Gibb River Diamonds Limited · ASX:GIB

Gibb River Diamonds — Investor Presentation (October 2018)

18 slides from Gibb River Diamonds's investor presentation, Oct 26, 2018

  1. Slide 1: POZ Minerals Limited Investor Presentation - Singapore

    POZ Minerals Limited Investor Presentation Singapore Australia’s Next Diamond Producer October 2018 Blina Diamond Project ASX Code: POZ Kimberley, Western Australia www.pozminerals.com.au

  2. Slide 2: POZ Minerals Limited (ASX Code – POZ)

    POZ Mineral Limited (ASX Code – POZ) Total Shares on Issue 179,079,445 Board Of Directors Market Capitalisation (undiluted at $0.06 per share) $11 M Cash on Hand (30 September 2018) $1.6 M Major Shareholders Shares % of Capital Jim Richards 35,349,735 19.7 Other Directors 14,540,555 8.1 Executive Ch

  3. Slide 3: Peer Comparison

    Peer Comparison Market capitalisation shows POZ as undervalued within peer group Company Stock Exchange Diamond Operations Location Market Cap & Code A$ million Lucapa Diamond Company ASX: LOM Mining/Development Angola/Lesotho 107 Newfield Resources Limited ASX: NWF Bulk Sampling Sierra Leone 84 Bli

  4. Slide 4: Blina Diamond Project, WA: Location

    Blina Diamond Project, WA: Location Excellent access,120km west of Derby, WA. • Total of 446km2 of POZ ground • Excellent logistics & access • Previous diamond production from Terrace 5 • Fancy yellow diamonds signature stone • Surrounds the former Ellendale 9 diamond mine • Granted mining leases 4

  5. Slide 5: Terrace 5 Targets West of the E9 Mine Area

    Terrace 5 Targets West of the E9 Mine Area 5

  6. Slide 6: Terrace 5 - Proven Diamondiferous Channels

    Terrace 5 - Proven Diamondiferous Channels Channels 1&2 • Tested grades average 6,8 cphm3 (carats per hundred cubic metres) • 1 to 5 metres deep • Free dig (no blasting) • Trial mining in Cuts 1 & 2 recovered 1,497 carats valued at US$389 per carat • High grade GPR trapsite targets to be tested Grav

  7. Slide 7: July 2018: POZ Trenching Discovery

    July 2018: POZ Trenching Discovery POZ Geologists discover 2.4 million square metres of new shallow gravel targets A recent POZ trenching program has identified 2.4 million m2 of previously untested, shallow and highly prospective gravels, all of which are free dig. The shallowest of these areas are

  8. Slide 8: Type Section Area A Diamond Target Gravels

    Type Section Area A Diamond Target Gravels 8

  9. Slide 9: Previous Work: Trial Mining of Terrace 5

    Previous Work: Trial Mining of Terrace 5 Trial Mining of Terrace 5 in 2005/06 at Cuts 1&2 (POZ ground) Cut 1 • 40,613 cubic metres mined • Grade: 3.53 carats per hundred cubic metres (cphm3) • 1,432 carats recovered Terrace 5 diamonds are in the basal gravels • This diamond parcel valued at US$389/c

  10. Slide 10: Blina Terrace 5 Diamond Valuation

    Blina Terrace 5 Diamond Valuation A recent independent valuation of a 1,497 carat parcel of diamonds from Terrace 5 stated: • The overall parcel valuation was US$389 per carat (A$505 per carat) • The Fancy Yellow component was valued at US$3,391 per carat (A$4,403 per carat) Terrace 5 diamonds. All

  11. Slide 11: High Grade Diamond Trap Sites

    High Grade Diamond Trap Sites Target gravels in a pothole Jim Richards, mining diamonds How potholes concentrate diamonds from potholes in Guyana, 1991 Auchas Diamond Mine, Namibia: Pothole sequence 11

  12. Slide 12: New Technology Ground Penetrating Radar (GPR) Targets High Grade Trap Sites

    New Technology Ground Penetrating Radar (GPR) Targets High Grade Trap Sites 2002 2017 Old GPR Technology: New GPR Technology: • Compare GPR last used at Previous Blina Survey POZ Minerals Survey Blina in 2002 with latest POZ GPR survey data in 2017 • New rapid GPR data acquisition rates fixes previo

  13. Slide 13: Untested 'High Grade' Targets 2, 3 & 4

    Untested ‘High Grade’ Targets 2, 3 &4 May 2018: Target 2 was auger drilled and returned these highly prospective gravels from 5 to 7 metres 13

  14. Slide 14: Alluvial Mining Shallow & Simple & Low-cost

    Alluvial Mining Shallow & Simple & Low-cost Blina Diamonds NL • Targets gravels only 0.3 to 6 metres deep mining alluvials in 2007 • Phase 1: Commission plant & commence bulk sample diamond recovery • Phase 2: Trial mining of best grades Blina Diamonds NL mining alluvials in 2007 14

  15. Slide 15: POZ Diamond Recovery Plant

    POZ Diamond Recovery Plant Trommel, Screens, and Diamond Sortex Blina Diamonds NL recovery plant in 2006 (~30m3 per POZ fabricated rotary POZ Trommel (~30m3 per hour) hour): same trommel has been purchased by POZ twin screen unit Grizzly Trommel DMS, Screens & Classifier POZ built diamond Sortex Mac

  16. Slide 16: Project Milestones

    Project Milestones Achievements So Far & Operational Goals Achievements So Far  Historic mining Agreement with Bunuba Group  Grant of four Mining Tenements  Alluvial trapsite targets defined by GPR surveys and historic data  Heritage clearance survey with Traditional Owners  Purchase of major p

  17. Slide 17: POZ Minerals Limited

    POZ Minerals Limited Australia’s Next Diamond Producer Contact Details: Jim Richards – Executive Chairman +61 8 9422 9500 16 Ord Street, West Perth, WA 6005 Email – info@pozminerals.com.au www.pozminerals.com.au ASX Code: POZ 17

  18. Slide 18: Disclaimer

    Disclaimer This presentation is an overview of the Company prepared with good intention. It is not a prospectus and offers no securities for subscription or sale in any jurisdiction, nor a securities recommendation. All information necessary for investment decisions is not contained herein and inves