  1. Slide 1: Yaouré Gold Mine Development Update – 10 September 2019

    PERSEUS MINING LIMITED| WWW.PERSEUSMINING.COM YAOURÉ GOLD MINE DEVELOPMENT UPDATE – 10 September 2019

  2. Slide 2: Cautionary Statements

    CAUTIONARY STATEMENTS Caution Regarding Forward Looking Information: This report contains forward-looking information which is based on the assumptions, estimates, analysis and opinions of management made in light of its experience and its perception of trends, current conditions and expected develo

  3. Slide 3: Yaouré Gold Project: Developing Perseus's 3rd Gold Mine

    YAOURÉ GOLD PROJECT DEVELOPING PERSEUS’S 3rd GOLD MINE ✓ Robust economics - Gold production of 215,000oz pa @ AISC of US$734/oz for first 5 years. Ore Reserves1 of 1.6 million ounces ✓ Fully Funded - Capital cost of US$265 million ✓ Development commenced – Same team that delivered Sissingué on time

  4. Slide 4: Yaouré Gold Project Development Update

    YAOURÉ GOLD PROJECT DEVELOPMENT UPDATE • Development on schedule • Community Consultation Committee established for local employment, skills survey complete, skills training underway • Ball and SAG mill fabrication 55% complete • Earthworks contracts awarded and most of contractors equipment on site

  5. Slide 5: Yaouré Gold Project Development Schedule

    YAOURÉ GOLD PROJECT DEVELOPMENT SCHEDULE 31/03/19 30/06/19 29/09/19 31/12/19 29/12/19 31/03/20 30/03/20 30/06/20 29/06/20 29/09/20 28/09/20 31/12/20 28/12/20 30/03/21 PROJECT MILESTONES: Award Engineering and Supply Contract Exploitation Permit Issued Plant Bulk Earthworks Commence Construction Camp

  6. Slide 6: Yaouré Gold Project Layout

    YAOURÉ GOLD PROJECT LAYOUT Site Layout Process Plant 3D Design PERSEUS MINING LIMITED| WWW.PERSEUSMINING.COM

  7. Slide 7: Ball and SAG Mill Fabrication ~55% Complete

    BALL and SAG MILL FABRICATION ~55% COMPLETE SAG Mill Pinion SAG Mill Shell final welding Ball Mill Feed Section complete Ball Mill Shell Discharge section SAG Mill Rock Box complete Inching Base Plate complete SAG Mill Ring Guard SAG Mill Feed Trunnion casting

  8. Slide 8: Camp and Fencing Commenced

    CAMP and FENCING COMMENCED Perimeter Fencing Construction Camp complete Permanent Camp clearing

  9. Slide 9: Civils and Bulk Earthworks Underway

    CIVILS and BULK EARTHWORKS UNDERWAY TSF clearing commenced Construction Fuel Farm Plant Site 100% cleared