Black Rock Mining Limited · ASX:BKT

Black Rock Mining — Investor Presentation (October 2018)

31 slides from Black Rock Mining's investor presentation, October 2018

  1. Slide 1: Mahenge Graphite – Best of Class Graphite Project

    Slide 1: Mahenge Graphite – Best of Class Graphite Project

    MA H E N G E G R A P H I T E BEST OF CLASS GRAPHITE PROJECT Naturally Better Graphite October 2018 Definitive Feasibility Study BLACK ROCK MINING (ASX: BKT) BLACKROCKMINING.COM.AU 1 1

  2. Slide 2: Important Information

    Slide 2: Important Information

    Important Information The release, publication or distribution of this presentation in certain COMPETENT PERSONS jurisdictions may be restricted by law and therefore persons in such jurisdictions into which this presentation is released, published or The information in this report that relates to Ex

  3. Slide 3: Table of Contents

    Slide 3: Table of Contents

    Table of Contents 1. Summary 2. Black Rock Mining 3. Mahenge Graphite Project – DFS Highlights 4. Mahenge Graphite Project – DFS Detail 5. Next Steps 6. Why Black Rock Appendices A. PFS to DFS Reconciliation B. Port of Dar es Salaam C. Pilot Plant and Flow Sheet D. Proposed Establishment Ramp Up E.

  4. Slide 4: 1. Black Rock Mining Summary

    Slide 4: 1. Black Rock Mining Summary

    1. Black Rock Mining Summary ▪ Mahenge Graphite Project – Black Rock Mining (ASX:BKT) has a 100% interest in the Mahenge Graphite Project located in Tanzania. ▪ Resource – Mineral Resource Estimate of 212 Mt at 7.8% TGC for over 16 Mt of contained graphite. Proven high quality multi-generational Res

  5. Slide 5: 2. Black Rock Mining – Corporate

    Slide 5: 2. Black Rock Mining – Corporate

    2. Black Rock Mining – Corporate ASX Code BKT Key Management Share Price at 19 October 2018 A$0.032 JOHN DE VRIES Shares on Issue 521.8M CEO and Managing Director Options 63.9M Mining Engineer with over 35 years-experience in mine development and operations. Previously, General Performance Rights 1M

  6. Slide 6: 2. Black Rock Mining – Mahenge Graphite Project

    Slide 6: 2. Black Rock Mining – Mahenge Graphite Project

    2. Black Rock Mining – Mahenge Graphite Project ▪ 100% project ownership – Black Rock Mining (ASX:BKT) has a 100% interest in the Mahenge Graphite Project located in Tanzania. ▪ Quality – Proven high quality Resource demonstrated to deliver highest grade concentrate available globally through a simp

  7. Slide 7: 2. Black Rock Mining – Graphite Fundamentals

    Slide 7: 2. Black Rock Mining – Graphite Fundamentals

    2. Black Rock Mining – Graphite Fundamentals ▪ Market in transition – Volume historically led by steel market and Chinese industrialisation. Lithium ion Batteries (LiB) reshaping product type and quality premiums. ▪ Environmental premiums – Significant footprint in refining for LiB has increased pre

  8. Slide 8: 2. Black Rock Mining – Global Graphite Market

    Slide 8: 2. Black Rock Mining – Global Graphite Market

    2. Black Rock Mining – Global Graphite Market ▪ Demand – Expected to double over next decade driven by batteries and expandable applications. ▪ Supply – Current Chinese supply under pressure with Chinese environmental targets driving mine closures. Supply expected to shift from China to Africa. ▪ Pr

  9. Slide 9: 3. DFS Highlights

    Slide 9: 3. DFS Highlights

    3. DFS Highlights ▪ Annual Steady State Production 240k tonnes per annum NPV10 All Brook Hunt Average Sales Price IRR ▪ Graphite Product 97.5% LOI sized Equity Post Tax C1 Margin (US$/t) (%) & FCI** (%) ▪ Life of Mine 32 years ▪ Mine life under Reserve 25 years 1,700 1,349 52.9% 78.1% ▪ Ore Reserves

  10. Slide 10: 4. DFS Detail – The Resource and Reserves

    Slide 10: 4. DFS Detail – The Resource and Reserves

    4. DFS Detail – The Resource and Reserves ▪ Global Resource – globally significant Mineral Resource Estimate (JORC compliant) with over 16Mt of contained graphite • Total area held under licence 519.8 km2 • 175 RC holes for 15,166.7 m of drilling • 34 Diamond holes for 3,911 m • 31 PQ diamond holes

