Diatreme Resources Limited · ASX:DRX

Diatreme Resources — Investor Presentation (October 2010)

30 slides from Diatreme Resources's investor presentation, Oct 13, 2010

  1. Slide 1: Broker Presentation Announcement

    Slide 1: Broker Presentation Announcement

    DIATREME RESOURCES LIMITED ABN: 33 061 267 061 Postal Address: P.O Box 10288 Brisbane Adelaide Street QLD 4000 Registered Office: Level 2 87 Wickham Terrace Spring Hill QLD 4000 PH: +61 (0)7 3832 5666 FX: +61 (0)7 3832 5300 www.diatreme.com.au manager@diatreme.com.au ASX : DRX 13 October 2010 Compan

  2. Slide 2: An Emerging Mine at Cyclone Deposit, Eucla Basin

    Slide 2: An Emerging Mine at Cyclone Deposit, Eucla Basin

    DIATREME RESOURCES LIMITED aN EMERGING MINE AT CYCLONE DEPOSIT EUCLA BASIN Presentation by: Se Gag TONY FAWDON ABN 33 061 267 061

  3. Slide 3: Disclaimer

    Slide 3: Disclaimer

    DISCLAIMER This presentation contains certain forward‐looking statements and forecasts which include without limitation, expectations regarding future performance, exploration, mineral resources, the financial position of Diatreme Resources Limited (the “Company”), industry growth or other trend pro

  4. Slide 4: Heavy Mineral Sands

    Slide 4: Heavy Mineral Sands

    HEAVY MINERAL SANDS Titaniferous Minerals Rutile, Ilmenite and Leucoxene are sources of titanium dioxide (TiO2) for the pigment industry , (used in most paints, plastics and papers as opacifiers), and for the production of titanium metal and welding electrodes. Zircon Zircon is a key raw mineral use

  5. Slide 5: Profile World Zircon

    Slide 5: Profile World Zircon

    DIATREME RESOURCES LIMITED PROFLE WORLD.ZIRCON “World Consumption 1,300,000 Tonnes Zircon * World Production Dominated by 3 Players * China 90% Dependent on Imports ¢ China importing 520,000 Tonnes Zircon Per Year ¢ Short Fall in Production, Increasing Demand ¢ Rerating of Industry as Product Prices

  6. Slide 6: Profile World Zircon & Rutile

    Slide 6: Profile World Zircon & Rutile

    DIATREME RESOURCES LIMITED PROFLE WORLD ZIRCON& RUTILE * World Shortage of Zircon and Rutile ¢ Dramatic Increases in Zircon & Rutile Over next 10 Yrs ¢ Main Supply of Zircon will come from Eucla Basin ¢ Short Fall in Production 2015 Onwards 400,000 tpa ¢ Short term Prices for Zircon to US$1,200 /ton

  7. Slide 7: Zircon & Titanium Production Locations

    Slide 7: Zircon & Titanium Production Locations

    ZIRCON & TITANIUM PRODUCTION LOCATIONS Zircon & Titanium global market >$3 billion annually Ukraine Atlantic coast of USA-Canada China Sierra Leone India-Sri Lanka Madagascar Atlantic coast of Brazil Australia South Africa The Eucla Basin Largely untested vast potential

  8. Slide 8: 2005–2010 Global Zircon Supply & Demand

    Slide 8: 2005–2010 Global Zircon Supply & Demand

    2005 – 2010 GLOBAL ZIRCON SUPPLY & DEMAND 2005年-2010年 全球供应与需求 ƒ A tight market through to 2008 resulted in escalating zircon prices ƒ 由于2008年市场短缺导致锆英砂价格逐步上升 ƒ Decline in production from major producers and Indonesia resulted in the zircon market falling into short supply through the course of 2008 ƒ

  9. Slide 9: Supply & Underlying Demand Estimate 1980-2020f

    Slide 9: Supply & Underlying Demand Estimate 1980-2020f

    SUPPLY & UNDERLYING DEMAND ESTIMAGE: 1980-2020f 供应与潜在需求情况:1980-2020预测 g a sin re i nc d m an De Supply Decreasing

  10. Slide 10: Zircon Price Forecast US$/Tonne FOB 2000–2015

    Slide 10: Zircon Price Forecast US$/Tonne FOB 2000–2015

    ZIRCON PRICE FORCAST US$/TONNE FOB: 2000 – 2015 锆砂价格预测 FOB 美元/吨:2000-2015

  11. Slide 11: Australia Project Locations

    Slide 11: Australia Project Locations

    AUSTRALIA PROJECT LOCATIONS

  12. Slide 12: DRX Profile

    Slide 12: DRX Profile

    DIATREME RESOURCES LIMITED DRX PROFILE — -Adyvanced project in Mineral Sands — Cyclone Deposit - Extensive tenement package throughout Australia - Base metal projects in Queensland and South Australia ¢ Chinese & Australian long term Shareholder support * Highly experienced and professional manageme

