Lundin Mining Corporation · TSX:LUN

Lundin Mining — Q3 2015 Earnings Presentation

28 slides from Lundin Mining's earnings presentation, Oct 29, 2015

  1. Slide 1: Third Quarter 2015 Results

    TSX: LUN OMX: LUMI Third Quarter 2015 Results October 29, 2015

  2. Slide 2: Cautionary Statements

    Cautionary Statements Caution Regarding Forward-Looking Information This presentation contains forward-looking information, including, but not limited to, guidance on estimated annual production and cash costs. This forward-looking information is not based on historical facts, but rather on current

  3. Slide 3: Participants

    Participants Presenters Paul Conibear President & CEO Marie Inkster Senior VP & CFO Questions Peter Quinn Chief Operating Officer Steve Gatley VP Technical Services 3

  4. Slide 4: Q3 2015 Operating Highlights

    Q3 2015 Operating Highlights Strong operating results, company on-track to meet 2015 guidance • Higher throughput at Candelaria supported strong Copper production, cash costs on track to meet full year guidance (Cu) • Copper production at Neves-Corvo benefitted from higher grades, cash costs higher

  5. Slide 5: Q3 2015 Operating Results

    Q3 2015 Operating Results Sales volumes remain healthy across the portfolio 1. Sales results for Candelaria are shown on a 100% basis and are for the period of Lundin Mining's ownership, commencing November 3, 2014. 5

  6. Slide 6: Q3 2015 Revenue Breakdown by Mine and Metal

    Q3 2015 Revenue Breakdown by Mine and Metal • 71% of sales from Candelaria and Eagle • 66% of sales from copper Sales Breakdown by Mine Sales Breakdown by Metal Aguablanca Other Lead Zinkgruvan 3% 4% 3% 10% Gold 7% Zinc 9% Neves-Corvo 16% Candelaria Nickel Copper 54% 11% 66% Eagle 17% 6

  7. Slide 7: 2015 YTD Cash Costs Remain Competitive

    2015 YTD Cash Costs Remain Competitive $4.00 2015 Copper C1 Cash Cost Curve $3.00 Candelaria $1.27/lb $2.00 $/lb $1.00 Neves Corvo Tenke $1.53/lb $0.00 $1.17/lb ($1.00) 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% $15.00 $1.80 2015 Nickel C1 Cash Cost Curve 2015 Zinc C1 Cash Cost Curve $1.50 $10.00 A

  8. Slide 8: Q3 2015 Financial Highlights

    Q3 2015 Financial Highlights Q3/2015 Q3/2014 %Δ Realized Copper (US$/lb)1 2.01 2.96 -32% Realized Nickel (US$/lb)1 3.98 6.89 -42% Realized Zinc (US$/lb)1 0.77 1.07 -28% Revenue ($US M) $353M $167M 112% Operating Earnings ($US M) $94M $43M 119% Net (Loss)/Income ($US M) ($35M) $34M nmf2 (attributable

  9. Slide 9: Normalized Earnings Reconciliation

    Normalized Earnings Reconciliation $ Millions Q3 2015 Q3 2014 Net (loss)/earnings attributable to shareholders ($34.6) $33.7 Foreign exchange ($5.7) ($10.4) Mark to market on securities $0.7 ($4.8) Community Development Agreement (Tierra Amarilla) $7.0 - Realized loss on sale of securities $4.9 Tax

  10. Slide 10: Operating Earnings – Q3 2015 vs. Q3 2014

    Operating Earnings – Q3 2015 vs. Q3 2014 • Operating earnings improved significantly when compared to the third quarter of 2014 due to contributions from Candelaria and Eagle, and foreign exchange • Lower commodity prices vs. last year, resulted in a $58M decrease in operating earnings $160 18.5 58.

  11. Slide 11: Strong Balance Sheet

    Strong Balance Sheet US$ M September 30, 2015 Cash and Cash Equivalents $550 Net Debt1 $454 Revolving Credit Facility (Undrawn) $350 Cash and Cash Equivalents $600 550 507 355 $US M $300 175 $0 Q4/14 Q1/15 Q2/15 Q3/15 • Net debt has improved by $375M from $829M (YE 2014) to $454M (end-Q3/15) • Net d

  12. Slide 12: 2015 Outlook

    2015 Outlook • Production guidance ranges Revised Guidancea (contained tonnes) Tonnes Cash Costsb refined to reflect YTD Candelaria (80%) 138,000 – 141,000 $1.35/lb performance Eagle 23,000 – 24,000 Neves-Corvo 54,000 – 56,000 $1.60/lb Copper • Cost guidance at Neves-Corvo Zinkgruvan 2,000 increased