  11. Slide 11: 4. DFS Detail – The Mine

    Slide 11: 4. DFS Detail – The Mine

    4. DFS Detail – The Mine ▪ Tonnes per annum – Modest 1 Mt/y per stage module, with only 1.5 Mt of rock moved given exceptionally low strip ratio. ▪ Low strip ratio – Low life of mine S.R. is 0.6, but varies between 0.5 to 1.0 through pit cut backs. ▪ Equipment – Small equipment proposed consistent w

  12. Slide 12: 4. DFS Detail – The Process Plant

    Slide 12: 4. DFS Detail – The Process Plant

    4. DFS Detail – The Process Plant ▪ Pilot plant – Design is based on data from 90 tonne pilot plant 15 circuit iterations. ▪ Simple – Single circuit eliminates intermediate screen – low technical risk coupled with capital and operating cost benefits. ▪ Modular – Equipment has been nominated as partl

  13. Slide 13: 4. DFS Detail – Site Masterplan

    Slide 13: 4. DFS Detail – Site Masterplan

    4. DFS Detail – Site Masterplan ▪ Light environmental touch ▪ No forest reserves ▪ No commercial crops ▪ No formal settlements ▪ Small dump footprint ▪ Dry stack mill residue ▪ No wet season decant ▪ Dry season water balance ▪ Effective AMD control ▪ 70% reduction in foot print relative to wet dams

  14. Slide 14: 4. DFS Detail – Utilities and Logistics

    Slide 14: 4. DFS Detail – Utilities and Logistics

    4. DFS Detail – Utilities and Logistics ▪ Best in class utilities and logistics – Access to grid power and rail to deep water port provide the Mahenge Graphite Project with best in class utilities and logistics ▪ Power • 60 km from 220 KV national grid • Hydro power • 8.1 cents/unit vs 32 cents/unit

  15. Slide 15: 4. DFS Detail – Capital Expenditure Estimate

    Slide 15: 4. DFS Detail – Capital Expenditure Estimate

    4. DFS Detail – Capital Expenditure Estimate Realistic and deliverable capital expenditure based on substantial engineering test work. Stage 1 Stage 2 Stage 3 Area (WBS Level 1) US$M US$M US$M ▪ Accurate vendor pricing – Over 90% of total capital 1 - Mining* 10.1 - - estimated from direct vendor quo

  16. Slide 16: 4. DFS Detail – Operational Expenditure Estimate

    Slide 16: 4. DFS Detail – Operational Expenditure Estimate

    4. DFS Detail – Operational Expenditure Estimate Defendable and deliverable best-in-class operational expenditure LOM Average LOM Average ▪ Mining – Topographical advantage – deposit US$/t feed US$/t concentrate delivers low strip ratio driving low mining Mining 7.9 98.2 costs. Processing 14.1 175.5

  17. Slide 17: 4. DFS Detail – Project Execution Plan

    Slide 17: 4. DFS Detail – Project Execution Plan

    4. DFS Detail – Project Execution Plan ▪ Segmented approach – Clear accountabilities with Company oversight improves control and quality. ▪ Early civils – Mining fleet completes early civil works with aggerate crusher relocated as stage one mill duty crusher. ▪ EPCM strategy – CPC to transition to o

  18. Slide 18: 4. DFS Detail – Timeline

    Slide 18: 4. DFS Detail – Timeline

    4. DFS Detail – Timeline ▪ Project development – 18 months from board approval to introducing ore into the plant ▪ Staged implementation – Three modules to be constructed over five years 2018 2019 2020 2021 2022 2023 2024 2025 Description Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q

  19. Slide 19: 4. DFS Detail – Graphite Pricing Assumptions

    Slide 19: 4. DFS Detail – Graphite Pricing Assumptions

    4. DFS Detail – Graphite Pricing Assumptions Contract ▪ Product quality – Assumed Mesh # Segment Basket Weight Shipping Channel & Discounts Basket (US$/t) average concentrate grade of Pricing (US$/t) (%) (US$/t) Agent (US$/t) (US$/t) 97.5% LOI with flake size distribution consistent with 90 +32 1,57

  20. Slide 20: 4. DFS Detail – Sales and Marketing

    Slide 20: 4. DFS Detail – Sales and Marketing

    4. DFS Detail – Sales and Marketing ▪ Products matched to markets – Product has large flake bias and Ultra Mahenge Flake Graphite Suitability Targets product has highest concentrate grade Products By Market / Application of any known natural flake graphite flotation concentrate. Strategy is to +32 +

