Bci Minerals Ltd · ASX:BCI

Bci Minerals — BC Iron — AJM 12th Annual Global Iron Ore & Steel Forecast Conference (March 2009)

22 slides from Bci Minerals's conference presentation, Mar 24, 2009

  1. Slide 1: AJM 12th Annual Global Iron Ore & Steel Forecast Conference

    For personal use only AJM 12th Annual Global Iron Ore & Steel Forecast Conference March 2009 Mike Young Managing Director

  2. Slide 2: Nullagine Iron Ore Project: Path to Mining

    NULLAGINE IRON ORE PROJECT For personal use only PATH TO MINING  Mineable Resource Pisolite Fines, low contaminants, ultralow P  Mining & Heritage Approvals Surface mining, no pit, above water table  Profitable Mining Methods Surface miner, low strip ratio, ore at surface  Infrastructure Haulage

  3. Slide 3: Company and Nullagine Project overview

    For personal use only Company  Listed ASX December 2006 - Maiden resource March 2008  Meas & Ind Resource Jan 2009 – DFS June 2009  Major shareholders  ConsMinerals and Alkane Resources  Offtake agreement with Tennant Metals Nullagine  Resource 46Mt @ 57% Fe and low Al2O3 and P Project  Feasi

  4. Slide 4: Projects Location

    PROJECTS LOCATION For personal use only Nullagine Project  1500 km2 holding in Pilbara  Adjacent to existing infrastructure Bungaroo Creek Project  Adjacent Rio’s Bungaroo CID  Greenfields project  Awaiting grant of tenure 4

  5. Slide 5: Nullagine Project

    NULLAGINE PROJECT For personal use only Bonnie Creek CID  46Mt DSO 57.0% Fe (64% CaFe)  60 Mt DSO 56.0% Fe present  Ultra-low P, High quality sinter blend  Adjacent to FMG operations Nullagine River CID  DSO & upgrade CID (~5 Mt) Shaw River CID  Potential DSO, upgrade & detritals 5

  6. Slide 6: BC Iron's Strategy

    BC IRON’S STRATEGY For personal use only Bonnie Creek Project  Startup/Ramp up 1.5/3/5 Mtpa  CapEx A$30-40M  OpEx ~$40/tonne FOB  Very low strip ratio – ore at surface  Terrain leveller surface miner  In-pit secondary crushing  Road haul to Christmas Creek/ Cloudbreak  Expand capacity from c

  7. Slide 7: Bonnie Creek – Mineral Resource

    BONNIE CREEK– Mineral Resource For personal use only Total Mineral Resource Estimate – January 2009 DSO Resource Estimate Class Mt Fe CaFe SiO2 Al2O3 P S LOI1000 Measured 1.7 57.0 64.8 3.50 2.10 0.02 0.02 12.0 Indicated 41.2 57.0 64.7 3.10 2.10 0.02 0.01 12.0 Inferred 3.3 56.8 64.5 3.40 2.10 0.02 0.

  8. Slide 8: Iron Ore Deposits – Pilbara Fines Peer Comparison

    IRON ORE DEPOSITS – Pilbara Fines Peer Comparison For personal use only Element/ Typical BCI CID BHP CID RIO CID FMG Compound Spec Bonnie Ck Yandi Robe R Chichester Fe >57 57.0 58.0 57.0 59.1 CaFe >60 64.7 64.2 62.8 64.0 SiO2 3–5 3.1 5.0 5.7 4.2 Al2O3 < 2.0 2.1 1.3 2.7 2.3 P < 0.10 0.016 0.04 0.04 0

  9. Slide 9: Bonnie Creek CID – Outcamp Prospect

    BONNIE CREEK CID – Outcamp Prospect For personal use only 801,000E 802,000E 803,000E 804,000E 805,000E 7,562,000N 7,561,000N Scale 500 m Outcamp-Warrigal  38 Mt at 57.0% Fe (64.7% CaFe)  Low strip ratio  Outcropping mineralisation 9

