed, with CAT selected • Cost & lead-times within project budget & schedule • Coordinating equipment purchases with CAT financing Initial Sustaining Primary Components Capex Capex New Purchases: CAT 6040 Shovel 1 1 CAT
Slide 15: Early Works
Early Works Clearing Path for Construction Start • Pipeline diversion from HLF footprint • Repair community water channel • Construction accommodations • Hotel renovation for accommodations, commissary and Jermuk offices • Preparing for temporary camp platform and utilities • On-site offices platfor
Slide 16: Sustainability
Sustainability Cornerstone of Our Construction & Operating Philosophy • Amended Environmental Impact Assessment • Aligns to 2015 feasibility study • All public hearings completed, and approval received in May 2016 • Environmental and social frameworks • ESIA amended; held for public consultation; an
Slide 17: Comparable Development Stage Companies
Comparable Development Stage Companies Targeting to Re-Rate Central to Construction Strategy Market Cap C$ (millions) $250 $414 $2,653 $792 $519 $2,017 P/NAV 0.5x 0.6x 0.9x 0.9x 0.9x 1.1x Volta Asset Name Amulsar Brucejack Hardrock Yaramoko Morelos Grande Asset Location Armenia Brazil B.C. Ontario B
Slide 18: The Value Proposition
The Value Proposition 2016/2017 Transformational Years Path forward for construction to becoming a mid-tier gold producer Financed to execute on the construction strategy Strong government and community support Low all-in sustaining costs Robust mining project with upside potential 18
Slide 19: Thank You
Thank You 19 Lydianinternational.co.uk | TSX:LYD
Slide 20: Lydian International Corporate Summary
Lydian International Corporate Summary • Ordinary Shares: LYD Trading Symbols • Publicly-trading Warrants LYD.WT • Ordinary Shares 699 million Share Capital • Publicly-trading Warrants 99 million • Unlisted Warrants 5 million Market Capitalization • Recent price of C$0.50 C$349 million • Sourced fro
Slide 21: Board of Directors
Board of Directors Development Oriented – Independent, Diverse Experience Gordon Wylie • 32 yrs mining experience • AngloGold-Ashanti Global (Non-executive director & Chair) • Exploration manager Howard Stevenson • 25 yrs global mining experience • Alacer Gold President & COO (President & CEO) • Mer
Slide 22: Mineral Reserves & Mineral Resources
Mineral Reserves & Mineral Resources Notes Notes to Mineral Reserves: 1. The pit design was based on an optimization shell generated on gold only at a gold price of $912/oz. 2. The economic evaluations were based on a gold price of $1,150/oz and a silver price of $16.00/oz. 3. A diluted gold cut-off
Slide 23: Presentation Notes
Presentation Notes LYDIAN