Northern Minerals Limited · ASX:NTU

Northern Minerals — Investor Presentation (October 2014)

39 slides from Northern Minerals's investor presentation, October 2014

  1. Slide 1: Investor Presentation

    INVESTOR PRESENTATION George Bauk Managing Director/CEO OCTOBER | 2014 | ASX:NTU OUR VISION To become the first significant dysprosium producer outside of China

  2. Slide 2: Important Notice

    Important Notice This presentation has been prepared by Northern Minerals Limited ("Northern Minerals” or the “Company”). it should not be considered as an offer or invitation to subscribe for or purchase any securities in the Company or as an inducement to make an offer or invitation with respect t

  3. Slide 3: Northern Minerals

    Northern Minerals Listed ASX October, 2006 (ASX:NTU) Flagship project Browns Range WA, 100% owned Since July 2010 expenditure exceeds $74M From maiden drill hole to PFS in under 3 years Xenotime - simple mineralogy Resource size only limited by funding Powering Technology. & ‘® Darwin Wyndham Je Kun

  4. Slide 4: Share Price ($/share)

    High $0.285* 6.0 Low 0.30 $0.115* 5.0 0.25 4.0 0.20 Share Price ($/share) Volume (m) 3.0 0.15 2.0 0.10 1.0 0.05 0.0 0.00 11 Oct 13 08 Nov 13 06 Dec 13 03 Jan 14 31 Jan 14 28 Feb 14 28 Mar 14 25 Apr 14 23 May 14 20 Jun 14 18 Jul 14 15 Aug 14 12 Sep 14 10 Oct 14 Volume Share Price

  5. Slide 5: Recent Achievements

    Recent Achievements Dysprosium 9.3% = Per nn Cerium Feasibility Study commenced Praseodymium F Neodymi Mineral Resource — A Samarium 52,372,000kg TREO Europlum in /—— Gadolinium h— Terbium Holmium 2.0% — Thulium 0.8% Ytterbium 4.4% Lutetium 0.6% Ft 60.5% Hydromet recovery 92% “ Dy and 92.6% TREO imp

  6. Slide 6: Our people

    Strategic management & leadership Confidence Values Integrity Rare earth operational experience Knowledge Commitment Conglin Yue Initiative George Bauk International mining knowledge Relationships Our Kevin Schultz Honesty Mark Tory Develop Results Colin McCavana Management Executive people SPIRIT Y

  7. Slide 7: Heavy Rare Earth Uses

    Heavy Rare Earth Uses

  8. Slide 8: Rare Earths Essential for Hybrid and Electric Vehicles

    Rare Earths Essential for Hybrid and Electric Vehicles China’s objective: to achieve 5 million hybrid and electric vehicles by 2020

  9. Slide 9: The rare earth marketing landscape

    The rare earth marketing landscape Dy still critical in energy intensive applications, despite efforts to find substitute materials Producers forecasting increased HRE prices in 2016 NdFeB magnet sector fastest growing - forecasted to grow 8-12% annually to 2020 Admission by Chinese producers illega

  10. Slide 10: Years is only the beginning

    10 years is only the beginning A Production Wolverine Current Reserve 23,595,000kg TREO Reserves Gambit West @ camvit @ Areas 2,048,000kg a Resource 4,338,300kg Scambit area esources fo on ee ea” size only “ar Fae er eee signee limited by @sohn Galt (Main Zone) | Mystique ee Rutten, Fe! Pen Intersec

  11. Slide 11: Outstanding Exploration Potential

    Outstanding Exploration Potential 1,500km2 Browns Range Dome WA/NT Greenfields Discovery 2010 6 out of 13 targets converted mineral resource Growth Potential Exploration only limited by funding Blue Sky Massive landholding WA and NT Access rights to 95% and only 12% explored to date Powering Technol

  12. Slide 12: Browns Range Dome

    Browns Range Dome =1920otmn The dome is a massive geological feature covering 1,500km2 and stretching 60km x 30km most of which hasn’t ae ; been effectively cai fant. = explored [| Nonhom MineraisGrarted Tenement.» [] Mining Lease [__] Notthern Minerals Tenement Application © Norther Minerals RE Min

  13. Slide 13: Extend Mine Life by Increasing Resources

    Extend Mine Life by Increasing Resources OPEN.... Gambit, Gambit West and Area 5 OPEN... Wolverine deposit open at depth and along strike, no drilling below 550m open near surface and open at depth, no drilling below 200m etme D> NaBH ar + Renee NORTHERN MINERALS. NORTHERN Browns Range Pr | MINERALS

  14. Slide 14: Ore Reserve and Mineral Resource summary

    TREO Dy2O3 Tb4O7 Y2O3 Ore kg kg kg kg Deposit Classification kg/t kg/t kg/t kg/t Tonnes contained contained contained contained Total1 Probable 3,409,000 6.92 23,595,000 0.60 2,048,000 0.09 306,000 4.01 13,663,000 TREO Dy2O3 Y2O3 Tb4O7 HREO TREO Deposit Category Mt % kg/t kg/t kg/t % kg Indicated 4.