  10. Slide 10: Bonnie Creek CID – Outcamp Prospect

    BONNIE CREEK CID – Outcamp Prospect For personal use only Conceptual ‘pit’ outline Regional surface  Shallow “pits” mainly above surrounding plains - mining ore from day 1 Above water table - lower environmental impact Low OpEx - low strip ratio, use of surface miners 10

  11. Slide 11: Bonnie Creek CID – Warrigal Well

    BONNIE CREEK CID – Warrigal Well For personal use only  Ore body at top of hills, no mining below surface Accessible by 4 WD along length of ore bodies Simple surface mining, very low strip ratios 11

  12. Slide 12: Bonnie Creek CID – Mining

    BONNIE CREEK CID – Mining For personal use only VERMEER TL1255 Terrain Leveller  Drill & Blast not required  Primary Crushing not required  Mine Haul Trucks not required VERMEER TL1255 operating at Cloud Break (FMG) – photo by BC Iron 12

  13. Slide 13: The Right Mill – Blast Furnace

    THE RIGHT MILL - BLAST FURNACE For personal use only Blast furnace • Iron ore & coal are added at the top in alternating layers – lump & coke only • Hot air is blasted into the bottom of the furnace • Rising gases provide environment for reducing the iron oxides – Fe2O3  FeO • Descending burden mel

  14. Slide 14: Niche Product – Sinter Feed

    NICHE PRODUCT – SINTER FEED For personal use only Sintering  All iron ore mines produce a lump and fines but only lump can be used in the blast furnace  Synthetic lump is made by from fines by high temperature agglomeration - sintering  Sintering creates “Made to order” lump  Optimal physical pr

  15. Slide 15: Sintering Quality

    SINTERING QUALITY For personal use only Sintering Qualities of BCI Ore  Independently tested in China – Shandong Uni  Blended with a typical fines sinter feed  Using 0, 10, 20, and 30% blend  Resulted in increased quantity and quality of sinter – “First Class”  Test work results:  Increased si

  16. Slide 16: Infrastructure

    INFRASTRUCTURE For personal use only Infrastructure Strategies  Rail Haulage with FMG/TPI  Port access via TPI Anderson Point – 2009  Port access via Utah Point facility - 2010  Port access via planned NWIOA facility - 2012  Rail Access under TPI State Agreement using contract haulage by a rail

  17. Slide 17: Marketing

    MARKETING For personal use only Marketing Offtake  Offtake agreement with Tennant Metals  25% Offtake to Tennant as Principal or Agent  Mechanisms for increased offtake  Australian company – Australian bank payments  BC Iron Ore Marketing Strategy  Customised sinter blend – high Value in Use 

  18. Slide 18: Bonnie Creek Project

    BONNIE CREEK PROJECT For personal use only  Baseline Environmental Surveys Completed  Infill drilling Completed  Resource Estimate Completed  Feasibility Study First Half 2009  Mining Approvals First Half 2009  Construction commences Second Half 2009  Production First Half 2010 2H 2008 1H 200

  19. Slide 19: Bonnie Creek Project

    BONNIE CREEK PROJECT For personal use only  Mineable Resource ✓ Pisolite Fines, low contaminants, “ULP"  Mining & Heritage Approvals ❐ Surface mining, no pit, above water table  Profitable Mining Methods ✓ Surface miner, low strip ratio, ore at surface  Infrastructure ❐ Haulage agreement / State

  20. Slide 20: For personal use only

    For personal use only This release may include forward-looking statements. These forward-looking statements are based on management’s expectations and beliefs concerning future events. Forward-looking statements are necessarily subject to risks, uncertainties and other factors, some of which are out

  21. Slide 21: Translation - The lawyers are winning.

    For personal use only Translation - The lawyers are winning. 21

  22. Slide 22: Mike Young, Managing Director; Blair Duncan, Operations Manager

    For personal use only Mike Young, Managing Director Blair Duncan, Operations Manager