Inpex Corporation · TSE:1605

Inpex — Investor Presentation (September 2024)

6 slides from Inpex's investor presentation, Sep 9, 2024

  1. Slide 1: Expansion Strategy of the LNG Business - Abadi LNG Project

    Expansion Strategy of the LNG Business -Abadi LNG Project- Managing Executive Officer, Senior Vice President, Asia Projects Akihiro Watanabe 0 Abadi drilling ship

  2. Slide 2: Abadi LNG Project

    Abadi LNG Project Abadi LNG Project Outline Project Schedule Marketing and Financing Project Economics / Anticipated Risks and Mitigation 1

  3. Slide 3: 1. Abadi LNG Project Outline

    1. Abadi LNG Project Outline Tanimbar Islands Saumlaki Gas Field Location Block Name Masela Block Indonesia Masela Block Timor-Leste Location Arafura Sea in Indonesia Period Until 2055 Abadi Gas Field INPEX 65% Australia Participating Pertamina 20% Interest Petronas 15% Planned LNG 9.5 MTPA Developm

  4. Slide 4: 2. Project Schedule

    2. Project Schedule Timeline: Aiming to start production in the early 2030s FEED Preparation FEED EPC Underway (Front-End Engineering Design) (Engineering, Procurement and Construction) Approx. 2 years Approx. 5 years Production FID Start Onshore G&G Survey  Preparatory activities for FEED are now

  5. Slide 5: 3. Marketing and Financing

    3. Marketing and Financing Continue marketing and financing activities in parallel with FEED toward FID  Conducting marketing activities since 2020 Marketing  Executed non-binding MOUs / LOIs with buyers mainly from Southeast Asia (including Indonesia) and East Asia, with their interests exceeding

  6. Slide 6: 4. Project Economics / Anticipated Risks and Mitigation

    4. Project Economics / Anticipated Risks and Mitigation Project Economics Target: IRR mid-10% range (based on realistic assumptions) Project Execution Risk Indonesia Country Risk Cost / Schedule (Green Field Project) • Make the most of the insights / • Close communication with • More solid and accur

INPEX — Investor Presentation (September 2024) on 6ix