Fire River Gold Corp

Fire River Gold — Investor Presentation (June 2012)

17 slides from Fire River Gold's investor presentation, June 2012

  1. Slide 1: Alaska's Newest Gold Producer

    Slide 1: Alaska's Newest Gold Producer

    June, 2012 ALASKA’S NEWEST GOLD PRODUCER TSX.V: FAU OTCQX: FVGCF FSE: FWR

  2. Slide 2: Disclaimer

    Slide 2: Disclaimer

    DISCLAIMER PRESENTATION IS ONLY A SERVICE This presentation is not intended as a solicitation or offering of securities in any jurisdiction and the information contained herein in no way should be construed or interpreted as such. No securities commission or other regulatory authority in Canada or a

  3. Slide 3: Management & Technical Team

    Slide 3: Management & Technical Team

    MANAGEMENT & TECHNICAL TEAM EXECUTIVE MANAGEMENT  R. David Russell, Chairman of the Board, Director  Richard Goodwin, President, Director  Timothy G. Smith, Vice President & COO  Brent Timmons, Vice President Finance, CFO SITE MANAGEMENT  Will Beach, Mine Manager  Jim Gillis, Mill Superintende

  4. Slide 4: Share Structure

    Slide 4: Share Structure

    SHARE STRUCTURE ISSUED & OUTSTANDING …………………………………………………………… 102,442,372 OPTIONS ……………………………………………………………………………… 9,280,000 WARRANTS …………………………………………………………………………… 21,858,616 FULLY DILUTED …………………………………………………………………….…. 133,580,988 MARKET CAP . ………………………………………………………………………...... $17.4 M MAY 24, 2012 FIRE

  5. Slide 5: Key Shareholders

    Slide 5: Key Shareholders

    KEY SHAREHOLDERS  Sprott Asset Management  RBC Asset Management  Mackenzie Financial  P & V Precious Metal Fund EXTENSIVE INTERNATIONAL SHAREHOLDER BASE FIRE RIVER GOLD CORP. 5

  6. Slide 6: Project Location: Tintina Gold Belt

    Slide 6: Project Location: Tintina Gold Belt

    PROJECT LOCATION: TINTINA GOLD BELT FIRE RIVER GOLD CORP. 6

  7. Slide 7: Nixon Fork Mine Claim Outline

    Slide 7: Nixon Fork Mine Claim Outline

    NIXON FORK MINE CLAIM OUTLINE Mineralization occurs along the perimeter of the intrusion which is approximately 16 km. LAND CLAIM EXPANSION POTENTIAL Crystal and Mystery Mines cover only 1km of this perimeter SIZE OF CLAIM: 11,000 acres * TERTIARY INTRUSION FIRE RIVER GOLD CORP. 7

  8. Slide 8: Nixon Fork Mine

    Slide 8: Nixon Fork Mine

    NIXON FORK MINE 8 Dry Stack 1. Housing Facility (85 people) 2. Crystal Mine Portal 3. Gravity and Flotation Mill Fuel Farm 4. CIL Circuit (Mill Expansion) 5. Mine Offices & Mine Dry Facility 6. Power Plant / Heat Recovery / Compressor 7. Maintenance Facility 8. Core Storage & Logging Area 2. 1 Km to

  9. Slide 9: Company Objectives

    Slide 9: Company Objectives

    COMPANY OBJECTIVES DEVELOPMENT  Ramp Nixon Fork Mine up to full production targets SUSTAINABILITY  Replenish annual mine production through ongoing drilling GROWTH  Evaluate strategic partnerships and/or acquisitions FIRE RIVER GOLD CORP. 9

  10. Slide 10: Development / Production

    Slide 10: Development / Production

    DEVELOPMENT / PRODUCTION MONTH JUN JUL AUG SEPT OCT NOV DEC JAN FEB MAR APR TOTAL 2011 2011 2011 2011 2011 2011 2011 2012 2012 2012 2012 Days 30 31 31 30 31 30 31 31 29 31 30 335 Tonnes/Month 680 847 2,278 5,223 3,127 3,562 3,401 2,747 2,056 1,954 12,560 38,435 Tonnes/Day 23 27 73 174 101 119 110 89

  11. Slide 11: 2012 Quarterly Projections

    Slide 11: 2012 Quarterly Projections

    2012 QUARTERLY PROJECTIONS QUARTERS 1ST QUARTER 2ND QUARTER 3RD QUARTER 4TH QUARTER 2012 JAN, FEB, MAR APR, MAY, JUN JUL, AUG, SEPT OCT, NOV, DEC TOTAL Underground Tonnes 6,750 21,310 14,400 15,000 57460 Grade (g/t) 15.6 16.7 15.7 16.7 16.3 Surface Tonnes 3,000 3,000 Grade (g/t) 15.0 15.0 Tailings T

  12. Slide 12: Resource Estimate

    Slide 12: Resource Estimate

    RESOURCE ESTIMATE INDICATED RESOURCES  129,060 tonnes grading 24.9 g/t (0.73 opt) in the mine  92,000 tonnes grading 7.9 g/t (0.23 opt) in the tailings  126,725 ozs of contained GOLD INFERRED RESOURCES  53,980 tonnes grading 28 g/t (0.82 opt) in the mine  48,000 tonnes grading 7.4 g/t (0.21 opt

  13. Slide 13: Current Mining Areas – Crystal Mine

    Slide 13: Current Mining Areas – Crystal Mine

    CURRENT MINING AREAS – CRYSTAL MINE FIRE RIVER GOLD CORP. 13

  14. Slide 14: Future Mining Areas

    Slide 14: Future Mining Areas

    FUTURE MINING AREAS 1. 3550 Zone 2. 3000 Zone 3. 3300 Zone 4. Mystery Mine 5. J5A Zone 6. Southern Cross 7. 3100 Zone FIRE RIVER GOLD CORP. 14

  15. Slide 15: Summary

    Slide 15: Summary

    SUMMARY  Near term target of 40,000 oz per year in 2013  Projected expansion to 50,000 oz per year in 2014  Operating costs estimated at $30 million per year  Capital costs estimated at $2.5 million per year  Cash costs estimated at $842/oz  Financial model sustainable by ongoing resource expa

  16. Slide 16: Why Fire River Gold?

    Slide 16: Why Fire River Gold?

    WHY FIRE RIVER GOLD?  High grade production history  Low political risk (Alaska)  Expansion potential  Facilities in place – low capital requirement  Experienced production team FIRE RIVER GOLD CORP. 16

  17. Slide 17: Contact Information

    Slide 17: Contact Information

    CONTACT INFORMATION 340 – 1200 West 73rd Ave. 6400 South Air Park Place Vancouver, B.C, Canada Suite 1 V6P 6G5 Anchorage, AK 99502 Tel: +1 604 261 0580 Tel: +1 907 243 2220 Fax: +1 604 261 0583 Fax: +1 907 243 2225 E-mail: info@firerivergold.com Mystery Creek Resources Inc. is a wholly owned subsidi