  15. Slide 15: Project Location

    Project Location a most attractive investm ation by the Frase Institute Survey of Mining Companies, 2013. NORTHERN TERRITORY BROWNS RANGE PROJECT (aH WESTERN ae oS AUSTRALIA The Browns Range Project is located within Ss DROWNS RANGE: the Gordon Downs pastoral lease in the Shire of Halls Creek, Weste

  16. Slide 16: Environment, Indigenous Employment, Community

    Environment Indigenous Employment > Government assessment & approval > Developing local > Extensive studies & surveys to employment strategy inform project design > Cultural awareness > Ongoing rehabilitation nr) > Ongoing employee support s . & compliance reporting & LICENCE TO p2) OPERATE o = © ¢

  17. Slide 17: Mineral concentrate production by year

    Year 1 Year 2 Year 3 Year 4 Year 5 Total 17,045tpa mineral concentrate @ 20% TREO

  18. Slide 18: Mining & Beneficiation Process Flowsheet

    On) | MINING BENEFICIATION ‘Mining & Production ; Process Flowsheet SR é Gas = Wet Magnetic Cleaner [ome) wy Separation Flotation ROM Ore om fr Q —— up Crushing lly hr ete oe CODD itrtion aa mw Tailings Storage Concentrate Gas al Facility $$$ NORTHERN ‘ Leach MINERALS. ah d——b Ge Residue Sulphation

  19. Slide 19: Accommodation village and site infrastructure

    Accommodation village, peak 325 people 1.8km airstrip Diesel generators and distribution Groundwater supply and distribution Consumable and reagent storage facilities Road transport via Halls Creek to/from Wyndham and Darwin ports Above ground Tailings Storage Facility Water Ponds Waste Water Treatm

  20. Slide 20: Pre-production Capital Cost Estimate

    Pre-production Capital Cost Estimate Mining ae Cost Area Aor % Teel $4M Ww J aia Plant Mine $3.1 1% Ancillary Beneficiation Plant $35.6 1% Infrasucture Hydrometallurgical Plant $37.8 12% Plant Infrastructure $56.6 18% Ancillary Infrastructure $73.8 24% Direct Costs Sub-Total $206.9 66% Indirect Cost

  21. Slide 21: Operating Costs

    Operating Costs (585,000tpa plant throughput) Average Annual Operating Cost By Expense Area Over LOM Mining (Average over LOM) Labour Power Reagents & Consumables Maintenance General & Administration Product Transport Total Annual Operating Costs By-product Revenue Operating Cost Excluding Royalties

  22. Slide 22: NPV, IRR and payback

    net present internal rate of value1 return production in pre-production capital cost payback from commencement of operations 110% discount rate Operating cost Operating cost excluding royalties including royalties and net of by-product revenue

  23. Slide 23: Source of Funds

    Source of Funds Announced Source Feb 2013 Actual ee ee $M Placements $3.8 Rights Issue $26.5 16% of BR + 20% offtake $26.0 Sale Gardiner Tanami Gold Assets $2.0 R&D Net Funding Costs/Interest Total $58.3 * Placements includes $2M announced in November 2012 Powering Technology. $11.1" $26.6 $16.8 -$2

  24. Slide 24: Application of Funds

    Application of Funds Announced Actual/Forecast Expense Category Feb 2013 to 31 Dec 14 $M $M . On track to deliver Geology/Exploration _ $14.0 $16.6 Feasibility Study Engineering, Infrastructure and Mining - : /y Study $12.2 $10.6 with a significantly Mineral Processing and Metallurgy $9.7 $8.8 of En

  25. Slide 25: Project Funding Status

    Project Funding Status ® Term sheets and MoUs out for discussion ® China, South East Asia and North America key target areas Other RE . . . . . . revenue ® Flexible funding strategies including possible 38% project joint venture partner, debt, equity and pre-sale of product Dysprosium 62% ®@ Data ro

  26. Slide 26: JORC resource increase and maiden Ore Reserve

    + JORC resource increase 52,372,000kg and maiden Ore Reserve 23,595,000kg * Co-existence Agreement signed, mining lease granted, primary environmental approval advanced * Completion of Pre-Feasibility Study, Feasibility study well underway

