  1. Slide 1: Lynas Rare Earths Limited Annual General Meeting

    For personal use only Lynas Rare Earths Limited Annual General Meeting 27 November 2024

  2. Slide 2: Disclaimer

    Disclaimer This presentation has been prepared by Lynas Rare Earths Limited (ABN 27 009 066 648) (Lynas as a general guide only and should not be relied upon as an indication or guarantee of future or the Company) this presentation contains summary information about Lynas and its subsidiaries perfor

  3. Slide 3: Acknowledgement of Country

    Acknowledgement You will need to of Country For personal use only 1. 2. Lynas xx Rare Earths acknowledges the Traditional Owners of the lands on which we live, work and meet, across Australia. We acknowledge and value Lynas’ Aboriginal and Torres Strait Islander employees, partners and communities a

  4. Slide 4: Chair's address

    Chair’s address John Humphrey For personal use only

  5. Slide 5: FY24 Operational highlights

    FY24 Operational highlights Continuing C&L operations in Malaysia following licence variation For personal use only Total costs reduced by 17% FY24 compared to FY23 due to focus on efficiencies Construction complete and commenced production at new Kalgoorlie Facility Major upgrade works completed at

  6. Slide 6: Increasing sustainability in our operations

    Increasing sustainability in our operations For personal use only 0.75MW rooftop solar panel 65MW Mt Weld hybrid power station installation underway at in progress with Zenith Energy Lynas Malaysia 6

  7. Slide 7: Building prosperity in our communities

    Building prosperity in our communities For personal use only 75% $10.1m $400k 40 invested in community Lynas Local Giving local suppliers in invested in R&D in community grants FY24 FY24 support and initiatives in FY24 since 2022 $84.1m 93% 1117 paid in employee $61.9m of employees are Employees glo

  8. Slide 8: CEO presentation

    CEO presentation Amanda Lacaze For personal use only

  9. Slide 9: Lynas 2025 growth plan: years of progress

    For personal use only Lynas 2025 growth plan: 5 years of progress

  10. Slide 10: Lynas 2025 growth plan objectives

    Lynas 2025 growth plan objectives 1 A larger business to meet forecast demand growth For personal use only 2 Diversified industrial footprint with processing facilities in optimal locations 3 Supplier of choice to strategic customers with a fit for market product portfolio 4 Enhanced performance thr

  11. Slide 11: A larger business to meet forecast demand growth

    1 A larger business to meet forecast demand growth For personal use only Mt Weld Expansion New Kalgoorlie Rare Earths Kuantan Facility Expansion Processing Facility 11

  12. Slide 12: Mt Weld Mineral Resource and Ore Reserve Update 2024

    Mt Weld Mineral Resource and Ore Reserve Update 2024^ For personal use only 92% increase 63% increase 46% increase in mineral resources in ore reserves from in TREO from August from June 2018* June 2018** 2018 92% increase >35 year >20 year in contained Dy oxide Ore Reserve mine life Ore Reserve min

  13. Slide 13: Mt Weld Mineral Resource distribution

    Mt Weld Mineral Resource distribution^ Extensive drilling program Enhanced understanding of mineralogy Expansive HRE halo For personal use only complete, over 84,000m in ore zones identified and scoped Plan view of hole collar points at Mt Weld. Current mined pit (grey) and dolerite dyke (green) dis

  14. Slide 14: Mt Weld in 2019

    For personal use only Mt Weld in 2019 14

  15. Slide 15: Mt Weld today

    Mt Weld today TSF3 For personal use only Filter building Stage 2 (grinding and flotation) Crusher pad 2019 TSF4 (under construction) Hybrid Power Station (under construction) New concentrate shed Expansion warehouse 15

  16. Slide 16: Mt Weld expansion Stage complete and operational

    Mt Weld expansion Stage 1 complete and operational For personal use only 16

  17. Slide 17: Mt Weld expansion Stage on track

    Mt Weld expansion Stage 2 on track For personal use only 17

  18. Slide 18: Mt Weld Expansion flythrough

    Mt Weld Expansion flythrough For personal use only Video available at: https://www.youtube.com/@LynasTV 18

  19. Slide 19: Lynas Malaysia in 2019

    Lynas Malaysia in 2019 For personal use only 19

  20. Slide 20: Lynas Malaysia today

    Lynas Malaysia today Plume from stack is water vapor (“steam”) WLP Permanent Disposal Facility under construction For personal use only Previous WLP Residue NUF storage facility Storage Facility MREC receival Waste gas treatment stacks Kilns Product finishing Primary and secondary leaching Onsite la

  21. Slide 21: Increasing capacity to 10.5Kt p.a. NdPr

    Increasing capacity to 10.5Kt p.a. NdPr For personal use only New robotic arm to lift crucibles New solvent extraction circuit 21

  22. Slide 22: Lynas Malaysia flythrough

    Lynas Malaysia flythrough For personal use only Video available at: https://www.youtube.com/@LynasTV 22

  23. Slide 23: Diversified industrial footprint with processing facilities in optimal locations

    2 Diversified industrial footprint with processing facilities in optimal locations United States For personal use only ~1.3ktpa NdPr Target finished product Processing Malaysia Capacity ~2.5 - 3.0ktpa Malaysia HRE ~7ktpa ~7ktpa Target Target NdPr NdPr Processing Processing production production Capa

  24. Slide 24: Lynas' Kalgoorlie Project in 2022

    Lynas’ Kalgoorlie Project in 2022 For personal use only 24

  25. Slide 25: Kalgoorlie Rare Earths Processing Facility today

    Kalgoorlie Rare Earths Processing Facility today Plume from stack is water vapor (“steam”) For personal use only Automated filter press Rotainer logistics Waste gas treatment Onsite laboratory 110m long kiln 25 Photo: Kalgoorlie Facility Nov 2024