  21. Slide 21: 4. DFS Detail – Permitting and Community

    Slide 21: 4. DFS Detail – Permitting and Community

    4. DFS Detail – Permitting and Community ▪ Environmental Permit – Granted in August 2018. ▪ Mining permit – Application in train and expected to be lodged in October 2018 based on DFS (one version of the truth strategy). ▪ Resettlement framework – Complete and has appropriate community support. ▪ Lo

  22. Slide 22: 4. DFS Detail – Financing

    Slide 22: 4. DFS Detail – Financing

    4. DFS Detail – Financing Board has significant experience in financing and building multi-generational mines globally Project/ MRL Project / MRL Project / MRL ▪ Financing strategy – Multiple options being BKT Debt BKT Equity Equity Sell Down Debt progressed with a focus on maximising share price an

  23. Slide 23: 5. Next Steps

    Slide 23: 5. Next Steps

    5. Next Steps ▪ Construction focus – Transition from “Study mode” to financing and construction ready ▪ Tanzanian centric model – Evolve Operational Readiness and commence recruitment of key national personal Immediate 1H CY19 2H CY19 CY20 Secure Offtake and Construction Ready with Module Assembly a

  24. Slide 24: 6. Why Black Rock

    Slide 24: 6. Why Black Rock

    6. Why Black Rock A uniquely favourable combination of geology and geography makes Mahenge uniquely competitive Geology ▪ Large flake size and industry leading concentrate grades produces a highly desirable product ▪ Massive deposit relatively under explored deposit able to support increased product

  25. Slide 25: Appendix – PFS to DFS Capex

    Slide 25: Appendix – PFS to DFS Capex

    Appendix – PFS to DFS Capex ▪ PFS – Inflated at 4.0% for 18 months to bring PFS to DFS starting point ▪ Scope changes ▪ Dry stacking - filter plant, electricals and piping – but offsets bore field costs ▪ Ifakara rail siding, warehousing and reach stacker, self perform con haulage ▪ Ultra circuit ad

  26. Slide 26: Appendix – PFS to DFS Opex

    Slide 26: Appendix – PFS to DFS Opex

    Appendix – PFS to DFS Opex ▪ Mining - Schedule and bench optimisation ▪ Dry stack – Truck placed and rolled ▪ Mill reagents – Reclaim water from dry stack reduces bore field costs. Optimisation of plant consumption based on metallurgical testwork results ▪ Fuel – Self performed product haulage plus

  27. Slide 27: Appendix – Port of Dar es Salaam

    Slide 27: Appendix – Port of Dar es Salaam

    Appendix – Port of Dar es Salaam ▪ Port of Dar es Salaam – Main deep water port for Tanzania, Zambia, DRC, Rwanda and Birundi. ▪ Shipping frequency – High frequency direct shipping to Asia with a sizeable number of empty container ships currently returning to Asia. ▪ Not seasonal – Consistent annual

  28. Slide 28: Appendix – Pilot Plant and Flow Sheet

    Slide 28: Appendix – Pilot Plant and Flow Sheet

    Appendix – Pilot Plant and Flow Sheet ▪ 90 tonne pilot plant run completed – Pilot plant testwork significantly reduce risk and increase financing options ▪ Pilot plant key facts – In addition to producing substantial volumes of product for customer testing the key facts are presented below • Testwo

  29. Slide 29: Appendix – Proposed Establishment Ramp up

    Slide 29: Appendix – Proposed Establishment Ramp up

    Appendix – Proposed Establishment Ramp up ▪ Tanzanian centric operating model with Australian based governance – Majority of organisation based in Tanzania with focus on local resources with Australian head office oversight ▪ Clear business systems to support operational readiness – Supportive of Ta

  30. Slide 30: Appendix – DFS Contributors

    Slide 30: Appendix – DFS Contributors

    Appendix – DFS Contributors ▪ Over 25,000 hours using tier 1 global consultants and contractors – the following significant studies contribute to the robustness of the DFS outcomes ▪ 90 tonne Pilot Plant – Largest pilot plant in class by a factor of 10 ▪ Vendor testing – materials handling, drying a

  31. Slide 31: John de Vries, Raymond Hekima – Contact

    Slide 31: John de Vries, Raymond Hekima – Contact

    John de Vries Raymond Hekima CEO & Managing Director Vice President Black Rock Mining Mahenge Resources +61 438 356 590 +255 719 382 631 jdv@blackrockmining.com.au Hekiray@blackrockmining.com.au BLACK ROCK MINING (ASX: BKT) BLACKROCKMINING.COM.AU 31 31