  13. Slide 13: Operational Overview and Outlook

    Operational Overview and Outlook Candelaria (80%) Eagle (100%) Neves-Corvo (100%) Zinkgruvan (100%) Aguablanca (100%) Tenke Fungurume (24%) 13

  14. Slide 14: Candelaria (Cu/Au/Ag), Chile

    Candelaria (Cu/Au/Ag), Chile Atacama Province, Region III, approximately 20 km south of Copiapó 14

  15. Slide 15: Candelaria Q3 2015 Results and Outlook

    Candelaria Q3 2015 Results and Outlook • Production (100% basis) of 45.2 kt exceeded Location Chile expectations due to higher plant throughput Ownership 80% • Cash costs of $1.44/lb Cu in-line with 2015 Production 138,000-141,000 t Cu expectations Guidance (80%) 2015 Cost Guidance $1.35/lb Cu • Sig

  16. Slide 16: Candelaria New Mine Plan – Improved Production & Costs

    Candelaria New Mine Plan – Improved Production & Costs • 25% increase in LOM copper production (2.4 Mt vs. 1.9 Mt) • Mine life extended to 2032 from 2028 • 5-year plan production profile significantly improved; underground drilling advancing targeted to improve mid-term production profile • Low cost

  17. Slide 17: Eagle Mine (Ni/Cu), Michigan, U.S.A.

    Eagle Mine (Ni/Cu), Michigan, U.S.A. 50 km northwest of Marquette in the Upper Peninsula of Michigan 17

  18. Slide 18: Eagle Q3 2015 Results and Outlook

    Eagle Q3 2015 Results and Outlook • Nickel production of 6.4 kt and copper Location Michigan, USA production of 6.5 kt met expectations Ownership 100% › Higher recoveries and throughput 2015 26,000–27,000 t Ni Production Guidance 23,000–24,000 t Cu • Cash costs of $2.38/lb Ni impacted by 2015 Cost G

  19. Slide 19: Neves-Corvo (Cu/Zn), Portugal

    Neves-Corvo (Cu/Zn), Portugal Situated 220 km southeast of Lisbon 19

  20. Slide 20: Neves-Corvo Q3 2015 Results and Outlook

    Neves-Corvo Q3 2015 Results and Outlook • Copper production of 13.9 kt benefitted Location Portugal from higher grades Ownership 100% 54,000–56,000 t Cu 2015 Production • Zinc production of 14.4 kt impacted by Guidance 59,000–62,000 t Zn 3,000-3,500 t Pb lower grades and recovery rates 2015 Cost Gui

  21. Slide 21: Zinkgruvan (Zn/Pb/Cu), Sweden

    Zinkgruvan (Zn/Pb/Cu), Sweden Situated 200 km southwest of Stockholm 21

  22. Slide 22: Zinkgruvan Q3 2015 Results and Outlook

    Zinkgruvan Q3 2015 Results and Outlook • Zinc production of 18.5 kt and lead Location Sweden production of 8.6 kt Ownership 100% 82,000–85,000 t Zn 2015 Production • Copper production of 0.5 kt reflects lower Guidance 31,000–33,000 t Pb 2,000 t Cu grades and recoveries 2015 Cost Guidance $0.40/lb Zn

  23. Slide 23: Aguablanca (Ni/Cu), Spain

    Aguablanca (Ni/Cu), Spain Situated 80 km north of Seville 23

  24. Slide 24: Aguablanca Q3 2015 Results and Outlook

    Aguablanca Q3 2015 Results and Outlook • Nickel production of 1.7 kt and copper Location Spain production of 1.7 kt impacted by: Ownership 100% 2015 Production 7,100 t Ni › Lower throughput, grades and Guidance 6,100 t Cu recoveries from stockpiled ore 2015 Cost Guidance $2.60/lb Ni • Cash costs of

  25. Slide 25: Tenke Fungurume (Cu/Co), DRC

    Tenke Fungurume (Cu/Co), DRC Situated 175 km northwest of Lubumbashi 25

  26. Slide 26: Tenke Q3 2015 Results and Outlook

    Tenke Q3 2015 Results and Outlook • Copper production (100% basis) of 49.0 Democratic Republic kt impacted by lower mill throughput Location of Congo Ownership 24% › Cobalt production of 4.0 kt 2015 Production Guidance 50,600 t Cu benefitted from higher ore grades (attributable share) 2015 Costs $1.

  27. Slide 27: Well Positioned in Any Market

    Well Positioned in Any Market  High quality, competitively positioned mines  Diversified base metals and geographic asset base  Meaningful production scale  Strong free cash flow and good margins  Conservative balance sheet 27

  28. Slide 28: Questions and Answers

    TSX: LUN OMX: LUMI Questions and Answers