Inpex Corporation · TSE:1605
Inpex — Investor Presentation (September 2024)
6 slides from Inpex's investor presentation, Sep 9, 2024
Slide 1: Expansion Strategy of the LNG Business - Abadi LNG Project
Expansion Strategy of the LNG Business -Abadi LNG Project- Managing Executive Officer, Senior Vice President, Asia Projects Akihiro Watanabe 0 Abadi drilling ship
Slide 2: Abadi LNG Project
Abadi LNG Project Abadi LNG Project Outline Project Schedule Marketing and Financing Project Economics / Anticipated Risks and Mitigation 1
Slide 3: 1. Abadi LNG Project Outline
1. Abadi LNG Project Outline Tanimbar Islands Saumlaki Gas Field Location Block Name Masela Block Indonesia Masela Block Timor-Leste Location Arafura Sea in Indonesia Period Until 2055 Abadi Gas Field INPEX 65% Australia Participating Pertamina 20% Interest Petronas 15% Planned LNG 9.5 MTPA Developm
Slide 4: 2. Project Schedule
2. Project Schedule Timeline: Aiming to start production in the early 2030s FEED Preparation FEED EPC Underway (Front-End Engineering Design) (Engineering, Procurement and Construction) Approx. 2 years Approx. 5 years Production FID Start Onshore G&G Survey Preparatory activities for FEED are now
Slide 5: 3. Marketing and Financing
3. Marketing and Financing Continue marketing and financing activities in parallel with FEED toward FID Conducting marketing activities since 2020 Marketing Executed non-binding MOUs / LOIs with buyers mainly from Southeast Asia (including Indonesia) and East Asia, with their interests exceeding
Slide 6: 4. Project Economics / Anticipated Risks and Mitigation
4. Project Economics / Anticipated Risks and Mitigation Project Economics Target: IRR mid-10% range (based on realistic assumptions) Project Execution Risk Indonesia Country Risk Cost / Schedule (Green Field Project) • Make the most of the insights / • Close communication with • More solid and accur
INPEX — Investor Presentation (September 2024) on 6ix