Perseus Mining Limited · ASX:PRU
Perseus Mining — Corporate Update (September 2019)
10 slides from Perseus Mining's corporate update, Sep 10, 2019
Slide 1: Yaouré Gold Mine Development Update – 10 September 2019
PERSEUS MINING LIMITED| WWW.PERSEUSMINING.COM YAOURÉ GOLD MINE DEVELOPMENT UPDATE – 10 September 2019
Slide 2: Cautionary Statements
CAUTIONARY STATEMENTS Caution Regarding Forward Looking Information: This report contains forward-looking information which is based on the assumptions, estimates, analysis and opinions of management made in light of its experience and its perception of trends, current conditions and expected develo
Slide 3: Yaouré Gold Project: Developing Perseus's 3rd Gold Mine
YAOURÉ GOLD PROJECT DEVELOPING PERSEUS’S 3rd GOLD MINE ✓ Robust economics - Gold production of 215,000oz pa @ AISC of US$734/oz for first 5 years. Ore Reserves1 of 1.6 million ounces ✓ Fully Funded - Capital cost of US$265 million ✓ Development commenced – Same team that delivered Sissingué on time
Slide 4: Yaouré Gold Project Development Update
YAOURÉ GOLD PROJECT DEVELOPMENT UPDATE • Development on schedule • Community Consultation Committee established for local employment, skills survey complete, skills training underway • Ball and SAG mill fabrication 55% complete • Earthworks contracts awarded and most of contractors equipment on site
Slide 5: Yaouré Gold Project Development Schedule
YAOURÉ GOLD PROJECT DEVELOPMENT SCHEDULE 31/03/19 30/06/19 29/09/19 31/12/19 29/12/19 31/03/20 30/03/20 30/06/20 29/06/20 29/09/20 28/09/20 31/12/20 28/12/20 30/03/21 PROJECT MILESTONES: Award Engineering and Supply Contract Exploitation Permit Issued Plant Bulk Earthworks Commence Construction Camp
Slide 6: Yaouré Gold Project Layout
YAOURÉ GOLD PROJECT LAYOUT Site Layout Process Plant 3D Design PERSEUS MINING LIMITED| WWW.PERSEUSMINING.COM
Slide 7: Ball and SAG Mill Fabrication ~55% Complete
BALL and SAG MILL FABRICATION ~55% COMPLETE SAG Mill Pinion SAG Mill Shell final welding Ball Mill Feed Section complete Ball Mill Shell Discharge section SAG Mill Rock Box complete Inching Base Plate complete SAG Mill Ring Guard SAG Mill Feed Trunnion casting
Slide 8: Camp and Fencing Commenced
CAMP and FENCING COMMENCED Perimeter Fencing Construction Camp complete Permanent Camp clearing
Slide 9: Civils and Bulk Earthworks Underway
CIVILS and BULK EARTHWORKS UNDERWAY TSF clearing commenced Construction Fuel Farm Plant Site 100% cleared
Slide 10: Contacts
CONTACTS ASX/TSX: PRU www.perseusmining.com Jeff Quartermaine Andrew Grove Managing Director & CEO GM Business Development & +61 8 6144 1700 Investor Relations +61 414 011 383 Panoramic view of the Yaouré site, Perseus’s third mine development. PERSEUS MINING LIMITED| WWW.PERSEUSMINING.COM