  26. Slide 26: Kalgoorlie official opening

    For personal use only Kalgoorlie official opening 8th November 2024 26

  27. Slide 27: Lynas Kalgoorlie flythrough

    Lynas Kalgoorlie flythrough For personal use only Video available at: https://www.youtube.com/@LynasTV 27

  28. Slide 28: Progressing Lynas' U.S. Rare Earths Separation Facility project

    Progressing Lynas’ U.S. Rare Earths Separation Facility project Partnering with the U.S. DoD to deliver onshore Rare Earths Processing For personal use only April 2020 July 2020 January 2021 June 2022 August 2023 March 2024 August 2024 Lynas announces Phase 1 HRE LRE separation facility $120m HRE aw

  29. Slide 29: Supplier of choice to strategic customers with a fit for market product portfolio

    3 Supplier of choice to strategic customers with a fit for market product portfolio For personal use only Dy and Tb to be produced at Lynas Malaysia for first time in CY2025 Photos; HRE separation circuit at Lynas Malaysia 29

  30. Slide 30: $10m R&D investment in FY24

    $10m R&D investment in FY24 For personal use only Process of the future Business of the future • Lower unit cost • New products • Lower GHG emissions • New markets e.g. catalysts • Reduced residues/by- for Green Hydrogen products • Reduced water and • Partnerships with industry chemical and research

  31. Slide 31: Enhanced performance through the cycle

    4 Enhanced performance through the cycle For personal use only 300% Production Volume REOt Lynas NdPr Production Cost EBITDA & NdPr market price 8,000 Index: 100=Average 2016 250% 700 110 7,000 600 90 6,000 200% 500 70 5,000 400 50 A$’mil 150% 30 US$/kg 4,000 300 3,000 10 100% 200 -10 2,000 100 -30

  32. Slide 32: Investing for growth

    5 Investing for growth For personal use only $1.45 billion invested from 2019 to 2024 External funding USA development • A$425m equity raising • United States • Approx A$213m JARE equity investment Government funding Operating cashflow • A$34.8m Australian Government MMI grants of US$288m 32

  33. Slide 33: Fit for the future

    For personal use only Fit for the future

  34. Slide 34: Positioned to meet market needs

    Positioned to meet market needs Rare earths market demand continues to grow Long term forecast for rare earths in magnets Supply requirements to 2050 For personal use only (kt REE) Source: Project Blue 34

  35. Slide 35: Productive, profitable and growing

    Productive, profitable and growing Low cost producer For personal use only 20-year life of mine at 12,000 tpa NdPr Expanded operating footprint Increased product range (LRE & HRE) Transitioning to clean energy sources 35

  36. Slide 36: Lynas Rare Earths Limited Annual General Meeting

    For personal use only Lynas Rare Earths Limited Annual General Meeting 27 November 2024

  37. Slide 37: Resolution – Remuneration Report

    Resolution 1 – Remuneration Report This resolution is seeking approval for adoption of the 2024 Remuneration Report which is set out in the Annual Report. The Remuneration Report sets out specific details of the Company’s remuneration For personal use only framework in the year ended 30 June 2024. P

  38. Slide 38: Text of Resolution – Remuneration Report

    Text of Resolution 1 – Remuneration Report For personal use only “That the Remuneration Report of the Company for the year ended 30 June 2024 be adopted.” 38

  39. Slide 39: Resolution – Re-election of Philippe Etienne as a Director

    Resolution 2 – Re-election of Philippe Etienne as a Director Mr Etienne joined the Company as a Non-Executive Director on 1 January 2015. He is a Non-Executive Director and Chair of Cleanaway Waste Management Limited (appointed Chair 20 September 2023) and Non-Executive Director of For personal use

  40. Slide 40: Text of Resolution – Re-election of Philippe Etienne as a Director

    Text of Resolution 2 – Re-election of Philippe Etienne as a Director For personal use only "That Philippe Etienne, having retired as a director of the Company pursuant to Article 13.2 of the Company’s Constitution and, being eligible, having offered himself for re-election, be appointed as a directo

  41. Slide 41: Resolution – Grant of Performance Rights for CEO Amanda Lacaze

    Resolution 3 – Grant of Performance Rights for the benefit of CEO & Managing Director – Amanda Lacaze For personal use only The Company proposes to issue up to 421,363 Performance Rights for the benefit of its CEO and Managing Director, Amanda Lacaze. Each Performance Right is a right to acquire one

  42. Slide 42: Text of Resolution – Grant of Performance Rights for CEO

    Text of Resolution 3 – Grant of Performance Rights for the benefit of CEO & Managing Director – Amanda Lacaze For personal use only “That pursuant to and in accordance with Listing Rule 10.14 of the ASX Listing Rules, and for all other purposes, the Company approves and authorises the Directors of t

  43. Slide 43: Lynas Rare Earths Limited Annual General Meeting

    For personal use only Lynas Rare Earths Limited Annual General Meeting 27 November 2024

  44. Slide 44: Visit us at LynasRareEarths.com

    For personal use only Visit us at LynasRareEarths.com 44

  45. Slide 45: Appendix A: JORC Compliance and Competent Person's Statement

    Appendix A: JORC Compliance and Competent Person’s Statement For personal use only Exploration Results The information in this report is based on, and fairly represents information and supporting documentation jointly prepared by Marcelle Watson, Geology Manager, and Dr. Ganesh Bhat, Principal Resou