  13. Slide 13: Cyclone Deposit

    Slide 13: Cyclone Deposit

    DIATREME RESOURCES LIMITED CYCLONE DEPOSIT, Cyclone Deposit 132 million tonnes @ 2.3% heavy minerals (1% HM cut-off grade) containing 3.1 Mt heavy mineral, JORC classified as: Measured 50 Mt at 2.7% HM Indicated 72 Mt at 2.2% HM Inferred 10 Mt at 1.7% HM TOTAL 132 Mt at 2.3% HM Mineral Assemblage of

  14. Slide 14: World Mineral Sand Deposits

    Slide 14: World Mineral Sand Deposits

    WORLD MINERAL SAND DEPOSITS Cyclone Deposit – High Grade Zircon

  15. Slide 15: Cyclone Project Timeline

    Slide 15: Cyclone Project Timeline

    CYCLONE PROJECT TIMELINE Completed Completed Commenced

  16. Slide 16: Project Potential

    Slide 16: Project Potential

    DIATREME RESOURCES LIMITED PROJECT POTENTIAL - Cyclone»Resource: 132 million tonnes @ 2.3% heavy minerals (1% HM cut-off grade) containing 3.1 Mt heavy mineral. * Mineralised overburden being assessed. * $50 Million per annum annual gross profit for initial 10 year minelife. *Potential to increase r

  17. Slide 17: Mineral Sands Projects

    Slide 17: Mineral Sands Projects

    DIATREME RESOURCES LIMITED MINERAL SANDS PROJ.EGTS I!

  18. Slide 18: Eucla Basin - Terrain

    Slide 18: Eucla Basin - Terrain

    4 DIATREME RESOURCES LIMITED EUCLA BASIN -TE Base Line Track — Cyclone Deposit Arckaringa — Old Seismic track View on the Ground Spinifex Scrubland View from the Air - Sand Ridges

  19. Slide 19: Major Shorelines & Deposits

    Slide 19: Major Shorelines & Deposits

    MAJOR SHORELINES & DEPOSITS CYCLONE

  20. Slide 20: Major Shorelines & Proposed Drilling Around Cyclone

    Slide 20: Major Shorelines & Proposed Drilling Around Cyclone

    MAJOR SHORELINES & PROPOSED DRILLING AROUND CYCLONE

  21. Slide 21: Cyclone Deposit & Potential Satellite Deposits

    Slide 21: Cyclone Deposit & Potential Satellite Deposits

    CYCLONE DEPOSIT & POTENTIAL SATELLITE DEPOSITS

  22. Slide 22: Cyclone Deposit - Section

    Slide 22: Cyclone Deposit - Section

    DIATREME RESOURCES LIMITED CYCLONE DEPOSIT - SECTION Le 24m @ 4.1% HM 10.5 @ 1.5% HM 6m @ 2.5% HM 13.6m @ 28% HM LEGEND >s% HM Mi >2.5% HM >1% HM Intersections at 1% HM cutoff 16.5en @ 2.9% HM 12m @ 1.8% HM A 4 l 4 DIATREME RESOURCES LIMITED LOST SANDS Pty Lid EUCLA BASIN PROJECT Western Australia C

  23. Slide 23: Cyclone Deposit Aircore Drilling in Progress

    Slide 23: Cyclone Deposit Aircore Drilling in Progress

    CYCLONE DEPOSIT AIRCORE DRILLING IN PROGRESS

  24. Slide 24: Transport Options

    Slide 24: Transport Options

    DIATREME RESOURCES LIMITED TRANSPORT OPTIONS » Google

  25. Slide 25: Ceduna, S.A. Depot and Company Owned Vehicles

    Slide 25: Ceduna, S.A. Depot and Company Owned Vehicles

    CEDUNA, S.A. DEPOT AND COMPANY OWNED VEHICLES

  26. Slide 26: Ceduna, S.A. Prep Laboratory

    Slide 26: Ceduna, S.A. Prep Laboratory

    CEDUNA, S.A. PREPREP LABORATORY

  27. Slide 27: Ceduna, S.A. Prep Lab - Splitting Samples

    Slide 27: Ceduna, S.A. Prep Lab - Splitting Samples

    CEDUNA, S.A. PREPREP LAB – SPLITTING SAMPLES

  28. Slide 28: Ceduna, S.A. Prep Lab - Ovens

    Slide 28: Ceduna, S.A. Prep Lab - Ovens

    CEDUNA, S.A. PREPREP LAB - OVENS

  29. Slide 29: DRX Corporate

    Slide 29: DRX Corporate

    DIATREME RESOURCES LIMITED V, DRX CORPORATE COMPANY BACKGROUND z y DIRECTORS INFORMATION Diatreme Resources (ASX Code: “DRX") 5 i Anthony John Fawdon FAICD, FAus, IMM. is a Brisbane, Queensland based company i = ~ : Chairman - Executive. DRX is a highly active diversified mineral ; avid Hugh Hall BA

  30. Slide 30: Bringing a World Class Zircon Rich Heavy Mineral Mine into Production

    Slide 30: Bringing a World Class Zircon Rich Heavy Mineral Mine into Production

    4 DIATREME RESOURCES LIMITED r Bringing a World Class Zircon Rich Heavy Mineral Mine into Production

Source: Internet Archive copy of diatreme.com.au