  27. Slide 27: Pathway to Production

    Pathway to Production 2014 Pilot Plant Programs = Tenure and Native Title = Project Approvals Feasibility Study Project Funding Procurement Early Works Construction Program Plant Construction Mining Commissioning Production Ramp Up Current Position > Powering Technology. 2015 Specialist engineers an

  28. Slide 28: Browns Range: The next Dy mine

    Browns Range: The next Dy mine Powering Technology. Feasibility Study Fe Offtake and funding Discussions ongoing Licencing

  29. Slide 29: Appendices

    APPENDICES NORTHERN

  30. Slide 30: Probable Ore Reserve

    Probable Ore Reserve Classification O°. OPEN PIT Wolverine Probable 863,000 5.30 4,574,000 0.47 407,000 0.07 62,000 3.14 2,712,000 Gambit West Probable 185,000 10.92 2,021,000 0.90 167,000 0.12 23,000 5.97 1,105,000 Gambit Probable 47,000 9.94 467,000 0.85 40,000 0.1 5,000 6. 287,000 Area 5 Probable

  31. Slide 31: Mineral Resource Estimate

    Mineral Resource Estimate Category Indicated 266 0.89 0.78 5.17 012 89 23,705,000 Wolverine inferred 18 0.81 0.67 4.45 Ol 87 14,564,000 Total! 4.46 0.86 0.74 488 on 88 38,269,000 Indicated 0.27 1.26 1.07 7.06 O14 90 3,424,000 Gambit West Inferred 012 0.64 0.54 3.67 0.07 85 753,000 Total! 0.39 1.07 0

  32. Slide 32: John Galt Project (WA)

    John Galt Project (WA) @ Rock chip samples up to 42% TREO with approximately 95% HREO @ Preliminary metallurgical tests indicate excellent recovery rates (>90%) with potential for concentrate grades >40% @ High grade mineralisation in talus (scree) material - hard-rock source of scree is the primary

  33. Slide 33: Boulder Ridge Project (NT)

    Boulder Ridge Project (NT) ® Rock chip samples from the Boulder Ridge project confirm high-grade heavy rare earths (HRE) @ Best results exceed 12% TREO, including up to 1.15% Dysprosium, with a dominance of HRE - up to 99% @ Further exploration planned to commence in Q4 2014 to refine drill targets

  34. Slide 34: Changing Production of Rare Earths

    Changing Production of Rare Earths 140 GLOBAL PRODUCTION 30] OF RARE EARTH OXIDES 1950 - 2013 no 100 1950 MONAZITE-PLACER ERA } MOUNTAIN PASS ERA 1960 : 1970 1980 : 1980 2000 : CHINESE ERA 2013 i EXPORT QUOTA ERA Powering Technology. Production increasing from sources outside of China Mt Weld (Aus)

  35. Slide 35: Rare earth supply chain

    Upstream Midstream Downstream Extraction Beneficiation & Separation Alloy Component End-use Hydrometallurgy manufacture manufacture manufacture Refining/Recycling High purity Mixed carbonate oxides (99-99.9%)

  36. Slide 36: The Right Leadership

    The Right Leadership A wealth experience and knowledge to strategically guide Northern Minerals to the next dysprosium miner BOARD OF DIRECTORS Conglin Yue - Executive Chairman * Long standing relationship with a number of major steel producing companies in China. * Chairman of Conglin Baoyuan Inter

  37. Slide 37: The Right Management

    The Right Management Relevant range of experience and expertise to develop and commercialise the Browns Range Project EXECUTIVE MANAGEMENT TEAM Robin Wilson - Exploration Manager Robin Jones - Project Manager * Geologist, with 20 years experience in Australia and Africa. * More than 20 years experie

  38. Slide 38: HRE Project vs LRE Project

    HRE Project Distribution of Rare Earths at Browns Range Wolverine (February 2014) Neodymium 315% Cerium 477% Lanthanum Europium 18% 0.4a% Praseodymium —— Lutetium 0.68% 0.60% Thulium 0.74% Terbium 132% Holmium usa Samarium 212% Ytterbium 4.39% Yttrium — Erbium 58.21% 5.33% Gadolinium 571% ——Dysprosi

  39. Slide 39: Typical Landscape Browns Range Project

    Typical Landscape Browns Range Project = ts ¢ f ne = is es Wat OS ee A ring Technology. ga

Northern Minerals — Investor Presentation (October 2014) on 6ix