  1. Slide 1: Dominion Energy Tredegar Parking Garage Solar Array Project

    Dominion Energy Tredegar Parking Garage Solar Array Project March 19, 2021 1

  2. Slide 2: Dominion Energy Project Team

    Dominion Energy Project Team Dominion Energy • Manager Capital Projects: Kyle Young • Senior Project Manager: Harvey Jones • External Affairs Manager: Felix Sarfo-Kantanka Jr. Project Partnerships • Vanasse Hangen Brustlin • Sun Tribe Solar 2

  3. Slide 3: Dominion Energy's Clean Energy Initiative

    Dominion Energy’s Clean Energy Initiative Over the next 15 years, Dominion Energy plans to add enough solar energy to power 4 million homes when the sun is shining in support of Virginia’s plan for 100% zero-carbon electricity by 2045 and our goal of net zero carbon and methane emissions across all

  4. Slide 4: Project Outline

    Project Outline Utilize existing top level of the Clearinghouse parking garage to install a new Solar Array Canopy. The generation of the Solar Array will be interconnected back to the electrical grid. 4

  5. Slide 5: Design Concept

    Design Concept • This project would be the largest solar array in downtown Richmond. • Canopy Design – Full roof canopy • Individual Solar Panels – 1,404 • Solar Array will generate enough energy equal to powering 120 homes. 5

  6. Slide 6: Elevations

    Elevations Top of Parapet Elevation = 917’ Solar Array Elevation = 102’ — Zoning Height BS Zoning = 127.5"* = Zoning Height 2001 SUP = 112.5’ ~# " September 2001 Restrictive 75) Covenants = 111.0’ — Mean Grade Elevation = 52.5” *B5 Zoning Height is 6 stories for a parking garage (5 stories + 1) Elev

  7. Slide 7: Photos and Schematics

    1 Photos and Schematics 3 2 4 1& 2. As you can see in both the picture view from Oregon Hill and the section, the existing vegetation blocks the view of the proposed solar array. (1) 3. This section shows the differences in elevation between the residential units on Oregon Hill and These pictures sh

  8. Slide 8: Viewshed Renderings

    Viewshed Renderings 1 2 3 • Rendering 1 – Oregon Hill fall/winter view. • Rendering 2 – Oregon Hill spring/summer view. • Rendering 3 – Belle Isle summer view. 8

  9. Slide 9: Project Milestones

    Project Milestones Partnership Selection: Sun Tribe Solar, August 2020 Neighborhood Engagement: Letters to neighbors, associations, project web page, September 2020 City of Richmond: Zoning Confirmation Request, September 2020 City of Richmond: Zoning Confirmation Approved, November 2020 Town Hall M

  10. Slide 10: Learn More

    Learn More Please visit our website at DominionEnergy.com/TredegarSolar 10